341 E 106TH ST 90003
Certificate Information: 341 E 106TH ST 90003
- Application / Permit
- 19014-10000-03485
- Plan Check / Job No.
- B19LA13410
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD NEW ACCESSORY DWELLING UNIT TO EXISTING DETACHED GARAGE PER AB 494 and SB 229
- Permit Issued
- Issued on 3/10/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 6/28/2019 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 2/7/2020 | SINA KHOSRAVI |
| Plan Check Approved | 2/7/2020 | GEORGE ALVAREZ |
| Issued | 3/10/2020 | LADBS |
| CofO in Progress | 8/12/2021 | EUGENE CASSIDY |
| Permit Finaled | 3/29/2023 | DANIEL ORRANTE |
| CofO Issued | 3/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2019 | JEANETTE VONG |
| Community Plan Implem. Overlay | Cleared | 2/7/2020 | RICHARD REASER |
| Construction near power lines | Cleared | 2/7/2020 | TORI CHEN |
| Construction within easement | Cleared | 2/7/2020 | TORI CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2020 | JEANETTE VONG |
| Low Impact Development | Cleared | 2/7/2020 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 2/7/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/7/2020 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/15/2020 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 4/17/2020 | Approved | BRIAN CHRISTIAN |
| Footing/Foundation/Slab | 4/21/2020 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2020 | Partial Approval | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 5/22/2020 | Approved | EUGENE CASSIDY |
| Gas Test | 5/22/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/22/2020 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 5/22/2020 | Partial Approval | EUGENE CASSIDY |
| HVAC-Rough | 5/27/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/27/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/27/2020 | Approved | EUGENE CASSIDY |
| Wood Frame | 5/27/2020 | Approved | EUGENE CASSIDY |
| Insulation | 5/29/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 6/2/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 6/2/2020 | Partial Approval | BRIAN CHRISTIAN |
| Sewer | 6/18/2020 | Approved | BRIAN CHRISTIAN |
| Underground Mechanical | 6/18/2020 | Approved | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 8/3/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 8/3/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Final | 8/3/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 8/3/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/3/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 8/3/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/7/2020 | Approved | EUGENE CASSIDY |
| Final | 8/7/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 8/7/2020 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/7/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Final | 8/14/2020 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 8/14/2020 | SGSOV Approved | EUGENE CASSIDY |
| Final | 9/18/2020 | Corrections Issued | DAVID FEILER |
| Final | 9/24/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/2/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/10/2021 | Approved | EUGENE CASSIDY |
| Final | 8/10/2021 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 8/10/2021 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 8/10/2021 | Approved | EUGENE CASSIDY |