1560 W 215TH ST 90501
Certificate Information: 1560 W 215TH ST 90501
- Application / Permit
- 19014-10000-03494
- Plan Check / Job No.
- B19LA13444
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT W/19'X13'-11" ADDITION AT SIDE PER AB 494 AND SB 229. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS
- Permit Issued
- Issued on 6/4/2021
- Issuing Office
- Current Status
- CofO Issued on 8/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2019 | APPLICANT |
| Green Plans Picked Up | 7/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | GEORGE ALVAREZ |
| Corrections Issued | 7/25/2019 | GEORGE ALVAREZ |
| Quality Review Completed | 8/3/2019 | STANLEY RAAP |
| Applicant returned to address corrections | 11/24/2020 | GEORGE ALVAREZ |
| Plan Check Approved | 4/20/2021 | GEORGE ALVAREZ |
| Issued | 6/4/2021 | APPLICANT |
| Building Plans Picked Up | 6/17/2021 | APPLICANT |
| CofO in Progress | 7/7/2023 | EUGENE CASSIDY |
| Permit Finaled | 8/22/2023 | ANSON MAGLASANG |
| CofO Issued | 8/22/2023 | ANSON MAGLASANG |
| Permit Finaled | 8/22/2023 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 11/13/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 11/13/2019 | ERIK BEASLEY |
| Miscellaneous | Cleared | 11/13/2019 | RICHARD REASER |
| Roof/Waste drainage to street | Cleared | 11/13/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 11/13/2019 | ERIK BEASLEY |
| Green Code | Cleared | 11/27/2019 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/27/2021 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 7/30/2021 | Partial Approval | JOHN KLARIN |
| Deputy Drilled-In Anchors | 8/5/2021 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 8/5/2021 | Corrections Issued | JOHN KLARIN |
| Footing/Foundation/Slab | 8/9/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 10/22/2021 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 10/22/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 10/22/2021 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 10/22/2021 | Approved | JOHN KLARIN |
| Insulation | 10/29/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 10/29/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/16/2021 | Corrections Issued | EUGENE CASSIDY |
| Drywall Nailing | 11/23/2021 | Corrections Issued | JOHN KLARIN |
| Drywall Nailing | 12/3/2021 | Approved | JOHN KLARIN |
| Gas Test | 12/3/2021 | Approved | JOHN KLARIN |
| Smoke Detectors | 12/13/2021 | Corrections Issued | EUGENE CASSIDY |
| Pre-Inspection | 4/5/2022 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 6/29/2022 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/11/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 10/11/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/11/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 10/11/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 11/22/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 11/22/2022 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 11/22/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 1/18/2023 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 2/3/2023 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/18/2023 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/31/2023 | Approved | EUGENE CASSIDY |
| Final | 5/31/2023 | Corrections Issued | EUGENE CASSIDY |
| Smoke Detectors | 5/31/2023 | Approved | EUGENE CASSIDY |
| Final | 7/7/2023 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 7/7/2023 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 7/7/2023 | Approved | EUGENE CASSIDY |