1823 S DUNSMUIR AVE 90019

Certificate Information: 1823 S DUNSMUIR AVE 90019

Application / Permit
19014-10000-03043
Plan Check / Job No.
B19LA11698
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERTING (E) SHED TO ADU PER AB494 AND SB 229. 101 SF PORTION TO BE DEMOLISHED, 304 SF TO REMAIN AND NEW 839 SF ADDITION.
Permit Issued
Issued on 11/27/2019
Issuing Office
Metro
Current Status
CofO Issued on 4/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2019 APPLICANT
Green Plans Picked Up 6/21/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 SAMUEL GONZALEZ
Corrections Issued 7/1/2019 SAMUEL GONZALEZ
Quality Review Completed 7/19/2019 QUAN NGHIEM
Building Plans Picked Up 7/24/2019 APPLICANT
Plan Check Approved 11/19/2019 SAMUEL GONZALEZ
Issued 11/27/2019 LADBS
CofO in Progress 12/15/2022 JOSE AVILA
No Progress 3/4/2023 MICHAEL PELHAM
CofO in Progress 4/7/2023 DONALD CRICHLOW
Permit Finaled 4/8/2023 DEROLD HAUFF
CofO Issued 4/8/2023 DEROLD HAUFF
Permit Finaled 4/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 10/10/2019 COLIN LOREDO
Low Impact Development Cleared 10/10/2019 ORVAL HERNANDEZ-MARCIAL
Address approval Cleared 11/19/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/19/2019 CELINA MORENO
Hydrant and Access approval Cleared 11/19/2019 JEREMY CARTER
Roof/Waste drainage to street Cleared 11/19/2019 CELINA MORENO
Sewer availability Cleared 11/19/2019 CELINA MORENO

Contact Information

Contractor Hawkins Harold; Lic. No.: 300521-B 1320 1/2 92ND STREET      LOS ANGELES, CA 90044

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/19/2019 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 2/4/2020 Corrections Issued DAVID CHAN
PLUMBING-Rough 2/10/2020 Partial Approval DAVID CHAN
Footing/Foundation/Slab 2/28/2020 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 7/20/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 5/13/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 5/13/2022 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Approved JOSE AVILA
Green Building Rough 5/13/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 5/13/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 5/23/2022 Corrections Issued JOSE AVILA
HVAC-Rough 5/23/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 5/23/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 6/10/2022 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 6/10/2022 Approved STUART CHAPMAN
HVAC-Rough 6/10/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 6/10/2022 Approved STUART CHAPMAN
Insulation 6/14/2022 Approved JOSE AVILA
Drywall Nailing 6/17/2022 Approved JOSE AVILA
Green Building Rough 6/17/2022 Approved JOSE AVILA
ELECTRICAL-Rough 7/8/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/8/2022 Approved JOSE AVILA
Shower Pan 7/8/2022 Approved JOSE AVILA
Wood Frame 7/8/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 11/4/2022 Approved JOSE AVILA
ELECTRICAL-Final 11/4/2022 Corrections Issued JOSE AVILA
Final 11/4/2022 Partial Inspection JOSE AVILA
Green Building Final 11/4/2022 Approved JOSE AVILA
HVAC-Final 11/4/2022 Corrections Issued JOSE AVILA
PLUMBING-Final 11/4/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Not Ready JOSE AVILA
Service/Power Release 11/4/2022 Approved JOSE AVILA
Smoke Detectors 11/4/2022 Approved JOSE AVILA
Service/Power Release 11/23/2022 Approved DONALD CRICHLOW
Final 12/5/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/5/2022 SGSOV Not Ready JOSE AVILA
Final 12/12/2022 OK to Issue CofO JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/12/2022 SGSOV Approved JOSE AVILA