1334 W UPTON PL 90041

Certificate Information: 1334 W UPTON PL 90041

Application / Permit
19014-10000-02793
Plan Check / Job No.
B19LA10863
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED TWO-STORY ADDITION TO (E) SFD; WORK TO INCLUDE REFRAMING THE ROOF
Permit Issued
Issued on 1/9/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/28/2019 APPLICANT
Green Plans Picked Up 6/4/2019 APPLICANT
Assigned to Plan Check Engineer 6/13/2019 SINA KHOSRAVI
Corrections Issued 6/18/2019 SINA KHOSRAVI
Quality Review Completed 6/21/2019 FELIX FIGUEROA
Building Plans Picked Up 6/24/2019 APPLICANT
Applicant returned to address corrections 8/7/2019 SINA KHOSRAVI
Applicant returned to address corrections 8/16/2019 SINA KHOSRAVI
Plan Check Approved 1/8/2020 SINA KHOSRAVI
Issued 1/9/2020 LADBS
CofO in Progress 2/25/2022 CRAIG VAUGHAN
CofO in Progress 2/25/2022 CRAIG VAUGHAN
Permit Finaled 2/11/2023 DANIEL ORRANTE
CofO Issued 2/11/2023 DANIEL ORRANTE
Permit Finaled 2/11/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/23/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 7/23/2019 CELINA MORENO
Grading Pre-Inspection Cleared 8/7/2019 SINA KHOSRAVI
Green Code Cleared 8/9/2019 DONALD CRICHLOW
Low Impact Development Cleared 8/27/2019 SARAH YOUSSEF

Contact Information

Contractor Owner-Builder       ,
Engineer Tangonan,, Jimmy G; Lic. No.: C50500 17770 CAPE JASMINE RD      CANYON COUNTRY, CA 91387

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/10/2020 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 1/15/2020 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 1/21/2020 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 1/21/2020 Approved CRAIG VAUGHAN
Green Building Rough 1/21/2020 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 2/18/2020 Approved BRIAN SULLIVAN
PLUMBING-Rough 3/9/2020 Partial Approval RUBEN SALAS
Special/Order Compliance 4/29/2020 Partial Inspection CRAIG VAUGHAN
Deputy Drilled-In Anchors 5/22/2020 No Access for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 6/3/2020 Partial Approval CRAIG VAUGHAN
Green Building Rough 6/3/2020 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 6/16/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 6/16/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 6/18/2020 Partial Approval CRAIG VAUGHAN
Green Building Rough 6/18/2020 Approved CRAIG VAUGHAN
HVAC-Rough 6/18/2020 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 6/18/2020 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 6/22/2020 Approved CRAIG VAUGHAN
HVAC-Rough 6/22/2020 Approved CRAIG VAUGHAN
Insulation 6/25/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 6/25/2020 Partial Approval HAMIK HARTOUNIAN
Insulation 6/30/2020 Approved CRAIG VAUGHAN
Drywall Nailing 7/6/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/16/2020 Approved BRIAN SULLIVAN
Final 10/20/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 10/20/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 10/20/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 10/20/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 2/24/2022 Approved CRAIG VAUGHAN
Final 2/24/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 2/24/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 2/24/2022 Approved CRAIG VAUGHAN