341 E 106TH ST 90003

Certificate Information: 341 E 106TH ST 90003

Application / Permit
19014-10000-03485
Plan Check / Job No.
B19LA13410
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD NEW ACCESSORY DWELLING UNIT TO EXISTING DETACHED GARAGE PER AB 494 and SB 229
Permit Issued
Issued on 3/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2019 APPLICANT
Assigned to Plan Check Engineer 6/28/2019 ARSALAN SHABESTARI
Corrections Issued 6/28/2019 ARSALAN SHABESTARI
Applicant returned to address corrections 2/7/2020 SINA KHOSRAVI
Plan Check Approved 2/7/2020 GEORGE ALVAREZ
Issued 3/10/2020 LADBS
CofO in Progress 8/12/2021 EUGENE CASSIDY
Permit Finaled 3/29/2023 DANIEL ORRANTE
CofO Issued 3/29/2023 DANIEL ORRANTE
Permit Finaled 3/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 6/28/2019 JEANETTE VONG
Community Plan Implem. Overlay Cleared 2/7/2020 RICHARD REASER
Construction near power lines Cleared 2/7/2020 TORI CHEN
Construction within easement Cleared 2/7/2020 TORI CHEN
Eng Process Fee Ord 176,300 Cleared 2/7/2020 JEANETTE VONG
Low Impact Development Cleared 2/7/2020 AMMAR ELTAWIL
Roof/Waste drainage to street Cleared 2/7/2020 JEANETTE VONG
Sewer availability Cleared 2/7/2020 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/15/2020 Corrections Issued EUGENE CASSIDY
Underground Mechanical 4/17/2020 Approved BRIAN CHRISTIAN
Footing/Foundation/Slab 4/21/2020 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 5/7/2020 Partial Approval BRIAN CHRISTIAN
ELECTRICAL-Rough 5/22/2020 Approved EUGENE CASSIDY
Gas Test 5/22/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 5/22/2020 Corrections Issued EUGENE CASSIDY
Wood Frame 5/22/2020 Partial Approval EUGENE CASSIDY
HVAC-Rough 5/27/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/27/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 5/27/2020 Approved EUGENE CASSIDY
Wood Frame 5/27/2020 Approved EUGENE CASSIDY
Insulation 5/29/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 6/2/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 6/2/2020 Partial Approval BRIAN CHRISTIAN
Sewer 6/18/2020 Approved BRIAN CHRISTIAN
Underground Mechanical 6/18/2020 Approved BRIAN CHRISTIAN
BUILDING-Rough-Frame 8/3/2020 Not Ready for Inspection EUGENE CASSIDY
Final 8/3/2020 Not Ready for Inspection EUGENE CASSIDY
Green Building Final 8/3/2020 Corrections Issued EUGENE CASSIDY
Green Building Rough 8/3/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/3/2020 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 8/3/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 8/7/2020 Approved EUGENE CASSIDY
Final 8/7/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 8/7/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/7/2020 SGSOV Not Ready EUGENE CASSIDY
Final 8/14/2020 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 8/14/2020 SGSOV Approved EUGENE CASSIDY
Final 9/18/2020 Corrections Issued DAVID FEILER
Final 9/24/2020 Corrections Issued EUGENE CASSIDY
Final 10/2/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 8/10/2021 Approved EUGENE CASSIDY
Final 8/10/2021 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 8/10/2021 Approved EUGENE CASSIDY
PLUMBING-Final 8/10/2021 Approved EUGENE CASSIDY