116-118 E 116TH ST 90061

Certificate Information: 116-118 E 116TH ST 90061

Application / Permit
19014-10000-03536
Plan Check / Job No.
B19LA13617
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
PROPOSED 2ND STORY ADDITION (24'-0" X 68'-0") TO (E) 1-STORY DUPLEX
Permit Issued
Issued on 11/15/2019
Issuing Office
Metro
Current Status
CofO Issued on 12/10/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2019 APPLICANT
Green Plans Picked Up 7/19/2019 APPLICANT
Assigned to Plan Check Engineer 7/22/2019 FARSHAD ALIMOHAMADI
Corrections Issued 7/29/2019 FARSHAD ALIMOHAMADI
Quality Review Completed 8/18/2019 YOUNG KIM
Building Plans Picked Up 8/22/2019 APPLICANT
Plan Check Approved 11/13/2019 FARSHAD ALIMOHAMADI
Issued 11/15/2019 LADBS
CofO in Progress 12/9/2020 ANSON MAGLASANG
Permit Finaled 12/10/2020 DEROLD HAUFF
CofO Issued 12/10/2020 DEROLD HAUFF
Permit Finaled 12/10/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/27/2019 ELENA LOPEZ
Sewer availability Cleared 9/27/2019 ELENA LOPEZ
Low Impact Development Cleared 10/18/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 10/18/2019 CELINA MORENO
Green Code Cleared 10/22/2019 VIVIAN LAO
ZI Cleared 11/5/2019 RICHARD REASER

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/24/2020 Not Ready for Inspection WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 3/9/2020 Partial Approval WILLIAM ROSE
Floor/Roof Diaphrgm/Shear Wall 3/26/2020 Partial Approval BRIAN CHRISTIAN
Wood Frame 3/26/2020 Partial Approval BRIAN CHRISTIAN
ELECTRICAL-Rough 4/20/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 4/20/2020 Partial Approval BRIAN CHRISTIAN
Insulation 4/20/2020 Partial Approval BRIAN CHRISTIAN
PLUMBING-Rough 4/20/2020 Approved BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Approved BRIAN CHRISTIAN
HVAC-Rough 4/27/2020 Approved BRIAN CHRISTIAN
Insulation 4/27/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 5/5/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 5/5/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 8/26/2020 Approved EUGENE CASSIDY
Final 8/26/2020 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 8/26/2020 Approved EUGENE CASSIDY
Green Building Final 8/26/2020 Approved EUGENE CASSIDY
Green Building Rough 8/26/2020 Approved EUGENE CASSIDY
MERV13>=Final 8/26/2020 Corrections Issued EUGENE CASSIDY
MERV13>=Rough 8/26/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/26/2020 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 8/26/2020 Approved EUGENE CASSIDY
Final 9/2/2020 Corrections Issued EUGENE CASSIDY
MERV13>=Final 9/2/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 11/24/2020 Approved EUGENE CASSIDY
Final 11/24/2020 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 11/24/2020 Approved EUGENE CASSIDY
PLUMBING-Final 11/24/2020 Approved EUGENE CASSIDY
Service/Power Release 11/24/2020 Approved EUGENE CASSIDY