5712 S 3RD AVE 90043
Certificate Information: 5712 S 3RD AVE 90043
- Application / Permit
- 19014-10000-03585
- Plan Check / Job No.
- B19LA13771
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- TO CONVERT (E) GARAGE 273 SF TO AN ADU AND ADD 476 SF TO ADU PER AB 494 and SB 229
- Permit Issued
- Issued on 12/4/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/12/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 7/12/2019 | ARSALAN SHABESTARI |
| Plan Check Approved | 9/24/2019 | ADAM HEGAZI |
| Issued | 12/4/2019 | LADBS |
| CofO in Progress | 2/10/2023 | DONALD CRICHLOW |
| Permit Finaled | 2/14/2023 | DEROLD HAUFF |
| CofO Issued | 2/14/2023 | DEROLD HAUFF |
| Permit Finaled | 2/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/12/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2019 | JEANETTE VONG |
| Low Impact Development | Cleared | 9/20/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/20/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 9/20/2019 | JEANETTE VONG |
| Construction near power lines | Cleared | 9/24/2019 | OSCAR CASTRO |
| Construction within easement | Cleared | 9/24/2019 | OSCAR CASTRO |
Contact Information
| Contractor | Southwest Construction And Home Improvement; Lic. No.: 831043-B | 2729 S ROBERTSON BLVD LOS ANGELES, CA 90034 |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2020 | Partial Approval | RUBEN SALAS |
| PLUMBING-Rough | 2/3/2020 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 2/12/2020 | Approved | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 2/25/2020 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2020 | Partial Inspection | COREY HUPP |
| Deputy Drilled-In Anchors | 3/26/2020 | Conditional Approval | COREY HUPP |
| ELECTRICAL-Rough | 3/31/2020 | Approved | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2020 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 4/7/2020 | Approved | ENRIQUE MIRELES |
| Wood Frame | 4/24/2020 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 5/12/2020 | Partial Approval | SABAS ALONSO |
| HVAC-Rough | 6/17/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 6/19/2020 | Approved | SABAS ALONSO |
| Insulation | 6/19/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/29/2020 | Approved | COREY HUPP |
| Shower Pan | 9/28/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 1/4/2022 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/7/2022 | Partial Approval | HORACE FULTZ |
| BUILDING-Rough-Frame | 12/14/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/14/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 12/14/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 12/14/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 12/14/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 12/14/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 12/14/2022 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 1/18/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 1/18/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/18/2023 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 1/18/2023 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 1/18/2023 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/18/2023 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 1/18/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 1/18/2023 | Approved | ANTHONY EGSON |
| Final | 2/2/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 2/2/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 2/10/2023 | Approved | DONALD CRICHLOW |
| Final | 2/10/2023 | OK to Issue CofO | DONALD CRICHLOW |
| HVAC-Final | 2/10/2023 | Approved | DONALD CRICHLOW |
| Service/Power Release | 2/10/2023 | Approved | DONALD CRICHLOW |