3960 W WILSHIRE BLVD FLR 1-5 90010
Certificate Information: 3960 W WILSHIRE BLVD FLR 1-5 90010
- Application / Permit
- 19014-10000-02543
- Plan Check / Job No.
- B19LA09903
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT TO (E) 5 STORY OFFICE BUILDING BUILDOUT CORE & CHELL
- Permit Issued
- Issued on 1/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2019 | APPLICANT |
| Green Plans Picked Up | 5/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | HERNAN ARREOLA |
| Corrections Issued | 7/1/2019 | HERNAN ARREOLA |
| Quality Review Completed | 7/1/2019 | SIAVOSH POURSABAHIAN |
| Disabled Access Plans Picked Up | 7/22/2019 | APPLICANT |
| Applicant returned to address corrections | 8/6/2019 | HERNAN ARREOLA |
| Applicant returned to address corrections | 9/3/2019 | HERNAN ARREOLA |
| Plan Check Approved | 2/27/2020 | HERNAN ARREOLA |
| Issued | 1/19/2021 | APPLICANT |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| CofO in Progress | 8/15/2023 | KATY RAMIREZ |
| CofO Issued | 8/15/2023 | ERNESTO CORRAL |
| Permit Finaled | 8/15/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/19/2019 | ERIK BEASLEY |
| ZA Case | Cleared | 7/19/2019 | SOPHIE GABEL-SCHEINBAU |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2019 | KAREN LE |
| Project located in CRA area | Cleared | 7/25/2019 | JIM URQUHART |
| Green Code | Cleared | 7/31/2019 | KHEDER ALRAZAA |
| Hydrant and Access approval | Cleared | 8/1/2019 | GEORGE SUCHAND |
| Metro Rail approval | Cleared | 8/9/2019 | EDDI ZEPEDA |
| Highway dedication | Cleared | 8/14/2019 | JAMES MORALEZ |
| DAS Clearance | Cleared | 8/28/2019 | HERNAN ARREOLA |
Contact Information
| Architect | Rios,, Mark William; Lic. No.: C15744 | 639 N LARCHMONT BLVD SUITE 100 LOS ANGELES, CA 90004 |
| Contractor | De Meo Construction; Lic. No.: 782851-B | 11816 JUNIETTE STREET CULVER CITY, CA 90230 |
| Engineer | Mahjoub,, Nina Azadeh; Lic. No.: C78947 | 21400 BURBANK BLVD 114 WOODLAND HILLS, CA 91367 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/2/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 2/22/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 3/5/2021 | Partial Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 3/10/2021 | Partial Approval | TIMOTHY BUXTON |
| Wood Frame | 3/12/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 3/15/2021 | Partial Approval | TIMOTHY BUXTON |
| Pre-Inspection | 3/22/2021 | Approved | TIMOTHY BUXTON |
| Wood Frame | 4/7/2021 | Partial Approval | TIMOTHY BUXTON |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Partial Approval | TIMOTHY BUXTON |
| Insulation | 5/7/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 5/11/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 5/17/2021 | Partial Approval | TIMOTHY BUXTON |
| Footing/Foundation/Slab | 6/7/2021 | Partial Approval | TIMOTHY BUXTON |
| Pre-Inspection | 6/7/2021 | Approved | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 6/23/2021 | Partial Approval | TIMOTHY BUXTON |
| Drywall Nailing | 7/12/2021 | Partial Approval | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 7/28/2021 | Approved | TIMOTHY BUXTON |
| Light Gage Steel Frame | 8/9/2021 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 8/16/2021 | Approved | DANIEL COLLINS |
| Drywall Nailing | 8/18/2021 | Partial Approval | DANIEL COLLINS |
| Drywall Nailing | 8/24/2021 | Partial Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 8/31/2021 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 9/3/2021 | Partial Approval | KATY RAMIREZ |
| Drywall Nailing | 9/13/2021 | Partial Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 9/13/2021 | Approved | JONATHAN QUACH |
| Drywall Nailing | 9/20/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/1/2021 | Partial Inspection | KATY RAMIREZ |
| Interior/Exterior Lathing | 11/3/2021 | Partial Approval | KATY RAMIREZ |
| Light Gage Steel Frame | 5/13/2022 | Not Ready for Inspection | KATY RAMIREZ |
| Pre-Inspection | 1/9/2023 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/27/2023 | Partial Approval | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 7/11/2023 | Partial Approval | ALFREDO LOPEZ |
| Final | 8/2/2023 | Partial Inspection | KATY RAMIREZ |
| Smoke Detectors | 8/2/2023 | Not Ready for Inspection | KATY RAMIREZ |
| Final | 8/8/2023 | Partial Inspection | KATY RAMIREZ |
| Green Building Final | 8/8/2023 | Approved | KATY RAMIREZ |
| Green Building Rough | 8/8/2023 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Approved | KATY RAMIREZ |
| Smoke Detectors | 8/8/2023 | Approved | KATY RAMIREZ |
| Final | 8/15/2023 | OK to Issue CofO | KATY RAMIREZ |