4278 N BRUNSWICK AVE 90039

Certificate Information: 4278 N BRUNSWICK AVE 90039

Application / Permit
19014-10000-03355
Plan Check / Job No.
B19LA12929
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FOR NEW 10'X22'-6" 1-STORY ADDITION TO (E) SFD
Permit Issued
Issued on 1/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/13/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2019 APPLICANT
Assigned to Plan Check Engineer 7/25/2019 VARAND SARKISIAN
Corrections Issued 7/29/2019 VARAND SARKISIAN
Green Plans Picked Up 8/1/2019 APPLICANT
Quality Review Completed 8/12/2019 JOSE RODRIGUEZ
Building Plans Picked Up 8/21/2019 APPLICANT
Plan Check Approved 1/13/2020 VARAND SARKISIAN
Issued 1/13/2020 LADBS
CofO in Progress 12/3/2021 HAMIK HARTOUNIAN
Permit Finaled 12/13/2021 DEROLD HAUFF
CofO Issued 12/13/2021 DEROLD HAUFF
Permit Finaled 12/13/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/21/2019 JAMES MORALEZ
Eng Process Fee Ord 176,300 Cleared 9/5/2019 JEANETTE VONG
Green Code Cleared 12/11/2019 VARAND SARKISIAN

Contact Information

Engineer Banning,, George Kwame; Lic. No.: C53074 7550 LILY COURT      FONTANA, CA 92336

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/14/2020 Conditional Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 1/15/2020 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/17/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/27/2020 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 1/31/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/6/2020 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 2/6/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 2/6/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/13/2020 Partial Approval HAMIK HARTOUNIAN
Insulation 2/13/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/28/2020 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 4/28/2020 Not Ready for Inspection OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 4/28/2020 Corrections Issued OSVALDO PARAMO
Deputy Wood Construction 4/29/2020 Conditional Approval HAMIK HARTOUNIAN
HVAC-Rough 5/1/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 5/1/2020 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/6/2020 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/6/2020 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 5/6/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 5/6/2020 Conditional Approval HAMIK HARTOUNIAN
PLUMBING-Rough 5/6/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 5/15/2020 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 5/15/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/15/2020 Partial Approval HAMIK HARTOUNIAN
Shower Pan 5/15/2020 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2020 Partial Approval CHRISTOPHER DELLEFIELD
Insulation 5/20/2020 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 5/26/2020 Approved HAMIK HARTOUNIAN
Insulation 5/26/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 6/24/2020 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 7/6/2020 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 8/27/2020 Corrections Issued HAMIK HARTOUNIAN
Final 8/27/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Final 8/27/2020 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/27/2020 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 8/27/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Final 9/3/2020 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 9/3/2020 Approved HAMIK HARTOUNIAN
Wood Frame 9/3/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/10/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 9/10/2020 Approved HAMIK HARTOUNIAN
Final 9/10/2020 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 9/10/2020 Approved HAMIK HARTOUNIAN
HVAC-Final 9/10/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Final 9/10/2020 Approved HAMIK HARTOUNIAN
Smoke Detectors 9/10/2020 Approved HAMIK HARTOUNIAN
Final 12/3/2021 OK to Issue CofO HAMIK HARTOUNIAN