2666 N PIRTLE ST 90039

Certificate Information: 2666 N PIRTLE ST 90039

Application / Permit
19014-10000-02623
Plan Check / Job No.
B19LA10295
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 STORY GROUND FLOOR ADDITION TO (E) 1 STORY SFD
Permit Issued
Issued on 1/24/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2019 APPLICANT
Assigned to Plan Check Engineer 6/20/2019 SERGIO GUTIERREZ
Corrections Issued 7/11/2019 SERGIO GUTIERREZ
Quality Review Completed 7/23/2019 KESETE HAREGOT
Building Plans Picked Up 7/25/2019 APPLICANT
Green Plans Picked Up 7/25/2019 APPLICANT
Plan Check Approved 9/27/2019 SERGIO GUTIERREZ
Issued 1/24/2020 LADBS
CofO in Progress 8/27/2020 STUART CHAPMAN
Permit Finaled 9/23/2020 DEROLD HAUFF
CofO Issued 9/23/2020 DEROLD HAUFF
Permit Finaled 9/23/2020 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 8/14/2019 SOPHIE GABEL-SCHEINBAU
Low Impact Development Cleared 9/6/2019 ORVAL HERNANDEZ-MARCI
Eng Process Fee Ord 176,300 Cleared 9/13/2019 JEANETTE VONG
Green Code Cleared 9/13/2019 DONALD CRICHLOW
Hydrant and Access approval Cleared 9/13/2019 JEREMY CARTER
Roof/Waste drainage to street Cleared 9/13/2019 JEANETTE VONG
Sewer availability Cleared 9/13/2019 JEANETTE VONG
Stormwater Pollution Mitigatn Cleared 9/19/2019 RYAN HUDSON

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/25/2020 Not Ready for Inspection AJA COLLAY
Excavation/Setback/Form/Re-Bar 3/4/2020 Conditional Approval AJA COLLAY
Footing/Foundation/Slab 3/4/2020 Conditional Approval AJA COLLAY
BUILDING-Rough-Frame 3/13/2020 Partial Approval AJA COLLAY
PLUMBING-Rough 3/13/2020 Partial Approval AJA COLLAY
Insulation 3/19/2020 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Conditional Approval RUBEN SALAS
ELECTRICAL-Rough 4/30/2020 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 4/30/2020 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/5/2020 Approved KATHRYN BUTTERWORTH
HVAC-Rough 5/5/2020 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 5/5/2020 Approved KATHRYN BUTTERWORTH
HVAC-Rough 5/11/2020 Conditional Approval MATTHEW NUCKOLLS
Wood Frame 5/11/2020 Approved MATTHEW NUCKOLLS
Insulation 5/19/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/19/2020 Approved THOMAS LOGRASSO
Drywall Nailing 5/26/2020 Approved THOMAS LOGRASSO
Shower Pan 5/26/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 5/29/2020 Approved THOMAS LOGRASSO
Final 7/29/2020 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Final 7/29/2020 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Final 7/29/2020 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/3/2020 Approved STUART CHAPMAN
Final 8/3/2020 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 8/3/2020 Approved STUART CHAPMAN
Green Building Final 8/3/2020 Approved STUART CHAPMAN
Green Building Rough 8/3/2020 Approved STUART CHAPMAN
MERV13>=Final 8/3/2020 Not Ready for Inspection STUART CHAPMAN
MERV13>=Rough 8/3/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/3/2020 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 8/3/2020 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 8/26/2020 Approved STUART CHAPMAN
Final 8/26/2020 Conditional Approval STUART CHAPMAN
HVAC-Final 8/26/2020 Approved STUART CHAPMAN
MERV13>=Final 8/26/2020 Approved STUART CHAPMAN
PLUMBING-Final 8/26/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/26/2020 SGSOV Approved STUART CHAPMAN
Smoke Detectors 8/26/2020 Approved STUART CHAPMAN