727-729 S GRAMERCY PL 90005

Certificate Information: 727-729 S GRAMERCY PL 90005

Application / Permit
19014-10000-02716
Plan Check / Job No.
B19LA10642
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Remove majority of interior and portion of area at rear; reconfigure to add irregular shape 84.2' x 32.25' 2nd floor for new unit, recreation room and add 22.25' x 19' attached carport at rear under 2nd floor. All works are per design
Permit Issued
Issued on 11/19/2019
Issuing Office
Metro
Current Status
CofO Issued on 8/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/22/2019 APPLICANT
Green Plans Picked Up 6/5/2019 APPLICANT
Assigned to Plan Check Engineer 6/13/2019 ALDOUS CHIC
Corrections Issued 6/17/2019 ALDOUS CHIC
Quality Review Completed 6/18/2019 ABDUL CHEGENI
Building Plans Picked Up 6/21/2019 APPLICANT
Plan Check Approved 10/3/2019 ALDOUS CHIC
Issued 11/19/2019 LADBS
CofO in Progress 12/11/2020 CHRIS CHRISTENSEN
Permit Finaled 8/4/2021 DEROLD HAUFF
Permit Finaled 8/4/2021 DEROLD HAUFF
CofO Issued 8/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/6/2019 JEANETTE VONG
Highway dedication Cleared 8/6/2019 JEANETTE VONG
Low Impact Development Cleared 9/10/2019 ORVAL HERNANDEZ-MARCI
Frnt yard landscape/Water mgmt Cleared 9/11/2019 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 9/20/2019 JEANETTE VONG
Hydrant and Access approval Cleared 9/20/2019 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 9/20/2019 JEANETTE VONG
Sewer availability Cleared 9/20/2019 JEANETTE VONG
Green Code Cleared 10/1/2019 NEGAR NEJAD

Contact Information

Contractor Owner-Builder       ,
Engineer Yu,, Kunyoung; Lic. No.: C66880 22812 ERIEL AVE      TORRANCE, CA 90505

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/22/2020 Corrections Issued HORACE FULTZ
Footing/Foundation/Slab 1/28/2020 Corrections Issued LUIS BARRALES
Excavation/Setback/Form/Re-Bar 2/3/2020 Partial Approval LUIS BARRALES
Pre-Inspection 2/25/2020 Corrections Issued ARTHUR SARGSYAN
Footing/Foundation/Slab 3/3/2020 Corrections Issued BRAD BESCOS
Excavation/Setback/Form/Re-Bar 3/5/2020 Approved BRAD BESCOS
Green Building Rough 3/5/2020 Not Ready for Inspection BRAD BESCOS
Footing/Foundation/Slab 4/23/2020 Conditional Approval SCOTT FINNILA
PLUMBING-Rough 4/27/2020 Partial Approval ARTHUR SARGSYAN
Footing/Foundation/Slab 4/30/2020 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/4/2020 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 5/4/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Partial Approval CHRIS CHRISTENSEN
Green Building Rough 5/15/2020 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/2/2020 Partial Approval ARTHUR SARGSYAN
Green Building Rough 6/2/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 6/11/2020 Approved ARTHUR SARGSYAN
Pre-Inspection 6/15/2020 Partial Approval ARTHUR SARGSYAN
ELECTRICAL-Rough 6/18/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 6/18/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 6/18/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 6/23/2020 Approved CHRIS CHRISTENSEN
Insulation 6/30/2020 Approved THOMAS LOGRASSO
Drywall Nailing 7/8/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Partial Approval CHRIS CHRISTENSEN
PLUMBING-Final 7/13/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 7/22/2020 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 9/8/2020 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Final 9/10/2020 Corrections Issued CHRIS CHRISTENSEN
Final 9/10/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/10/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 9/10/2020 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 9/10/2020 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 9/10/2020 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Final 9/16/2020 Approved CHRIS CHRISTENSEN
Footing/Foundation/Slab 9/16/2020 Partial Approval CHRIS CHRISTENSEN
HVAC-Final 9/16/2020 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 9/16/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 9/29/2020 Approved CHRIS CHRISTENSEN
Green Building Final 10/5/2020 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 10/5/2020 Approved CHRIS CHRISTENSEN
Service/Power Release 10/5/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 10/21/2020 Corrections Issued JOSEPH MCGARRY
PLUMBING-Final 10/27/2020 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 11/2/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Final 11/2/2020 Approved CHRIS CHRISTENSEN
Final 11/4/2020 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 11/4/2020 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 11/4/2020 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 11/4/2020 Approved JOSEPH MCGARRY
Final 11/13/2020 Conditional Approval CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/13/2020 SGSOV Approved CHRIS CHRISTENSEN
Final 12/11/2020 OK to Issue CofO CHRIS CHRISTENSEN
Special/Order Compliance 12/24/2020 Corrections Issued CHRIS CHRISTENSEN