2949 S VINEYARD AVE 90016
Certificate Information: 2949 S VINEYARD AVE 90016
- Application / Permit
- 19014-10000-03615
- Plan Check / Job No.
- B19LA13856
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2ND STORY ACCESSORY DWELLING UNIT ABOVE (E) GARAGE
- Permit Issued
- Issued on 7/20/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2019 | MANUEL MONTUFAR |
| Corrections Issued | 8/15/2019 | ARMEN JIVALAGIAN |
| Quality Review Completed | 8/30/2019 | TIEN JEN WANG |
| Building Plans Picked Up | 9/6/2019 | APPLICANT |
| Green Plans Picked Up | 9/6/2019 | APPLICANT |
| Plan Check Approved | 7/8/2021 | MANUEL MONTUFAR |
| Issued | 7/20/2021 | APPLICANT |
| CofO in Progress | 6/3/2022 | STUART CHAPMAN |
| Permit Finaled | 7/13/2022 | DEROLD HAUFF |
| CofO Issued | 7/13/2022 | DEROLD HAUFF |
| Permit Finaled | 7/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/20/2019 | CELINA MORENO |
| Flood clearance | Cleared | 6/17/2020 | BRYAN GATHUKA |
| Construction near power lines | Cleared | 7/1/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/1/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 5/25/2021 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | WALLIE JONG |
| Roof/Waste drainage to street | Cleared | 6/4/2021 | JEANIE LAM |
| Sewer availability | Cleared | 6/4/2021 | JEANIE LAM |
| Green Code | Cleared | 6/28/2021 | MANUEL MONTUFAR |
Contact Information
| Contractor | James Terry R; Lic. No.: 572426-B | 6226 ACACIA ST LOS ANGELES, CA 90056 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 10/1/2021 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/1/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 10/8/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/18/2021 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 11/18/2021 | Approved | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 11/18/2021 | Approved | STUART CHAPMAN |
| Green Building Rough | 11/18/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Rough | 11/18/2021 | Approved | STUART CHAPMAN |
| Insulation | 11/24/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/24/2021 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 12/7/2021 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2021 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 12/7/2021 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 12/7/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/17/2022 | Approved | STUART CHAPMAN |
| Final | 2/17/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 2/17/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/17/2022 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 2/17/2022 | Approved | STUART CHAPMAN |
| Final | 3/18/2022 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 6/3/2022 | Approved | STUART CHAPMAN |
| Final | 6/3/2022 | OK to Issue CofO | STUART CHAPMAN |
| HVAC-Final | 6/3/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 6/3/2022 | Approved | STUART CHAPMAN |