11024 W BLIX ST 91602

Certificate Information: 11024 W BLIX ST 91602

Application / Permit
19014-10000-03320
Plan Check / Job No.
B19LA12772
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
22'-5" X 25'-8" IRREGULAR SHAPED ADDITION TO EXISTING SINGLE FAMILY DWELLING; INTERIOR REMODEL
Permit Issued
Issued on 6/20/2019
Issuing Office
Metro
Current Status
CofO Issued on 7/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/20/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 SELLA BENYAMIN
Plan Check Approved 6/20/2019 JEFFREY MACHADO
Issued 6/20/2019 LADBS
CofO in Progress 6/17/2021 THOMAS FINNILA
CofO Issued 7/10/2021 MICHAEL SMITH
Permit Finaled 7/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/20/2019 JEANETTE VONG
Roof/Waste drainage to street Cleared 6/20/2019 JEANETTE VONG
Sewer availability Cleared 6/20/2019 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,
Engineer Argeanton,, Luke James; Lic. No.: C81166 17320 RANSPOT AVE      LAKE ELSINORE, CA 92530

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/31/2019 Partial Approval JEFFREY PARD
PLUMBING-Rough 7/31/2019 Partial Approval JEFFREY PARD
Service/Power Release 9/27/2019 Approved JEFFREY PARD
Service/Power Release 12/27/2019 Not Ready for Inspection JEFFREY PARD
Pre-Inspection 7/6/2020 Partial Inspection THOMAS FINNILA
BUILDING-Rough-Frame 8/4/2020 Corrections Issued THOMAS FINNILA
BUILDING-Rough-Frame 9/4/2020 Partial Approval THOMAS FINNILA
ELECTRICAL-Rough 9/4/2020 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 9/4/2020 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 9/16/2020 Approved THOMAS FINNILA
PLUMBING-Rough 9/16/2020 Approved THOMAS FINNILA
ELECTRICAL-Rough 9/17/2020 Approved THOMAS FINNILA
Gas Test 9/17/2020 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 9/17/2020 Partial Approval THOMAS FINNILA
Wood Frame 9/17/2020 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 10/8/2020 Approved KATHRYN BUTTERWORTH
Gas Test 10/8/2020 Approved KATHRYN BUTTERWORTH
Insulation 10/8/2020 Approved KATHRYN BUTTERWORTH
Wood Frame 10/8/2020 Approved KATHRYN BUTTERWORTH
Drywall Nailing 11/12/2020 Approved THOMAS FINNILA
ELECTRICAL-Final 12/23/2020 Partial Inspection THOMAS FINNILA
Grounding or Bonding 12/31/2020 Partial Inspection THOMAS FINNILA
PLUMBING-Final 3/19/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 3/31/2021 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Final 4/7/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 4/8/2021 No Access for Inspection DAVID MATSON
ELECTRICAL-Final 4/28/2021 Partial Inspection THOMAS FINNILA
HVAC-Final 4/28/2021 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 5/13/2021 Not Ready for Inspection JOHN HAYES
Final 5/13/2021 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 5/19/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 5/19/2021 Not Ready for Inspection THOMAS FINNILA
Green Building Rough 5/19/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 5/28/2021 Approved THOMAS FINNILA
Service/Power Release 6/4/2021 Approved THOMAS FINNILA
Final 6/10/2021 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 6/10/2021 Approved THOMAS FINNILA
Green Building Final 6/10/2021 Corrections Issued THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Approved THOMAS FINNILA
Smoke Detectors 6/10/2021 Approved THOMAS FINNILA
Final 6/17/2021 OK to Issue CofO THOMAS FINNILA
Green Building Final 6/17/2021 Approved THOMAS FINNILA