2666 N PIRTLE ST 90039
Certificate Information: 2666 N PIRTLE ST 90039
- Application / Permit
- 19014-10000-02623
- Plan Check / Job No.
- B19LA10295
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 STORY GROUND FLOOR ADDITION TO (E) 1 STORY SFD
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 7/11/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 7/23/2019 | KESETE HAREGOT |
| Building Plans Picked Up | 7/25/2019 | APPLICANT |
| Green Plans Picked Up | 7/25/2019 | APPLICANT |
| Plan Check Approved | 9/27/2019 | SERGIO GUTIERREZ |
| Issued | 1/24/2020 | LADBS |
| CofO in Progress | 8/27/2020 | STUART CHAPMAN |
| Permit Finaled | 9/23/2020 | DEROLD HAUFF |
| CofO Issued | 9/23/2020 | DEROLD HAUFF |
| Permit Finaled | 9/23/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| ZI | Cleared | 8/14/2019 | SOPHIE GABEL-SCHEINBAU |
| Low Impact Development | Cleared | 9/6/2019 | ORVAL HERNANDEZ-MARCI |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2019 | JEANETTE VONG |
| Green Code | Cleared | 9/13/2019 | DONALD CRICHLOW |
| Hydrant and Access approval | Cleared | 9/13/2019 | JEREMY CARTER |
| Roof/Waste drainage to street | Cleared | 9/13/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 9/13/2019 | JEANETTE VONG |
| Stormwater Pollution Mitigatn | Cleared | 9/19/2019 | RYAN HUDSON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/25/2020 | Not Ready for Inspection | AJA COLLAY |
| Excavation/Setback/Form/Re-Bar | 3/4/2020 | Conditional Approval | AJA COLLAY |
| Footing/Foundation/Slab | 3/4/2020 | Conditional Approval | AJA COLLAY |
| BUILDING-Rough-Frame | 3/13/2020 | Partial Approval | AJA COLLAY |
| PLUMBING-Rough | 3/13/2020 | Partial Approval | AJA COLLAY |
| Insulation | 3/19/2020 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2020 | Conditional Approval | RUBEN SALAS |
| ELECTRICAL-Rough | 4/30/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 4/30/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 5/5/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 5/5/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 5/5/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 5/11/2020 | Conditional Approval | MATTHEW NUCKOLLS |
| Wood Frame | 5/11/2020 | Approved | MATTHEW NUCKOLLS |
| Insulation | 5/19/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/19/2020 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 5/26/2020 | Approved | THOMAS LOGRASSO |
| Shower Pan | 5/26/2020 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 5/29/2020 | Approved | THOMAS LOGRASSO |
| Final | 7/29/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| HVAC-Final | 7/29/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 7/29/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/3/2020 | Approved | STUART CHAPMAN |
| Final | 8/3/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 8/3/2020 | Approved | STUART CHAPMAN |
| Green Building Final | 8/3/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 8/3/2020 | Approved | STUART CHAPMAN |
| MERV13>=Final | 8/3/2020 | Not Ready for Inspection | STUART CHAPMAN |
| MERV13>=Rough | 8/3/2020 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/3/2020 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 8/3/2020 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 8/26/2020 | Approved | STUART CHAPMAN |
| Final | 8/26/2020 | Conditional Approval | STUART CHAPMAN |
| HVAC-Final | 8/26/2020 | Approved | STUART CHAPMAN |
| MERV13>=Final | 8/26/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 8/26/2020 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/26/2020 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 8/26/2020 | Approved | STUART CHAPMAN |