10772 W TABOR ST 90034
Certificate Information: 10772 W TABOR ST 90034
- Application / Permit
- 19014-10000-02670
- Plan Check / Job No.
- B19LA10425
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION AT REAR TO AN (E) 1-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED (1)-CAR GARAGE.
- Permit Issued
- Issued on 3/9/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2019 | KEVIN MORALES |
| Corrections Issued | 5/21/2019 | KEVIN MORALES |
| Plan Check Approved | 5/21/2019 | KEVIN MORALES |
| Issued | 3/9/2020 | LADBS |
| Permit Finaled | 9/24/2024 | RICHARD STEINBACH |
| CofO Issued | 9/24/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/24/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/21/2019 | ELAINE LEI |
| Grading Pre-Inspection | Cleared | 5/21/2019 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 5/21/2019 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chan,, Albert Fong; Lic. No.: C61343 | 2261 PEPPERWOOD LN CORONA, CA 92882 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/17/2020 | Approved | EVAN COOPER |
| Special/Order Compliance | 4/17/2020 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 4/30/2020 | Partial Approval | EVAN COOPER |
| Green Building Rough | 4/30/2020 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 4/30/2020 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 5/13/2020 | Partial Approval | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 5/13/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 5/13/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/13/2020 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/11/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 6/15/2020 | Approved | JUSTIN CURTIS |
| Shower Pan | 6/15/2020 | Approved | JUSTIN CURTIS |
| Drywall Nailing | 6/19/2020 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 6/19/2020 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 6/19/2020 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 8/17/2020 | Approved | OGANES TARAKHCHYAN |
| Final | 8/17/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Final | 8/17/2020 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 8/17/2020 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 8/17/2020 | Approved | OGANES TARAKHCHYAN |