2715 N BENEDICT ST 90039
Certificate Information: 2715 N BENEDICT ST 90039
- Application / Permit
- 19014-10000-02757
- Plan Check / Job No.
- B19LA10766
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING. , ( add bedroom, bathroom, w-i-c, laundry room and enlarge/ remodel kitchen.
- Permit Issued
- Issued on 8/27/2020
- Issuing Office
- Current Status
- CofO Issued on 7/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2019 | LAMAR DAVIS |
| Corrections Issued | 5/24/2019 | LAMAR DAVIS |
| Plan Check Approved | 7/18/2019 | SAM CHANG |
| Issued | 8/27/2020 | APPLICANT |
| Building Plans Picked Up | 9/4/2020 | APPLICANT |
| CofO in Progress | 7/20/2021 | KATHRYN BUTTERWORTH |
| Permit Finaled | 7/27/2021 | DEROLD HAUFF |
| CofO Issued | 7/27/2021 | DEROLD HAUFF |
| Permit Finaled | 7/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/2/2019 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 7/11/2019 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 7/11/2019 | ADRIAN SANCHEZ |
| ZI | Cleared | 7/11/2019 | ANNA VAN |
Contact Information
| Contractor | Av Design Build Construction; Lic. No.: 1033230-B | 4654 E AVE S UNIT B116 PALMDALE, CA 93552 |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/24/2020 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 10/5/2020 | Corrections Issued | CRAIG VAUGHAN |
| Piling/Pier/Caisson | 10/13/2020 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 10/30/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Insulation | 11/2/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 11/2/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Wood Frame | 11/2/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2020 | Not Ready for Inspection | COREY HUPP |
| Insulation | 11/5/2020 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 12/22/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 12/22/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 12/22/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 12/30/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2020 | Approved | HAMIK HARTOUNIAN |
| MERV13>=Rough | 12/30/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 1/6/2021 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 1/11/2021 | Approved | SCOTT FINNILA |
| Insulation | 1/14/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 1/14/2021 | Partial Approval | COREY HUPP |
| Drywall Nailing | 1/25/2021 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 2/2/2021 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 2/19/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 4/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 4/23/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/23/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 4/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 4/23/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 4/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 4/23/2021 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Service/Power Release | 4/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Smoke Detectors | 4/23/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 5/6/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 5/6/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Gas Test | 5/6/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 5/6/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 5/6/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 5/6/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 6/15/2021 | Corrections Issued | RICHARD STEINBACH |
| Service/Power Release | 6/15/2021 | Approved | RICHARD STEINBACH |
| Final | 7/16/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Final | 7/20/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |