745 E SUNSET AVE 90291
Certificate Information: 745 E SUNSET AVE 90291
- Application / Permit
- 19014-10000-03483
- Plan Check / Job No.
- B19LA13406
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST FLOOR ADDITION (30FT X 30FT) AND ADD 2ND (108FT X 32FT) STORY TO (E) ONE STORY SINGLE FAMILY. see comment.
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2019 | TSE MING HUANG |
| Corrections Issued | 7/26/2019 | TSE MING HUANG |
| Quality Review Completed | 8/3/2019 | STANLEY RAAP |
| Green Plans Picked Up | 9/10/2020 | APPLICANT |
| Plan Check Approved | 9/28/2021 | TSE MING HUANG |
| Issued | 3/3/2022 | APPLICANT |
| Building Plans Picked Up | 8/24/2023 | APPLICANT |
| CofO in Progress | 5/2/2025 | JESUS RODRIGUEZ |
| Permit Finaled | 5/6/2025 | RICHARD STEINBACH |
| CofO Issued | 5/6/2025 | RICHARD STEINBACH |
| Permit Finaled | 5/6/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/19/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 8/19/2019 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 8/19/2019 | LEE GUILBEAUX |
| Frnt yard landscape/Water mgmt | Cleared | 6/19/2020 | TERRI OSBORNE |
| Hydrant and Access approval | Cleared | 7/6/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 8/25/2020 | ROBIN YAMADA |
| Green Code | Cleared | 9/9/2020 | TSE MING HUANG |
| Permit | Cleared | 10/23/2020 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 10/23/2020 | HISASHI KOBAYAKAWA |
| Coastal Zone | Cleared | 10/27/2020 | JASON CHAN |
| Specific Plan | Cleared | 10/27/2020 | JASON CHAN |
Contact Information
| Architect | Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 | 17116 RAYMER STREET NORTHRIDGE, CA 91325 |
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/7/2023 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Drilled-In Anchors | 9/22/2023 | Approved | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 9/22/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 9/22/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Conditional Approval | TEMISTOCLES CAAL |
| PLUMBING-Rough | 3/28/2024 | Corrections Issued | HERBERT GIRON |
| Gas Test | 4/1/2024 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 4/1/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2024 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Partial Approval | HERBERT GIRON |
| HVAC-Rough | 5/14/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2024 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 5/17/2024 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 5/21/2024 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 5/23/2024 | Approved | HERBERT GIRON |
| Deputy Drilled-In Anchors | 5/31/2024 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2024 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 7/15/2024 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/16/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | HERBERT GIRON |
| Green Building Rough | 8/23/2024 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 8/23/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/10/2024 | Approved | HERBERT GIRON |
| Insulation | 9/10/2024 | Approved | HERBERT GIRON |
| Shower Pan | 9/19/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 9/24/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 9/24/2024 | Approved | HERBERT GIRON |
| Gas Test | 2/20/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 4/3/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 4/3/2025 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/3/2025 | Corrections Issued | TEMISTOCLES CAAL |
| Service/Power Release | 4/3/2025 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 4/7/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 4/7/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 4/7/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Final | 4/8/2025 | Approved | JESUS RODRIGUEZ |
| Final | 4/29/2025 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 4/29/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 4/29/2025 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 4/29/2025 | Approved | JESUS RODRIGUEZ |