111 N GARDNER ST 90036

Certificate Information: 111 N GARDNER ST 90036

Application / Permit
19014-10000-03212
Plan Check / Job No.
B19LA12361
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SECOND STORY ADDITION AND REMODEL OF (E) SINGLE FAMILY RESIDENCE, DEMO (E) DECK.
Permit Issued
Issued on 1/6/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2019 APPLICANT
Assigned to Plan Check Engineer 7/24/2019 ZAW HAN
Corrections Issued 7/31/2019 ZAW HAN
Green Plans Picked Up 8/1/2019 APPLICANT
Quality Review Completed 9/11/2019 HERNAN ARREOLA
Building Plans Picked Up 9/24/2019 APPLICANT
Applicant returned to address corrections 11/5/2019 ZAW HAN
Plan Check Approved 12/12/2019 ZAW HAN
Issued 1/6/2020 LADBS
CofO in Progress 11/15/2023 LILIANA PORTILLO
CofO in Progress 11/15/2023 LILIANA PORTILLO
Permit Finaled 11/26/2023 DEROLD HAUFF
CofO Issued 11/26/2023 DEROLD HAUFF
Permit Finaled 11/26/2023 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 10/22/2019 MICAELA TORRES-GIL
Miscellaneous Cleared 10/22/2019 MICAELA TORRES-GIL
ZI Cleared 10/22/2019 MICAELA TORRES-GIL
Eng Process Fee Ord 176,300 Cleared 10/28/2019 CELINA MORENO
Sewer availability Cleared 10/28/2019 CELINA MORENO
Green Code Cleared 10/29/2019 VIVIAN LAO
Low Impact Development Cleared 11/25/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/12/2019 THOMAS LANG

Contact Information

Architect Barrett, Cooke; Lic. No.: C37365       ,
Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2020 Conditional Approval MICHAEL FAUNCE
METHANE-Barrier 3/2/2020 Conditional Approval MICHAEL FAUNCE
METHANE-Subgrade 3/2/2020 Conditional Approval MICHAEL FAUNCE
BUILDING-Rough-Frame 3/24/2020 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 3/24/2020 Partial Approval JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval ROBERT VORHIS
Insulation 3/31/2020 Partial Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 4/6/2020 Partial Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 7/9/2020 Approved CHRIS CHRISTENSEN
METHANE-Barrier 7/9/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 7/9/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Drywall Nailing 9/4/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Approved CHRIS CHRISTENSEN
Green Building Rough 9/4/2020 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/13/2020 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/13/2020 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Rough 10/13/2020 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 10/13/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 10/13/2020 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 10/20/2020 Approved CHRIS CHRISTENSEN
HVAC-Rough 10/20/2020 Conditional Approval CHRIS CHRISTENSEN
PLUMBING-Rough 10/20/2020 Conditional Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 10/26/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 10/26/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Insulation 11/2/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 11/2/2020 Approved CHRIS CHRISTENSEN
Drywall Nailing 11/19/2020 Approved CHRIS CHRISTENSEN
Shower Pan 12/8/2020 Partial Approval CHRIS CHRISTENSEN
Interior/Exterior Lathing 12/14/2020 Approved CHRIS CHRISTENSEN
Shower Pan 12/14/2020 Approved CHRIS CHRISTENSEN
Final 6/2/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 6/2/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 6/2/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 6/2/2021 Approved CHRIS CHRISTENSEN
Final 3/17/2022 Corrections Issued CRAIG DAVIS
Green Building Final 3/17/2022 Corrections Issued CRAIG DAVIS
Final 4/8/2022 Conditional Approval ARTHUR SARGSYAN
Green Building Final 4/8/2022 Approved ARTHUR SARGSYAN
Special/Order Compliance 6/26/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Final 11/14/2023 Approved LILIANA PORTILLO
Final 11/14/2023 OK to Issue CofO LILIANA PORTILLO
HVAC-Final 11/14/2023 Approved LILIANA PORTILLO
PLUMBING-Final 11/14/2023 Approved LILIANA PORTILLO