745 E SUNSET AVE 90291

Certificate Information: 745 E SUNSET AVE 90291

Application / Permit
19014-10000-03483
Plan Check / Job No.
B19LA13406
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST FLOOR ADDITION (30FT X 30FT) AND ADD 2ND (108FT X 32FT) STORY TO (E) ONE STORY SINGLE FAMILY. see comment.
Permit Issued
Issued on 3/3/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/28/2019 APPLICANT
Assigned to Plan Check Engineer 7/17/2019 TSE MING HUANG
Corrections Issued 7/26/2019 TSE MING HUANG
Quality Review Completed 8/3/2019 STANLEY RAAP
Green Plans Picked Up 9/10/2020 APPLICANT
Plan Check Approved 9/28/2021 TSE MING HUANG
Issued 3/3/2022 APPLICANT
Building Plans Picked Up 8/24/2023 APPLICANT
CofO in Progress 5/2/2025 JESUS RODRIGUEZ
Permit Finaled 5/6/2025 RICHARD STEINBACH
CofO Issued 5/6/2025 RICHARD STEINBACH
Permit Finaled 5/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/19/2019 LEE GUILBEAUX
Sewer availability Cleared 8/19/2019 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/19/2019 LEE GUILBEAUX
Frnt yard landscape/Water mgmt Cleared 6/19/2020 TERRI OSBORNE
Hydrant and Access approval Cleared 7/6/2020 MATTHEW CRAIG
Low Impact Development Cleared 8/25/2020 ROBIN YAMADA
Green Code Cleared 9/9/2020 TSE MING HUANG
Permit Cleared 10/23/2020 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 10/23/2020 HISASHI KOBAYAKAWA
Coastal Zone Cleared 10/27/2020 JASON CHAN
Specific Plan Cleared 10/27/2020 JASON CHAN

Contact Information

Architect Santiago-Dieppa,, Rafael Angel; Lic. No.: C10361 17116 RAYMER STREET      NORTHRIDGE, CA 91325
Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/7/2023 Not Ready for Inspection HERBERT GIRON
Deputy Drilled-In Anchors 9/22/2023 Approved HERBERT GIRON
Excavation/Setback/Form/Re-Bar 9/22/2023 Approved HERBERT GIRON
Footing/Foundation/Slab 9/22/2023 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 10/31/2023 Conditional Approval TEMISTOCLES CAAL
PLUMBING-Rough 3/28/2024 Corrections Issued HERBERT GIRON
Gas Test 4/1/2024 Approved HERBERT GIRON
PLUMBING-Rough 4/1/2024 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/19/2024 Partial Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Partial Approval HERBERT GIRON
HVAC-Rough 5/14/2024 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/17/2024 Corrections Issued HERBERT GIRON
HVAC-Rough 5/17/2024 Conditional Approval HERBERT GIRON
ELECTRICAL-Rough 5/21/2024 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 5/23/2024 Approved HERBERT GIRON
Deputy Drilled-In Anchors 5/31/2024 Conditional Approval HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Corrections Issued HERBERT GIRON
Interior/Exterior Lathing 7/15/2024 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 8/16/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/16/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/23/2024 Approved HERBERT GIRON
Green Building Rough 8/23/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 8/23/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 9/10/2024 Approved HERBERT GIRON
Insulation 9/10/2024 Approved HERBERT GIRON
Shower Pan 9/19/2024 Approved JESUS PINEDA
Drywall Nailing 9/24/2024 Approved HERBERT GIRON
Interior/Exterior Lathing 9/24/2024 Approved HERBERT GIRON
Gas Test 2/20/2025 Approved HERBERT GIRON
ELECTRICAL-Final 4/3/2025 Corrections Issued TEMISTOCLES CAAL
HVAC-Final 4/3/2025 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Final 4/3/2025 Corrections Issued TEMISTOCLES CAAL
Service/Power Release 4/3/2025 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Final 4/7/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 4/7/2025 Approved JESUS RODRIGUEZ
Service/Power Release 4/7/2025 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 4/8/2025 Approved JESUS RODRIGUEZ
Final 4/29/2025 OK to Issue CofO JESUS RODRIGUEZ
Green Building Final 4/29/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 4/29/2025 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 4/29/2025 Approved JESUS RODRIGUEZ
Smoke Detectors 4/29/2025 Approved JESUS RODRIGUEZ