422 S OXFORD AVE 90020

Certificate Information: 422 S OXFORD AVE 90020

Application / Permit
19014-10000-02787
Plan Check / Job No.
B19LA10831
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing garage to accessory dwelling unit per AB494 and SB229 and addition to 1st floor, new 2nd floor. "COMPLY WITH DEPARTMENT ORDER effective date 10/01/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". All permits shall be for the same time period limitation. CEIS Case Number is 826652.
Permit Issued
Issued on 9/14/2021
Issuing Office
Current Status
CofO in Progress on 8/15/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2019 APPLICANT
Assigned to Plan Check Engineer 6/27/2019 VU NGUYEN
Corrections Issued 7/11/2019 VU NGUYEN
Quality Review Completed 7/19/2019 JOSE RODRIGUEZ
Building Plans Picked Up 7/23/2019 APPLICANT
Green Plans Picked Up 9/20/2019 APPLICANT
Applicant returned to address corrections 6/11/2021 VU NGUYEN
Applicant returned to address corrections 6/18/2021 VU NGUYEN
Applicant returned to address corrections 9/4/2021 VU NGUYEN
Plan Check Approved 9/14/2021 VU NGUYEN
Issued 9/14/2021 APPLICANT
CofO in Progress 8/15/2023 GLEN RAND

Permit Application Clearance Information

Project located in CRA area Cleared 8/22/2019 JIM URQUHART
CPC Cleared 10/1/2019 TERRI OSBORNE
Green Code Cleared 10/1/2019 VIVIAN LAO
Address approval Cleared 6/28/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 6/29/2021 STEVE MELGAR
Sewer availability Cleared 6/29/2021 STEVE MELGAR
Low Impact Development Cleared 8/24/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/26/2021 STEVE MELGAR
Hold Cleared 9/27/2021 JASON SHEETS

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/9/2021 Corrections Issued GLEN RAND
Pre-Inspection 11/10/2021 Corrections Issued GLEN RAND
Pre-Inspection 2/24/2022 Corrections Issued GLEN RAND
Pre-Inspection 3/4/2022 Corrections Issued GLEN RAND
Underground Mechanical 3/17/2022 Approved GLEN RAND
Footing/Foundation/Slab 4/6/2022 Corrections Issued GLEN RAND
Footing/Foundation/Slab 4/11/2022 Corrections Issued GLEN RAND
Footing/Foundation/Slab 4/27/2022 Approved GLEN RAND
Pre-Inspection 5/25/2022 Partial Approval GLEN RAND
Wood Frame 6/15/2022 Partial Approval WILLIAM MICHALAK
BUILDING-Rough-Frame 7/21/2022 Corrections Issued GLEN RAND
BUILDING-Rough-Frame 7/28/2022 Partial Approval GLEN RAND
BUILDING-Rough-Frame 8/19/2022 Corrections Issued GLEN RAND
ELECTRICAL-Rough 8/19/2022 Corrections Issued GLEN RAND
HVAC-Rough 8/19/2022 Corrections Issued GLEN RAND
PLUMBING-Rough 8/19/2022 Corrections Issued GLEN RAND
BUILDING-Rough-Frame 8/25/2022 Corrections Issued GLEN RAND
ELECTRICAL-Rough 8/25/2022 Corrections Issued GLEN RAND
HVAC-Rough 8/25/2022 Corrections Issued GLEN RAND
PLUMBING-Rough 8/25/2022 Corrections Issued GLEN RAND
BUILDING-Rough-Frame 3/7/2023 Approved GLEN RAND
ELECTRICAL-Rough 3/7/2023 Approved GLEN RAND
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Approved GLEN RAND
HVAC-Rough 3/7/2023 Approved GLEN RAND
PLUMBING-Rough 3/7/2023 Approved GLEN RAND
Underground Mechanical 3/13/2023 Approved GLEN RAND
Insulation 3/17/2023 Approved GLEN RAND
Interior/Exterior Lathing 3/17/2023 Approved GLEN RAND
Drywall Nailing 3/23/2023 Approved GLEN RAND
Interior/Exterior Lathing 4/11/2023 Approved GLEN RAND
Interior/Exterior Lathing 4/24/2023 Approved GLEN RAND
SGSOV-Seismic Gas S/O Valve 5/12/2023 SGSOV Not Ready GLEN RAND
Final 5/16/2023 Corrections Issued GLEN RAND
SGSOV-Seismic Gas S/O Valve 5/16/2023 SGSOV Approved GLEN RAND
Smoke Detectors 5/16/2023 Approved GLEN RAND
Final 7/27/2023 Corrections Issued GLEN RAND
Final 8/15/2023 OK to Issue CofO GLEN RAND