1001-1003 E 74TH ST 90001
Certificate Information: 1001-1003 E 74TH ST 90001
- Application / Permit
- 19014-10000-02713
- Plan Check / Job No.
- B19LA10640
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- FOR PROPOSED REAR ADDITION TO (E) DUPLEX
- Permit Issued
- Issued on 12/11/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2019 | SAMUEL GONZALEZ |
| Corrections Issued | 6/28/2019 | SAMUEL GONZALEZ |
| Green Plans Picked Up | 6/28/2019 | APPLICANT |
| Quality Review Completed | 7/19/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 7/22/2019 | APPLICANT |
| Plan Check Approved | 4/15/2020 | SAMUEL GONZALEZ |
| Issued | 12/11/2023 | APPLICANT |
| CofO in Progress | 2/13/2025 | MICHAEL LEWIS |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
| CofO Issued | 2/14/2025 | DEROLD HAUFF |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 7/29/2019 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2019 | KARAN PATEL |
| Sewer availability | Cleared | 8/1/2019 | KARAN PATEL |
| Low Impact Development | Cleared | 9/5/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 9/5/2019 | JEANETTE VONG |
| Green Code | Cleared | 9/25/2019 | COLIN LOREDO |
| Housing rent stabilization | Cleared | 11/30/2023 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/18/2024 | Corrections Issued | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 2/23/2024 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 2/23/2024 | Conditional Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 3/29/2024 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2024 | Partial Approval | MICHAEL LEWIS |
| PLUMBING-Rough | 4/5/2024 | Approved | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2024 | Partial Approval | MICHAEL LEWIS |
| Insulation | 4/16/2024 | Partial Approval | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/1/2024 | Corrections Issued | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 7/1/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| ELECTRICAL-Rough | 7/9/2024 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 7/9/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 7/9/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 7/11/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 7/11/2024 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/11/2024 | Approved | MICHAEL LEWIS |
| Shower Pan | 7/11/2024 | Approved | MICHAEL LEWIS |
| Insulation | 7/15/2024 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 7/22/2024 | Approved | MICHAEL LEWIS |
| Final | 12/3/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 12/3/2024 | Approved | MICHAEL LEWIS |
| Green Building Final | 12/3/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/3/2024 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 12/3/2024 | Approved | MICHAEL LEWIS |
| Final | 2/12/2025 | OK to Issue CofO | JOHN QUINTANILLA |