116-118 E 116TH ST 90061
Certificate Information: 116-118 E 116TH ST 90061
- Application / Permit
- 19014-10000-03536
- Plan Check / Job No.
- B19LA13617
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSED 2ND STORY ADDITION (24'-0" X 68'-0") TO (E) 1-STORY DUPLEX
- Permit Issued
- Issued on 11/15/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2019 | APPLICANT |
| Green Plans Picked Up | 7/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 7/29/2019 | FARSHAD ALIMOHAMADI |
| Quality Review Completed | 8/18/2019 | YOUNG KIM |
| Building Plans Picked Up | 8/22/2019 | APPLICANT |
| Plan Check Approved | 11/13/2019 | FARSHAD ALIMOHAMADI |
| Issued | 11/15/2019 | LADBS |
| CofO in Progress | 12/9/2020 | ANSON MAGLASANG |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
| CofO Issued | 12/10/2020 | DEROLD HAUFF |
| Permit Finaled | 12/10/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/27/2019 | ELENA LOPEZ |
| Sewer availability | Cleared | 9/27/2019 | ELENA LOPEZ |
| Low Impact Development | Cleared | 10/18/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 10/18/2019 | CELINA MORENO |
| Green Code | Cleared | 10/22/2019 | VIVIAN LAO |
| ZI | Cleared | 11/5/2019 | RICHARD REASER |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2020 | Not Ready for Inspection | WILLIAM ROSE |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2020 | Partial Approval | WILLIAM ROSE |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2020 | Partial Approval | BRIAN CHRISTIAN |
| Wood Frame | 3/26/2020 | Partial Approval | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 4/20/2020 | Approved | BRIAN CHRISTIAN |
| HVAC-Rough | 4/20/2020 | Partial Approval | BRIAN CHRISTIAN |
| Insulation | 4/20/2020 | Partial Approval | BRIAN CHRISTIAN |
| PLUMBING-Rough | 4/20/2020 | Approved | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Approved | BRIAN CHRISTIAN |
| HVAC-Rough | 4/27/2020 | Approved | BRIAN CHRISTIAN |
| Insulation | 4/27/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 5/5/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 5/5/2020 | Approved | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 8/26/2020 | Approved | EUGENE CASSIDY |
| Final | 8/26/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/26/2020 | Approved | EUGENE CASSIDY |
| Green Building Final | 8/26/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 8/26/2020 | Approved | EUGENE CASSIDY |
| MERV13>=Final | 8/26/2020 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Rough | 8/26/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/26/2020 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 8/26/2020 | Approved | EUGENE CASSIDY |
| Final | 9/2/2020 | Corrections Issued | EUGENE CASSIDY |
| MERV13>=Final | 9/2/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/24/2020 | Approved | EUGENE CASSIDY |
| Final | 11/24/2020 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 11/24/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 11/24/2020 | Approved | EUGENE CASSIDY |
| Service/Power Release | 11/24/2020 | Approved | EUGENE CASSIDY |