755 S LOS ANGELES ST 90014
Certificate Information: 755 S LOS ANGELES ST 90014
- Application / Permit
- 19014-10000-03300
- Plan Check / Job No.
- B19LA12673
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Addition of the 6th Floor to an (E) 5-story office building for new restaurant.
- Permit Issued
- Issued on 12/31/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 12/23/2019 | WING SUEN |
| Issued | 12/31/2019 | LADBS |
| CofO in Progress | 1/14/2022 | MARK FERRARI |
| CofO Issued | 1/14/2022 | ERNESTO CORRAL |
| Permit Finaled | 1/14/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Encroachment in public way | Cleared | 9/9/2019 | JAMES KHO |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2019 | EMIL KYUPELYAN |
| Highway dedication | Cleared | 9/9/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 9/9/2019 | EMIL KYUPELYAN |
| DAS Clearance | Cleared | 10/8/2019 | WING SUEN |
| Project located in CRA area | Cleared | 10/15/2019 | JIM URQUHART |
| Hydrant and Access approval | Cleared | 10/18/2019 | JEREMY CARTER |
| Building over 3-story or 36-ft | Cleared | 10/22/2019 | CALOSHA APPROVED |
| Food establishment approval | Cleared | 10/28/2019 | LACDHS APPROVED |
| Green Code | Cleared | 10/29/2019 | DONALD CRICHLOW |
| "D" conditions | Cleared | 10/30/2019 | NOAH MCCOY |
| CPC | Cleared | 10/30/2019 | NOAH MCCOY |
| CPC | Cleared | 10/30/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 10/30/2019 | NOAH MCCOY |
| Food Service Establishment | Cleared | 10/31/2019 | RAMESHBHAIR PATEL |
| Fire Marshall Fire Life Safety | Cleared | 11/27/2019 | OSCAR SALGADO JR |
| Low Impact Development | Cleared | 12/19/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Swinerton Builders; Lic. No.: 92-B | 260 TOWNSEND STREET 5TH FLOOR LEGAL SAN FRANCISCO, CA 94107 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Structural Steel Frame | 11/5/2020 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 11/16/2020 | Partial Approval | DANIEL COLLINS |
| Structural Steel Frame | 11/16/2020 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 11/19/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Light Gage Steel Frame | 12/3/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Structural Steel Frame | 12/3/2020 | Not Ready for Inspection | DANIEL COLLINS |
| Light Gage Steel Frame | 12/7/2020 | Partial Approval | KATY RAMIREZ |
| Structural Steel Frame | 12/7/2020 | Not Ready for Inspection | KATY RAMIREZ |
| Footing/Foundation/Slab | 12/11/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/11/2020 | Partial Approval | DANIEL COLLINS |
| Structural Steel Frame | 12/11/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 12/15/2020 | Approved | DANIEL COLLINS |
| Light Gage Steel Frame | 12/15/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 12/18/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/18/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 12/23/2020 | Approved | DANIEL COLLINS |
| Light Gage Steel Frame | 12/23/2020 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 12/31/2020 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 12/31/2020 | Partial Approval | DANIEL COLLINS |
| Insulation | 1/5/2021 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 1/5/2021 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 1/11/2021 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Partial Inspection | DANIEL COLLINS |
| Insulation | 1/11/2021 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 1/11/2021 | Partial Approval | DANIEL COLLINS |
| Structural Steel Frame | 1/11/2021 | Approved | DANIEL COLLINS |
| Drywall Nailing | 1/14/2021 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 1/21/2021 | Partial Approval | DANIEL COLLINS |
| Insulation | 1/21/2021 | Partial Approval | DANIEL COLLINS |
| Interior/Exterior Lathing | 1/21/2021 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 1/21/2021 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 2/2/2021 | Partial Approval | DANIEL COLLINS |
| Floor/Roof Diaphrgm/Shear Wall | 2/2/2021 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 2/2/2021 | Partial Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 2/5/2021 | Partial Approval | DANIEL COLLINS |
| Structural Steel Frame | 2/5/2021 | Partial Approval | DANIEL COLLINS |
| Interior/Exterior Lathing | 2/9/2021 | Partial Approval | DANIEL COLLINS |
| Final | 3/23/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Footing/Foundation/Slab | 3/23/2021 | Approved | DANIEL COLLINS |
| Green Building Final | 3/23/2021 | Approved | DANIEL COLLINS |
| Green Building Rough | 3/23/2021 | Approved | DANIEL COLLINS |
| Reinforced Concrete Frame | 3/23/2021 | Approved | DANIEL COLLINS |
| Reinforced Masonry Frame | 3/23/2021 | Approved | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 3/23/2021 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 3/23/2021 | Approved | DANIEL COLLINS |
| Final | 5/3/2021 | Partial Inspection | DANIEL COLLINS |
| Final | 6/10/2021 | Partial Inspection | DANIEL COLLINS |
| Final | 12/14/2021 | Not Ready for Inspection | MARK FERRARI |
| Final | 1/11/2022 | Conditional Approval | MARK FERRARI |