10772 W TABOR ST 90034

Certificate Information: 10772 W TABOR ST 90034

Application / Permit
19014-10000-02670
Plan Check / Job No.
B19LA10425
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION AT REAR TO AN (E) 1-STORY SINGLE FAMILY RESIDENCE WITH ATTACHED (1)-CAR GARAGE.
Permit Issued
Issued on 3/9/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2019 APPLICANT
Assigned to Plan Check Engineer 5/21/2019 KEVIN MORALES
Corrections Issued 5/21/2019 KEVIN MORALES
Plan Check Approved 5/21/2019 KEVIN MORALES
Issued 3/9/2020 LADBS
Permit Finaled 9/24/2024 RICHARD STEINBACH
CofO Issued 9/24/2024 RICHARD STEINBACH
Permit Finaled 9/24/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/21/2019 ELAINE LEI
Grading Pre-Inspection Cleared 5/21/2019 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 5/21/2019 ELAINE LEI

Contact Information

Contractor Owner-Builder       ,
Engineer Chan,, Albert Fong; Lic. No.: C61343 2261 PEPPERWOOD LN      CORONA, CA 92882

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2020 Approved EVAN COOPER
Special/Order Compliance 4/17/2020 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/27/2020 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/30/2020 Partial Approval EVAN COOPER
Green Building Rough 4/30/2020 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 4/30/2020 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 5/13/2020 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 5/13/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 5/13/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 5/13/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/11/2020 Partial Approval OGANES TARAKHCHYAN
Insulation 6/15/2020 Approved JUSTIN CURTIS
Shower Pan 6/15/2020 Approved JUSTIN CURTIS
Drywall Nailing 6/19/2020 Approved OGANES TARAKHCHYAN
Green Building Rough 6/19/2020 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/19/2020 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/17/2020 Approved OGANES TARAKHCHYAN
Final 8/17/2020 Partial Approval OGANES TARAKHCHYAN
Green Building Final 8/17/2020 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/17/2020 SGSOV Approved OGANES TARAKHCHYAN
Smoke Detectors 8/17/2020 Approved OGANES TARAKHCHYAN