727-729 S GRAMERCY PL 90005
Certificate Information: 727-729 S GRAMERCY PL 90005
- Application / Permit
- 19014-10000-02716
- Plan Check / Job No.
- B19LA10642
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- Remove majority of interior and portion of area at rear; reconfigure to add irregular shape 84.2' x 32.25' 2nd floor for new unit, recreation room and add 22.25' x 19' attached carport at rear under 2nd floor. All works are per design
- Permit Issued
- Issued on 11/19/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2019 | APPLICANT |
| Green Plans Picked Up | 6/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | ALDOUS CHIC |
| Corrections Issued | 6/17/2019 | ALDOUS CHIC |
| Quality Review Completed | 6/18/2019 | ABDUL CHEGENI |
| Building Plans Picked Up | 6/21/2019 | APPLICANT |
| Plan Check Approved | 10/3/2019 | ALDOUS CHIC |
| Issued | 11/19/2019 | LADBS |
| CofO in Progress | 12/11/2020 | CHRIS CHRISTENSEN |
| Permit Finaled | 8/4/2021 | DEROLD HAUFF |
| Permit Finaled | 8/4/2021 | DEROLD HAUFF |
| CofO Issued | 8/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2019 | JEANETTE VONG |
| Highway dedication | Cleared | 8/6/2019 | JEANETTE VONG |
| Low Impact Development | Cleared | 9/10/2019 | ORVAL HERNANDEZ-MARCI |
| Frnt yard landscape/Water mgmt | Cleared | 9/11/2019 | ANNA VIDAL |
| Eng Process Fee Ord 176,300 | Cleared | 9/20/2019 | JEANETTE VONG |
| Hydrant and Access approval | Cleared | 9/20/2019 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 9/20/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 9/20/2019 | JEANETTE VONG |
| Green Code | Cleared | 10/1/2019 | NEGAR NEJAD |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yu,, Kunyoung; Lic. No.: C66880 | 22812 ERIEL AVE TORRANCE, CA 90505 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/22/2020 | Corrections Issued | HORACE FULTZ |
| Footing/Foundation/Slab | 1/28/2020 | Corrections Issued | LUIS BARRALES |
| Excavation/Setback/Form/Re-Bar | 2/3/2020 | Partial Approval | LUIS BARRALES |
| Pre-Inspection | 2/25/2020 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 3/3/2020 | Corrections Issued | BRAD BESCOS |
| Excavation/Setback/Form/Re-Bar | 3/5/2020 | Approved | BRAD BESCOS |
| Green Building Rough | 3/5/2020 | Not Ready for Inspection | BRAD BESCOS |
| Footing/Foundation/Slab | 4/23/2020 | Conditional Approval | SCOTT FINNILA |
| PLUMBING-Rough | 4/27/2020 | Partial Approval | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 4/30/2020 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/4/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 5/4/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 5/15/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/2/2020 | Partial Approval | ARTHUR SARGSYAN |
| Green Building Rough | 6/2/2020 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 6/11/2020 | Approved | ARTHUR SARGSYAN |
| Pre-Inspection | 6/15/2020 | Partial Approval | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 6/18/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 6/18/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 6/23/2020 | Approved | CHRIS CHRISTENSEN |
| Insulation | 6/30/2020 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 7/8/2020 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2020 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Final | 7/13/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 7/22/2020 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/8/2020 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 9/10/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 9/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 9/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/10/2020 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/10/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 9/16/2020 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/16/2020 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Final | 9/16/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 9/16/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 9/29/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 10/5/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 10/5/2020 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 10/5/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 10/21/2020 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 10/27/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 11/2/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/2/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 11/4/2020 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 11/4/2020 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 11/4/2020 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 11/4/2020 | Approved | JOSEPH MCGARRY |
| Final | 11/13/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/13/2020 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 12/11/2020 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Special/Order Compliance | 12/24/2020 | Corrections Issued | CHRIS CHRISTENSEN |