7400 S RAYMOND AVE 90044
Certificate Information: 7400 S RAYMOND AVE 90044
- Application / Permit
- 19014-10000-03040
- Plan Check / Job No.
- B19LA11686
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2ND-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 OVER EXISTING GARAGE. NEW 1ST FLOOR ADDITION TO GARAGE TO ADD STORAGE & LAUNDRY
- Permit Issued
- Issued on 9/10/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 1/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/17/2019 | PRANITA SHAH |
| Green Plans Picked Up | 7/18/2019 | APPLICANT |
| Corrections Issued | 7/24/2019 | PRANITA SHAH |
| Quality Review Completed | 7/30/2019 | TU HUA |
| Building Plans Picked Up | 8/7/2019 | APPLICANT |
| Plan Check Approved | 9/9/2019 | PRANITA SHAH |
| Issued | 9/10/2019 | LADBS |
| CofO in Progress | 12/3/2020 | FREDDIE RIVERA |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
| CofO Issued | 1/23/2021 | DEROLD HAUFF |
| Permit Finaled | 1/23/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/14/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 8/14/2019 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2019 | ERIK BEASLEY |
| Green Code | Cleared | 8/16/2019 | VIVIAN LAO |
| Sewer availability | Cleared | 8/16/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 9/3/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/3/2019 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wong,, Jim Chu Man; Lic. No.: C69393 | PO BOX 373 GLENDORA, CA 91740 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/21/2019 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/21/2019 | Corrections Issued | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 11/1/2019 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 11/1/2019 | Not Ready for Inspection | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 12/6/2019 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 12/6/2019 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2020 | Partial Approval | EUGENE CASSIDY |
| Wood Frame | 1/8/2020 | Partial Approval | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/19/2020 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2020 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 2/19/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 3/25/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Rough | 3/25/2020 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 3/25/2020 | Approved | EUGENE CASSIDY |
| Sewer | 3/25/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/2/2020 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/2/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/2/2020 | Corrections Issued | EUGENE CASSIDY |
| Interior/Exterior Lathing | 4/2/2020 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/21/2020 | Approved | EUGENE CASSIDY |
| Insulation | 4/21/2020 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 5/15/2020 | Approved | EUGENE CASSIDY |
| Final | 9/8/2020 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 9/8/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| Service/Power Release | 9/8/2020 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/23/2020 | Approved | DAVID FEILER |
| Final | 9/23/2020 | Corrections Issued | DAVID FEILER |
| Green Building Final | 9/23/2020 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 9/23/2020 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 9/23/2020 | Approved | DAVID FEILER |
| Final | 12/2/2020 | OK to Issue CofO | FREDDIE RIVERA |
| Gas Test | 12/2/2020 | Approved | FREDDIE RIVERA |
| Service/Power Release | 12/2/2020 | Approved | FREDDIE RIVERA |