Permit Issued
Issued on 3/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2019 APPLICANT
Assigned to Plan Check Engineer 8/1/2019 SINA KHOSRAVI
Corrections Issued 8/7/2019 SINA KHOSRAVI
Green Plans Picked Up 8/16/2019 APPLICANT
Quality Review Completed 8/25/2019 YOUNG KIM
Building Plans Picked Up 8/28/2019 APPLICANT
Applicant returned to address corrections 2/11/2020 SINA KHOSRAVI
Plan Check Approved 2/19/2020 SINA KHOSRAVI
Issued 3/13/2020 LADBS
CofO in Progress 9/28/2021 EVAN COOPER
Permit Finaled 10/16/2021 DANIEL ORRANTE
CofO Issued 10/16/2021 DANIEL ORRANTE
Permit Finaled 10/16/2021 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/27/2019 PATRICK MISCHLICH
Low Impact Development Cleared 9/27/2019 MITESH PATEL
Address approval Cleared 9/30/2019 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 9/30/2019 ANTHONY MAINEZ
Sewer availability Cleared 9/30/2019 ANTHONY MAINEZ
Green Code Cleared 10/7/2019 NEGAR NEJAD
Construction near power lines Cleared 2/3/2020 RIDWAN HARDY
Roof/Waste drainage to street Cleared 2/4/2020 ANTHONY MAINEZ

Contact Information

Contractor Lannen Construction Inc; Lic. No.: 811038-B 5841 AIRDROME ST      LOS ANGELES, CA 90019
Engineer Behshid,, Farshid; Lic. No.: S4585 4647 ENCINAS DR      LA CANADA, CA 91011
Engineer Mahn,, Jonathan Edward; Lic. No.: C60293 12848 FOOTHILL BLVD      SYLMAR, CA 91381

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/24/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 8/5/2020 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 8/20/2020 Not Ready for Inspection EVAN COOPER
METHANE-Barrier 8/20/2020 Approved EVAN COOPER
METHANE-Subgrade 8/20/2020 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 9/3/2020 Partial Approval EVAN COOPER
PLUMBING-Rough 9/24/2020 Partial Approval EVAN COOPER
Underground Mechanical 9/24/2020 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 10/1/2020 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 10/1/2020 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 10/2/2020 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 10/14/2020 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Partial Approval EVAN COOPER
Footing/Foundation/Slab 11/17/2020 Approved EVAN COOPER
HVAC-Rough 11/17/2020 Corrections Issued EVAN COOPER
PLUMBING-Rough 11/17/2020 Approved EVAN COOPER
Wood Frame 11/17/2020 Corrections Issued EVAN COOPER
HVAC-Rough 12/15/2020 Approved EVAN COOPER
Wood Frame 12/15/2020 Partial Approval EVAN COOPER
Interior/Exterior Lathing 2/25/2021 Not Ready for Inspection EVAN COOPER
Insulation 3/10/2021 Approved EVAN COOPER
Interior/Exterior Lathing 3/10/2021 Partial Approval EVAN COOPER
Drywall Nailing 3/19/2021 Approved EVAN COOPER
Green Building Rough 3/19/2021 Approved EVAN COOPER
Shower Pan 3/19/2021 Approved EVAN COOPER
Special/Order Compliance 3/19/2021 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 5/7/2021 Approved RYAN BARNES
ELECTRICAL-Final 8/31/2021 Corrections Issued EVAN COOPER
HVAC-Final 8/31/2021 Corrections Issued EVAN COOPER
PLUMBING-Final 8/31/2021 Corrections Issued EVAN COOPER
BUILDING-Rough-Frame 9/20/2021 Approved EVAN COOPER
ELECTRICAL-Final 9/20/2021 Approved EVAN COOPER
Final 9/20/2021 Corrections Issued EVAN COOPER
Green Building Final 9/20/2021 Approved EVAN COOPER
HVAC-Final 9/20/2021 Approved EVAN COOPER
METHANE-Final 9/20/2021 Approved EVAN COOPER
METHANE-Rough 9/20/2021 Approved EVAN COOPER
PLUMBING-Final 9/20/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 9/20/2021 SGSOV Approved EVAN COOPER
Smoke Detectors 9/20/2021 Approved EVAN COOPER
Final 9/27/2021 Conditional Approval EVAN COOPER
Service/Power Release 9/27/2021 Approved EVAN COOPER