4077 W PICO BLVD 90019
Certificate Information: 4077 W PICO BLVD 90019
- Application / Permit
- 19014-10000-03025
- Plan Check / Job No.
- B19LA11626
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- NEW 2ND STORY ADDITION TO EXISTING COMMERCIAL BUILDING AND TENANT IMPROVEMENT "COMPLY WITH DEPARTMENT ORDER effective date 03/18/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector AGUSTIN ALVAREZ MORALES of CITATIONS SOUTH. CEIS Case Number is 849309. (Created: IMSV7 / 03-13-19)
- Permit Issued
- Issued on 2/19/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/28/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/5/2019 | APPLICANT |
| Green Plans Picked Up | 6/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2019 | EMMANUEL MARTINEZ |
| Corrections Issued | 6/24/2019 | EMMANUEL MARTINEZ |
| Quality Review Completed | 7/1/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 7/11/2019 | APPLICANT |
| Applicant returned to address corrections | 10/30/2019 | EMMANUEL MARTINEZ |
| Plan Check Approved | 12/5/2019 | EMMANUEL MARTINEZ |
| Issued | 2/19/2020 | LADBS |
| CofO in Progress | 5/28/2021 | TIMOTHY BUXTON |
| CofO Issued | 5/28/2021 | ERNESTO CORRAL |
| Permit Finaled | 5/28/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2019 | CELINA MORENO |
| Green Code | Cleared | 10/16/2019 | VIVIAN LAO |
| Sewer availability | Cleared | 10/16/2019 | CELINA MORENO |
| Low Impact Development | Cleared | 10/22/2019 | ORVAL HERNANDEZ-MARCI |
| Project located in CRA area | Cleared | 10/22/2019 | JIM URQUHART |
| Roof/Waste drainage to street | Cleared | 10/22/2019 | ELAINE LEI |
| ZI | Cleared | 10/25/2019 | DIANA JIMENEZ |
| Hydrant and Access approval | Cleared | 10/30/2019 | JEREMY CARTER |
| DAS Clearance | Cleared | 11/26/2019 | SHINE LIN |
Contact Information
| Architect | Zane,, Jonathan Leonard; Lic. No.: C11046 | 958 NORTH LA CADENA DRIVE COLTON, CA 92324 |
| Contractor | Statewide General Contractors Inc; Lic. No.: 935055-B | 16385 TRISHA WAY RIVERSIDE, CA 92504 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 2/25/2020 | Not Ready for Inspection | JONATHAN QUACH |
| METHANE-Rough | 2/25/2020 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 2/25/2020 | Corrections Issued | JONATHAN QUACH |
| Footing/Foundation/Slab | 5/18/2020 | Approved | TIMOTHY BUXTON |
| METHANE-Barrier | 5/18/2020 | Approved | TIMOTHY BUXTON |
| METHANE-Subgrade | 5/18/2020 | Approved | TIMOTHY BUXTON |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2020 | Partial Approval | TIMOTHY BUXTON |
| Green Building Rough | 6/4/2020 | Not Ready for Inspection | TIMOTHY BUXTON |
| METHANE-Rough | 6/4/2020 | Approved | TIMOTHY BUXTON |
| Wood Frame | 6/4/2020 | Corrections Issued | TIMOTHY BUXTON |
| Green Building Rough | 8/11/2020 | Approved | TIMOTHY BUXTON |
| Wood Frame | 8/11/2020 | Approved | TIMOTHY BUXTON |
| Wood Frame | 2/17/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Drywall Nailing | 3/10/2021 | Approved | TIMOTHY BUXTON |
| Green Building Final | 3/26/2021 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 3/26/2021 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 3/26/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Wood Frame | 3/26/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 5/3/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Green Building Final | 5/3/2021 | Approved | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 5/3/2021 | SGSOV No Gas | TIMOTHY BUXTON |
| Smoke Detectors | 5/3/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 5/3/2021 | Approved | TIMOTHY BUXTON |
| Final | 5/13/2021 | Not Ready for Inspection | TIMOTHY BUXTON |
| Final | 5/20/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Final | 5/27/2021 | Conditional Approval | TIMOTHY BUXTON |