1560 W 215TH ST 90501

Certificate Information: 1560 W 215TH ST 90501

Application / Permit
19014-10000-03494
Plan Check / Job No.
B19LA13444
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT W/19'X13'-11" ADDITION AT SIDE PER AB 494 AND SB 229. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 6/4/2021
Issuing Office
Current Status
CofO Issued on 8/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/1/2019 APPLICANT
Green Plans Picked Up 7/10/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 GEORGE ALVAREZ
Corrections Issued 7/25/2019 GEORGE ALVAREZ
Quality Review Completed 8/3/2019 STANLEY RAAP
Applicant returned to address corrections 11/24/2020 GEORGE ALVAREZ
Plan Check Approved 4/20/2021 GEORGE ALVAREZ
Issued 6/4/2021 APPLICANT
Building Plans Picked Up 6/17/2021 APPLICANT
CofO in Progress 7/7/2023 EUGENE CASSIDY
Permit Finaled 8/22/2023 ANSON MAGLASANG
CofO Issued 8/22/2023 ANSON MAGLASANG
Permit Finaled 8/22/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 11/13/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 11/13/2019 ERIK BEASLEY
Miscellaneous Cleared 11/13/2019 RICHARD REASER
Roof/Waste drainage to street Cleared 11/13/2019 ERIK BEASLEY
Sewer availability Cleared 11/13/2019 ERIK BEASLEY
Green Code Cleared 11/27/2019 KHEDER ALRAZAA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/27/2021 Corrections Issued JOHN KLARIN
PLUMBING-Rough 7/30/2021 Partial Approval JOHN KLARIN
Deputy Drilled-In Anchors 8/5/2021 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 8/5/2021 Corrections Issued JOHN KLARIN
Footing/Foundation/Slab 8/9/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 10/22/2021 Approved JOHN KLARIN
ELECTRICAL-Rough 10/22/2021 Approved JOHN KLARIN
Green Building Rough 10/22/2021 Approved JOHN KLARIN
PLUMBING-Rough 10/22/2021 Approved JOHN KLARIN
Insulation 10/29/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 10/29/2021 Approved JOHN KLARIN
Drywall Nailing 11/16/2021 Corrections Issued EUGENE CASSIDY
Drywall Nailing 11/23/2021 Corrections Issued JOHN KLARIN
Drywall Nailing 12/3/2021 Approved JOHN KLARIN
Gas Test 12/3/2021 Approved JOHN KLARIN
Smoke Detectors 12/13/2021 Corrections Issued EUGENE CASSIDY
Pre-Inspection 4/5/2022 Corrections Issued EUGENE CASSIDY
Service/Power Release 6/29/2022 Corrections Issued EUGENE CASSIDY
Final 10/11/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 10/11/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 10/11/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 10/11/2022 Not Ready for Inspection EUGENE CASSIDY
Final 11/22/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 11/22/2022 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 11/22/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 1/18/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 2/3/2023 Partial Approval EUGENE CASSIDY
ELECTRICAL-Final 4/18/2023 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 5/31/2023 Approved EUGENE CASSIDY
Final 5/31/2023 Corrections Issued EUGENE CASSIDY
Smoke Detectors 5/31/2023 Approved EUGENE CASSIDY
Final 7/7/2023 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 7/7/2023 Approved EUGENE CASSIDY
PLUMBING-Final 7/7/2023 Approved EUGENE CASSIDY