817 W 147TH ST 90247

Certificate Information: 817 W 147TH ST 90247

Application / Permit
19014-10000-03353
Plan Check / Job No.
B19LA12919
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to (E) garage and conversion of entire building to an Accessory Dwelling Unit per AB 494 and SB 229.
Permit Issued
Issued on 8/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2020 APPLICANT
Assigned to Plan Check Engineer 1/7/2020 ADAM HEGAZI
Corrections Issued 1/7/2020 ADAM HEGAZI
Plan Check Approved 1/14/2020 SERGIO GUTIERREZ
Issued 8/10/2020 APPLICANT
Building Plans Picked Up 11/6/2020 APPLICANT
CofO in Progress 10/6/2022 ALIZAH MAYAGOITIA
Permit Finaled 3/18/2023 DANIEL ORRANTE
CofO Issued 3/18/2023 DANIEL ORRANTE
Permit Finaled 3/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction within easement Cleared 12/31/2019 RIDWAN HARDY
Address approval Cleared 1/7/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 1/7/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/14/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/14/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/12/2021 Approved JOHN KLARIN
METHANE-Barrier 10/12/2021 Approved JOHN KLARIN
METHANE-Subgrade 10/12/2021 Approved JOHN KLARIN
PLUMBING-Rough 10/12/2021 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 12/2/2021 Partial Approval JOHN KLARIN
ELECTRICAL-Rough 12/2/2021 Approved JOHN KLARIN
Green Building Rough 12/2/2021 Approved JOHN KLARIN
MERV13>=Rough 12/2/2021 Approved JOHN KLARIN
METHANE-Rough 12/2/2021 Approved JOHN KLARIN
PLUMBING-Rough 12/2/2021 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Approved JOHN KLARIN
HVAC-Rough 12/9/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 12/9/2021 Not Ready for Inspection JOHN KLARIN
Drywall Nailing 12/17/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/17/2021 Approved EUGENE CASSIDY
Shower Pan 12/17/2021 Not Ready for Inspection EUGENE CASSIDY
Shower Pan 1/21/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 3/4/2022 Approved JOHN KLARIN
Service/Power Release 3/4/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 5/4/2022 Approved EUGENE CASSIDY
Final 5/4/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 5/4/2022 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 5/4/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/4/2022 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 5/4/2022 Approved EUGENE CASSIDY
Final 5/23/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 5/23/2022 Approved ALIZAH MAYAGOITIA
MERV13>=Final 5/23/2022 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 10/6/2022 Approved ALIZAH MAYAGOITIA
Final 10/6/2022 OK to Issue CofO ALIZAH MAYAGOITIA
HVAC-Final 10/6/2022 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 10/6/2022 Approved ALIZAH MAYAGOITIA