917 E BURR ST 90032
Certificate Information: 917 E BURR ST 90032
- Application / Permit
- 19014-10000-02675
- Plan Check / Job No.
- B19LA10461
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (1,200 SQFT.) 2-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 10/7/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2019 | APPLICANT |
| Green Plans Picked Up | 6/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2019 | ADAM HEGAZI |
| Corrections Issued | 6/10/2019 | ADAM HEGAZI |
| Quality Review Completed | 6/19/2019 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 6/21/2019 | APPLICANT |
| Plan Check Approved | 10/7/2019 | ADAM HEGAZI |
| Issued | 10/7/2019 | LADBS |
| CofO in Progress | 12/14/2020 | COREY HUPP |
| CofO in Progress | 12/14/2020 | COREY HUPP |
| Permit Finaled | 12/17/2020 | DEROLD HAUFF |
| CofO Issued | 12/17/2020 | DEROLD HAUFF |
| Permit Finaled | 12/17/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/21/2019 | PATRICK MISCHLICH |
| Address approval | Cleared | 8/15/2019 | KAREN LE |
| BHO/Hillside ordinance | Cleared | 8/15/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 8/15/2019 | CELINA MORENO |
| BHO/Hillside ordinance | Cleared | 8/15/2019 | KAREN LE |
| Eng Process Fee Ord 176,300 | Cleared | 8/15/2019 | KAREN LE |
| Grading Pre-Inspection | Cleared | 8/15/2019 | PATRICK MISCHLICH |
| Green Code | Cleared | 8/15/2019 | COLIN LOREDO |
| Hydrant and Access approval | Cleared | 8/15/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 8/15/2019 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 8/15/2019 | KAREN LE |
| Sewer availability | Cleared | 8/15/2019 | KAREN LE |
| "D" conditions | Cleared | 8/26/2019 | JOE LUCKEY |
| "Q" conditions | Cleared | 8/26/2019 | JOE LUCKEY |
| GPI Written Notices | Cleared | 8/26/2019 | ARMEN JIVALAGIAN |
| ZI | Cleared | 8/26/2019 | JOE LUCKEY |
Contact Information
| Contractor | Sarmiento Construction; Lic. No.: 819153-B | 13012 WELBY WAY NORTH HOLLYWOOD, CA 91606 |
| Engineer | Chan,, Albert Fong; Lic. No.: C61343 | 2261 PEPPERWOOD LN CORONA, CA 92882 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 11/26/2019 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 12/6/2019 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 12/13/2019 | Partial Approval | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/16/2020 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 1/16/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 1/16/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/6/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 3/6/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 3/6/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/31/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 3/31/2020 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 3/31/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 4/29/2020 | Corrections Issued | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 4/29/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 4/29/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 4/29/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 4/29/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/6/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 5/6/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Rough | 5/6/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 5/6/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Verify Sprinkler Sign Off | 5/6/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 5/11/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/11/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 5/11/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/14/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 5/14/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 5/14/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 5/19/2020 | Corrections Issued | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 5/19/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 5/27/2020 | Corrections Issued | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 5/27/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 6/2/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/5/2020 | Partial Approval | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 6/5/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 6/9/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/9/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 11/4/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 11/4/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 11/4/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 11/4/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 11/4/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Final | 11/4/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2020 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Service/Power Release | 11/4/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/4/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Verify Sprinkler Sign Off | 11/4/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 11/13/2020 | Approved | OSVALDO PARAMO |
| Final | 11/13/2020 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 11/13/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 11/13/2020 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 11/13/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 11/13/2020 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 11/13/2020 | Approved | OSVALDO PARAMO |
| Final | 12/2/2020 | OK to Issue CofO | COREY HUPP |
| Green Building Final | 12/2/2020 | Approved | COREY HUPP |
| Service/Power Release | 12/2/2020 | Approved | COREY HUPP |