662 N SALTAIR AVE 90049

Certificate Information: 662 N SALTAIR AVE 90049

Application / Permit
19014-10000-03268
Plan Check / Job No.
B19LA12576
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL OF 2 STORY SFD WITH ADDITION OF 456 SQ FT TO LIVING AREA. IN ADDITION A NEW ROOF, REMODEL OF FOUR BATHROOMS AND KITCHEN.
Permit Issued
Issued on 9/16/2019
Issuing Office
Metro
Current Status
Issued on 9/16/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/18/2019 APPLICANT
Green Plans Picked Up 6/28/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 VARAND SARKISIAN
Corrections Issued 7/15/2019 VARAND SARKISIAN
Quality Review Completed 7/23/2019 JOSE RODRIGUEZ
Building Plans Picked Up 7/24/2019 APPLICANT
Plan Check Approved 9/13/2019 VARAND SARKISIAN
Issued 9/16/2019 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/24/2019 KARAN PATEL
Hydrant and Access approval Cleared 7/24/2019 ROBERT DUFF
Roof/Waste drainage to street Cleared 7/24/2019 KARAN PATEL
Sewer availability Cleared 7/24/2019 KARAN PATEL
Green Code Cleared 8/8/2019 KHEDER ALRAZAA
Low Impact Development Cleared 8/22/2019 ORVAL HERNANDEZ-MARCI
Grading Pre-Inspection Cleared 9/13/2019 VARAND SARKISIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Nick; Lic. No.: L7022 4966 TOPANGA CYN BLVD      WOODLAND HILLS, CA 91364
Engineer Mercado,, Lizandro; Lic. No.: S4331 25583 AVENUE STANFORD      VALENCIA, CA 91355

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/11/2019 Corrections Issued ANTHONY MCDOWALL
Footing/Foundation/Slab 12/19/2019 Partial Approval ANTHONY MCDOWALL
Footing/Foundation/Slab 2/10/2020 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 No Access for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 8/25/2020 Corrections Issued CARLOS MATAMOROS
Gas Test 8/25/2020 Approved CARLOS MATAMOROS
HVAC-Rough 8/25/2020 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 8/25/2020 Corrections Issued CARLOS MATAMOROS
Wood Frame 8/25/2020 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Partial Approval CARLOS MATAMOROS
Green Building Rough 9/1/2020 Not Ready for Inspection CARLOS MATAMOROS
BUILDING-Rough-Frame 9/22/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 9/22/2020 Approved CARLOS MATAMOROS
Green Building Rough 9/22/2020 Approved CARLOS MATAMOROS
HVAC-Rough 9/22/2020 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/22/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 10/7/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 10/7/2020 Approved CARLOS MATAMOROS
Insulation 10/16/2020 Approved CARLOS MATAMOROS
Shower Pan 10/16/2020 Partial Approval CARLOS MATAMOROS
Drywall Nailing 11/6/2020 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 11/17/2020 Approved CARLOS MATAMOROS
ELECTRICAL-Final 5/21/2021 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 5/21/2021 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 5/21/2021 Not Ready for Inspection CARLOS MATAMOROS