823 S LORRAINE BLVD 90005

Certificate Information: 823 S LORRAINE BLVD 90005

Application / Permit
19014-10000-02550
Plan Check / Job No.
B19LA09931
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
15'-0" X 27'-0" ADDITION TO AND CONVERT EXISTING DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 3/20/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2019 APPLICANT
Assigned to Plan Check Engineer 6/7/2019 JEROME MAGAT PALMA
Corrections Issued 6/10/2019 JEROME MAGAT PALMA
Quality Review Completed 6/10/2019 ABDUL CHEGENI
Green Plans Picked Up 7/11/2019 APPLICANT
Applicant returned to address corrections 7/25/2019 JEROME MAGAT PALMA
Plan Check Approved 10/17/2019 JEROME MAGAT PALMA
Issued 3/20/2020 LADBS
Building Plans Picked Up 8/4/2021 APPLICANT
CofO in Progress 5/3/2024 JEFFREY MEAD
Permit Finaled 5/9/2024 DEROLD HAUFF
CofO Issued 5/9/2024 DEROLD HAUFF
Permit Finaled 5/9/2024 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 6/12/2019 BRADLEY FURUYA
Address approval Cleared 7/18/2019 ELAINE LEI
Green Code Cleared 7/18/2019 SARAH ABOULHOSN
Construction near power lines Cleared 8/29/2019 RIDWAN HARDY
Construction within easement Cleared 8/29/2019 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 10/15/2019 GUILLERMO PETRA
Sewer availability Cleared 10/15/2019 GUILLERMO PETRA
Hydrant and Access approval Cleared 10/17/2019 GEORGE SUCHAND
Low Impact Development Cleared 10/17/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/17/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,
Engineer Kim,, Taewon; Lic. No.: C80632 28000 S WESTERN AVE UNIT 209      SAN PEDRO, CA 90732

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/23/2020 Approved CHRIS CHRISTENSEN
Sewer 10/13/2020 Approved CHRIS CHRISTENSEN
Sewer 10/21/2020 Approved CHRIS CHRISTENSEN
Underground Mechanical 10/21/2020 Approved CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 10/23/2020 Approved ARTHUR SARGSYAN
Excavation/Setback/Form/Re-Bar 10/30/2020 Corrections Issued CHRIS CHRISTENSEN
Excavation/Setback/Form/Re-Bar 11/9/2020 Not Ready for Inspection DONALD CRICHLOW
Footing/Foundation/Slab 11/9/2020 Not Ready for Inspection DONALD CRICHLOW
METHANE-Barrier 11/9/2020 Not Ready for Inspection DONALD CRICHLOW
METHANE-Subgrade 11/9/2020 Not Ready for Inspection DONALD CRICHLOW
Pre-Inspection 11/16/2020 Approved CHRIS CHRISTENSEN
Deputy Drilled-In Anchors 1/25/2023 Partial Approval JEFFREY MEAD
BUILDING-Rough-Frame 5/2/2024 Approved JEFFREY MEAD
Final 5/2/2024 OK to Issue CofO JEFFREY MEAD
Footing/Foundation/Slab 5/2/2024 Approved JEFFREY MEAD
Green Building Final 5/2/2024 Approved JEFFREY MEAD
Green Building Rough 5/2/2024 Approved JEFFREY MEAD
METHANE-Barrier 5/2/2024 Approved JEFFREY MEAD
METHANE-Final 5/2/2024 Approved JEFFREY MEAD
METHANE-Rough 5/2/2024 Approved JEFFREY MEAD
METHANE-Subgrade 5/2/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 5/2/2024 SGSOV Approved JEFFREY MEAD
Smoke Detectors 5/2/2024 Approved JEFFREY MEAD