755 S LOS ANGELES ST 90014

Certificate Information: 755 S LOS ANGELES ST 90014

Application / Permit
19014-10000-03300
Plan Check / Job No.
B19LA12673
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Addition of the 6th Floor to an (E) 5-story office building for new restaurant.
Permit Issued
Issued on 12/31/2019
Issuing Office
Metro
Current Status
CofO Issued on 1/14/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 12/23/2019 WING SUEN
Issued 12/31/2019 LADBS
CofO in Progress 1/14/2022 MARK FERRARI
CofO Issued 1/14/2022 ERNESTO CORRAL
Permit Finaled 1/14/2022 ERNESTO CORRAL

Permit Application Clearance Information

Encroachment in public way Cleared 9/9/2019 JAMES KHO
Eng Process Fee Ord 176,300 Cleared 9/9/2019 EMIL KYUPELYAN
Highway dedication Cleared 9/9/2019 EMIL KYUPELYAN
Sewer availability Cleared 9/9/2019 EMIL KYUPELYAN
DAS Clearance Cleared 10/8/2019 WING SUEN
Project located in CRA area Cleared 10/15/2019 JIM URQUHART
Hydrant and Access approval Cleared 10/18/2019 JEREMY CARTER
Building over 3-story or 36-ft Cleared 10/22/2019 CALOSHA APPROVED
Food establishment approval Cleared 10/28/2019 LACDHS APPROVED
Green Code Cleared 10/29/2019 DONALD CRICHLOW
"D" conditions Cleared 10/30/2019 NOAH MCCOY
CPC Cleared 10/30/2019 NOAH MCCOY
CPC Cleared 10/30/2019 NOAH MCCOY
Miscellaneous Cleared 10/30/2019 NOAH MCCOY
Food Service Establishment Cleared 10/31/2019 RAMESHBHAIR PATEL
Fire Marshall Fire Life Safety Cleared 11/27/2019 OSCAR SALGADO JR
Low Impact Development Cleared 12/19/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/19/2019 ADRIAN CASTRO

Contact Information

Contractor Swinerton Builders; Lic. No.: 92-B 260 TOWNSEND STREET   5TH FLOOR LEGAL    SAN FRANCISCO, CA 94107

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Structural Steel Frame 11/5/2020 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 11/16/2020 Partial Approval DANIEL COLLINS
Structural Steel Frame 11/16/2020 Partial Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 11/19/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 11/19/2020 Not Ready for Inspection DANIEL COLLINS
Light Gage Steel Frame 12/3/2020 Not Ready for Inspection DANIEL COLLINS
Structural Steel Frame 12/3/2020 Not Ready for Inspection DANIEL COLLINS
Light Gage Steel Frame 12/7/2020 Partial Approval KATY RAMIREZ
Structural Steel Frame 12/7/2020 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 12/11/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/11/2020 Partial Approval DANIEL COLLINS
Structural Steel Frame 12/11/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 12/15/2020 Approved DANIEL COLLINS
Light Gage Steel Frame 12/15/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 12/18/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/18/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 12/23/2020 Approved DANIEL COLLINS
Light Gage Steel Frame 12/23/2020 Partial Approval DANIEL COLLINS
Drywall Nailing 12/31/2020 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 12/31/2020 Partial Approval DANIEL COLLINS
Insulation 1/5/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 1/5/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 1/11/2021 Partial Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Inspection DANIEL COLLINS
Insulation 1/11/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 1/11/2021 Partial Approval DANIEL COLLINS
Structural Steel Frame 1/11/2021 Approved DANIEL COLLINS
Drywall Nailing 1/14/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 1/21/2021 Partial Approval DANIEL COLLINS
Insulation 1/21/2021 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 1/21/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 1/21/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 2/2/2021 Partial Approval DANIEL COLLINS
Floor/Roof Diaphrgm/Shear Wall 2/2/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 2/2/2021 Partial Approval DANIEL COLLINS
Footing/Foundation/Slab 2/5/2021 Partial Approval DANIEL COLLINS
Structural Steel Frame 2/5/2021 Partial Approval DANIEL COLLINS
Interior/Exterior Lathing 2/9/2021 Partial Approval DANIEL COLLINS
Final 3/23/2021 Not Ready for Inspection DANIEL COLLINS
Footing/Foundation/Slab 3/23/2021 Approved DANIEL COLLINS
Green Building Final 3/23/2021 Approved DANIEL COLLINS
Green Building Rough 3/23/2021 Approved DANIEL COLLINS
Reinforced Concrete Frame 3/23/2021 Approved DANIEL COLLINS
Reinforced Masonry Frame 3/23/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Approved DANIEL COLLINS
Smoke Detectors 3/23/2021 Approved DANIEL COLLINS
Final 5/3/2021 Partial Inspection DANIEL COLLINS
Final 6/10/2021 Partial Inspection DANIEL COLLINS
Final 12/14/2021 Not Ready for Inspection MARK FERRARI
Final 1/11/2022 Conditional Approval MARK FERRARI