1126 S RIDGELEY DR 90019
Certificate Information: 1126 S RIDGELEY DR 90019
- Application / Permit
- 19014-10000-03517
- Plan Check / Job No.
- B19LA13541
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL AND ( 10'-0" X 13'-3") ADDITION TO THE REAR OF EXISTING SFD "COMPLY WITH DEPARTMENT ORDER effective date 03/06/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 849358.
- Permit Issued
- Issued on 11/19/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 2/8/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 7/5/2019 | ARSALAN SHABESTARI |
| Plan Check Approved | 11/14/2019 | FARSHAD ALIMOHAMADI |
| Issued | 11/19/2019 | LADBS |
| Building Plans Picked Up | 7/1/2020 | APPLICANT |
| CofO in Progress | 1/20/2022 | PIERRE VEGA |
| CofO in Progress | 1/20/2022 | PIERRE VEGA |
| CofO Issued | 2/8/2022 | DANIEL SANCHEZ |
| Permit Finaled | 2/8/2022 | DANIEL SANCHEZ |
Permit Application Clearance Information
| CPC | Cleared | 7/5/2019 | SOPHIE GABEL-SCHEINBAU |
| CPC | Cleared | 7/5/2019 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 7/5/2019 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 7/5/2019 | JEANIE LAM |
| Sewer availability | Cleared | 7/5/2019 | ERIK BEASLEY |
| ZA Case | Cleared | 7/5/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 7/5/2019 | SOPHIE GABEL-SCHEINBAU |
| HPOZ | Cleared | 11/8/2019 | CHRISTINA PARK |
Contact Information
| Contractor | Anchor Builders Inc; Lic. No.: 1029392-B | 2911 W CUBBON STREET SANTA ANA, CA 92704 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN FRANCHINI, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2019 | Not Ready for Inspection | BENEDICT MATHIAS |
| METHANE-Barrier | 12/16/2019 | Not Ready for Inspection | BENEDICT MATHIAS |
| METHANE-Subgrade | 12/16/2019 | Not Ready for Inspection | BENEDICT MATHIAS |
| Footing/Foundation/Slab | 2/10/2020 | Approved | BENEDICT MATHIAS |
| METHANE-Barrier | 2/10/2020 | Approved | BENEDICT MATHIAS |
| METHANE-Subgrade | 2/10/2020 | Approved | BENEDICT MATHIAS |
| BUILDING-Rough-Frame | 3/10/2020 | Corrections Issued | EDDY ARDESSI |
| ELECTRICAL-Rough | 3/10/2020 | Corrections Issued | EDDY ARDESSI |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2020 | Approved | EDDY ARDESSI |
| Gas Test | 3/10/2020 | Partial Approval | EDDY ARDESSI |
| HVAC-Rough | 3/10/2020 | Corrections Issued | EDDY ARDESSI |
| PLUMBING-Rough | 3/10/2020 | Corrections Issued | EDDY ARDESSI |
| Shower Pan | 3/10/2020 | Approved | EDDY ARDESSI |
| BUILDING-Rough-Frame | 4/16/2020 | Not Ready for Inspection | GORDON ZUBER |
| ELECTRICAL-Rough | 4/16/2020 | Not Ready for Inspection | GORDON ZUBER |
| Green Building Rough | 4/16/2020 | Not Ready for Inspection | GORDON ZUBER |
| METHANE-Rough | 4/16/2020 | Not Ready for Inspection | GORDON ZUBER |
| Underground Mechanical | 4/16/2020 | Not Ready for Inspection | GORDON ZUBER |
| Insulation | 7/10/2020 | Not Ready for Inspection | GORDON ZUBER |
| Interior/Exterior Lathing | 7/10/2020 | Not Ready for Inspection | GORDON ZUBER |
| BUILDING-Rough-Frame | 12/29/2020 | Approved | EDDY ARDESSI |
| Final | 12/29/2020 | Corrections Issued | EDDY ARDESSI |
| Green Building Final | 12/29/2020 | Approved | EDDY ARDESSI |
| Green Building Rough | 12/29/2020 | Approved | EDDY ARDESSI |
| METHANE-Final | 12/29/2020 | Approved | EDDY ARDESSI |
| METHANE-Rough | 12/29/2020 | Approved | EDDY ARDESSI |
| SGSOV-Seismic Gas S/O Valve | 12/29/2020 | SGSOV Approved | EDDY ARDESSI |
| Smoke Detectors | 12/29/2020 | Approved | EDDY ARDESSI |
| Final | 1/20/2022 | OK to Issue CofO | PIERRE VEGA |