17532 W RAYMER ST 91325
Certificate Information: 17532 W RAYMER ST 91325
- Application / Permit
- 19014-10000-02836
- Plan Check / Job No.
- B19LA11030
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD NEW ATTACHED 2-CAR GARAGE AND NEW HALLWAY INTO GARAGE
- Permit Issued
- Issued on 8/15/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/3/2019 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 6/17/2019 | ZAW HAN |
| Plan Check Approved | 7/29/2019 | ADAM HEGAZI |
| Issued | 8/15/2019 | LADBS |
| CofO in Progress | 5/16/2022 | RAUL OLAGI |
| Permit Finaled | 6/11/2022 | MICHAEL SMITH |
| CofO Issued | 6/11/2022 | MICHAEL SMITH |
| Permit Finaled | 6/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 6/5/2019 | FARSHAD ALIMOHAMADI |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2019 | JEANIE LAM |
| Low Impact Development | Cleared | 7/29/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 7/29/2019 | JEANIE LAM |
Contact Information
| Architect | Stage,, Christopher Barrett; Lic. No.: C32866 | 10815 OREGON AVENUE CULVER CITY, CA 90232 |
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/10/2019 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 10/17/2019 | No Access for Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 10/23/2019 | Corrections Issued | MARK JOHNSON |
| Footing/Foundation/Slab | 12/28/2019 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 3/17/2020 | Not Ready for Inspection | MARK JOHNSON |
| ELECTRICAL-Rough | 3/17/2020 | Approved | MARK JOHNSON |
| Green Building Rough | 3/17/2020 | Not Ready for Inspection | MARK JOHNSON |
| HVAC-Rough | 3/17/2020 | Corrections Issued | MARK JOHNSON |
| PLUMBING-Rough | 3/17/2020 | Corrections Issued | MARK JOHNSON |
| Rough-Elec/Plmb/HVAC | 3/17/2020 | Not Ready for Inspection | MARK JOHNSON |
| Wood Frame | 3/17/2020 | Partial Approval | MARK JOHNSON |
| BUILDING-Rough-Frame | 3/24/2020 | Corrections Issued | MARK JOHNSON |
| Green Building Rough | 3/24/2020 | Not Ready for Inspection | MARK JOHNSON |
| Rough-Elec/Plmb/HVAC | 3/24/2020 | Approved | MARK JOHNSON |
| Wood Frame | 3/24/2020 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 3/27/2020 | Approved | MARK JOHNSON |
| Green Building Rough | 3/27/2020 | Approved | MARK JOHNSON |
| Interior/Exterior Lathing | 3/27/2020 | Approved | MARK JOHNSON |
| Wood Frame | 3/27/2020 | Approved | MARK JOHNSON |
| Drywall Nailing | 4/1/2020 | Not Ready for Inspection | MARK JOHNSON |
| Insulation | 4/1/2020 | Approved | MARK JOHNSON |
| Drywall Nailing | 4/6/2020 | Approved | MARK JOHNSON |
| Final | 4/4/2022 | Corrections Issued | RAUL OLAGI |
| Green Building Final | 4/4/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/4/2022 | SGSOV Approved | RAUL OLAGI |
| Smoke Detectors | 4/4/2022 | Approved | RAUL OLAGI |
| Final | 5/13/2022 | OK to Issue CofO | RAUL OLAGI |
| Green Building Final | 5/13/2022 | Approved | RAUL OLAGI |