1701-1703 S WOOSTER ST 90035

Certificate Information: 1701-1703 S WOOSTER ST 90035

Application / Permit
19014-10000-03206
Plan Check / Job No.
B19LA12333
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD NEW 2ND STORY ATTACHED ACCESSORY DWELLING UNIT PER ORDINANCE AND LAMC 12.22 A.33 (c) &(e). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 10/8/2021
Issuing Office
Current Status
CofO Issued on 1/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/14/2019 APPLICANT
Assigned to Plan Check Engineer 7/24/2019 ZAW HAN
Green Plans Picked Up 7/25/2019 APPLICANT
Corrections Issued 8/5/2019 ZAW HAN
Quality Review Completed 8/16/2019 HERNAN ARREOLA
Plan Check Approved 9/22/2021 ZAW HAN
Issued 10/8/2021 APPLICANT
Building Plans Picked Up 11/8/2021 APPLICANT
CofO in Progress 1/9/2026 WILBER ROSALES
Permit Finaled 1/17/2026 RICHARD STEINBACH
CofO Issued 1/17/2026 RICHARD STEINBACH
Permit Finaled 1/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

CPC Cleared 7/2/2021 DANIEL CORONADO
CPC Cleared 7/7/2021 DANIEL CORONADO
Address approval Cleared 7/12/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 7/12/2021 RENZ SORIANO
Permit Cleared 7/12/2021 RENZ SORIANO
Sewer availability Cleared 7/12/2021 RENZ SORIANO
Green Code Cleared 8/19/2021 VIVIAN LAO
Roof/Waste drainage to street Cleared 9/17/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Hanna,, Ashraf Waguih H T; Lic. No.: C53286 5952 N WILLARD AVE      SAN GABRIEL, CA 91775

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Subgrade 7/26/2022 Not Ready for Inspection JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 7/29/2022 Corrections Issued EVAN COOPER
Footing/Foundation/Slab 7/29/2022 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 8/8/2022 Corrections Issued EVAN COOPER
Excavation/Setback/Form/Re-Bar 8/22/2022 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 8/22/2022 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 9/19/2022 Approved MICHAEL PELHAM
Footing/Foundation/Slab 9/19/2022 Approved MICHAEL PELHAM
Deputy Drilled-In Anchors 10/18/2022 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/23/2022 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/11/2023 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Rough 1/20/2023 Approved JEREMY TODD
HVAC-Rough 1/20/2023 Approved JEREMY TODD
PLUMBING-Rough 1/20/2023 Approved JEREMY TODD
Insulation 2/6/2023 Corrections Issued JEREMY TODD
Insulation 3/9/2023 Approved JEREMY TODD
Interior/Exterior Lathing 3/9/2023 Approved JEREMY TODD
Drywall Nailing 3/29/2023 Corrections Issued JEREMY TODD
Green Building Rough 3/29/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 4/11/2023 Approved JEREMY TODD
Drywall Nailing 4/11/2023 Partial Approval JEREMY TODD
Drywall Nailing 4/4/2025 Approved EVAN COOPER
Final 4/4/2025 Corrections Issued EVAN COOPER
Green Building Final 4/4/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 4/4/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 4/4/2025 Approved EVAN COOPER
Final 1/8/2026 OK to Issue CofO WILBER ROSALES