1558 W 215TH ST 90501

Certificate Information: 1558 W 215TH ST 90501

Application / Permit
19014-10000-03495
Plan Check / Job No.
B19LA13444
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
18'8"X18'4" ADDITION TO SINGLE FAMILY DWELLING AT FRONT OF LOT TO CONNECT TO REC ROOM AND CONVERT REC RM TO MASTER SUITE. (2 of 2). ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 6/4/2021
Issuing Office
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2019 APPLICANT
Green Plans Picked Up 7/10/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 GEORGE ALVAREZ
Corrections Issued 7/25/2019 GEORGE ALVAREZ
Quality Review Completed 8/3/2019 STANLEY RAAP
Applicant returned to address corrections 11/24/2020 GEORGE ALVAREZ
Plan Check Approved 4/20/2021 GEORGE ALVAREZ
Issued 6/4/2021 APPLICANT
Building Plans Picked Up 6/17/2021 APPLICANT
CofO in Progress 7/7/2023 EUGENE CASSIDY
CofO Issued 8/22/2023 ANSON MAGLASANG
Permit Finaled 8/22/2023 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/13/2019 ERIK BEASLEY
Roof/Waste drainage to street Cleared 11/13/2019 ERIK BEASLEY
Sewer availability Cleared 11/13/2019 ERIK BEASLEY
Green Code Cleared 11/27/2019 KHEDER ALRAZAA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/5/2021 Partial Approval CRAIG DAVIS
BUILDING-Rough-Frame 11/1/2021 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 11/1/2021 Not Ready for Inspection ANSON MAGLASANG
Green Building Rough 11/1/2021 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 11/1/2021 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 11/4/2021 Approved JOHN KLARIN
PLUMBING-Rough 11/4/2021 Approved JOHN KLARIN
Pre-Inspection 11/4/2021 Approved JOHN KLARIN
Insulation 11/16/2021 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 11/16/2021 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 11/23/2021 Conditional Approval JOHN KLARIN
Insulation 11/30/2021 Approved JOHN KLARIN
Drywall Nailing 12/13/2021 Approved EUGENE CASSIDY
Shower Pan 12/20/2021 Approved JOHN KLARIN
Pre-Inspection 9/9/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 2/9/2023 Approved EUGENE CASSIDY
Final 2/9/2023 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 2/9/2023 Approved EUGENE CASSIDY
Green Building Final 2/9/2023 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 2/9/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 2/9/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 7/7/2023 Approved EUGENE CASSIDY
Final 7/7/2023 OK to Issue CofO EUGENE CASSIDY
Green Building Final 7/7/2023 Approved EUGENE CASSIDY
HVAC-Final 7/7/2023 Approved EUGENE CASSIDY
PLUMBING-Final 7/7/2023 Approved EUGENE CASSIDY
Smoke Detectors 7/7/2023 Approved EUGENE CASSIDY