1516 S LINCOLN BLVD 90291
Certificate Information: 1516 S LINCOLN BLVD 90291
- Application / Permit
- 19014-10000-02511
- Plan Check / Job No.
- B19LA09716
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ADDITION & REMODEL TO EXISTING 1-STORY (SPRINKLERED) RETAIL STORE. RE-STRIPE PARKING AREA.
- Permit Issued
- Issued on 3/8/2021
- Issuing Office
- Current Status
- CofO Issued on 6/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2019 | PRANITA SHAH |
| Corrections Issued | 6/20/2019 | PRANITA SHAH |
| Quality Review Completed | 6/21/2019 | TU HUA |
| Building Plans Picked Up | 6/25/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 9/11/2019 | APPLICANT |
| Applicant returned to address corrections | 11/21/2020 | PRANITA SHAH |
| Green Plans Picked Up | 12/23/2020 | APPLICANT |
| Plan Check Approved | 3/5/2021 | PRANITA SHAH |
| Issued | 3/8/2021 | APPLICANT |
| CofO in Progress | 5/25/2021 | SORIN CIRSTOIU |
| No Progress | 5/25/2021 | SORIN CIRSTOIU |
| CofO in Progress | 5/26/2021 | SORIN CIRSTOIU |
| Permit Finaled | 6/2/2021 | TED RIES |
| CofO Issued | 6/2/2021 | TED RIES |
| Permit Finaled | 6/2/2021 | TED RIES |
Permit Application Clearance Information
| Miscellaneous | Cleared | 6/26/2019 | ANNA VAN |
| Green Code | Cleared | 10/29/2019 | KHEDER ALRAZAA |
| Low Impact Development | Cleared | 4/22/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 4/23/2020 | CECILIO NAVARRO |
| Highway dedication | Cleared | 4/30/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 7/16/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2020 | DINAH GARIN |
| DAS Clearance | Cleared | 10/23/2020 | ELIZABETH TOMS |
| "Q" conditions | Cleared | 11/10/2020 | SARAHI ORTEGA |
| Comm Cor/Mini-Mall | Cleared | 11/10/2020 | SARAHI ORTEGA |
| Comm Cor/Mini-Mall | Cleared | 11/10/2020 | SARAHI ORTEGA |
| Comm Cor/Mini-Mall | Cleared | 11/10/2020 | SARAHI ORTEGA |
| Supp. Use District POD/CDO/TDO | Cleared | 11/10/2020 | SARAHI ORTEGA |
| ZA Case | Cleared | 11/10/2020 | SARAHI ORTEGA |
| ZI | Cleared | 11/10/2020 | SARAHI ORTEGA |
Contact Information
| Contractor | Athiva Services Inc; Lic. No.: 850795-B | 5932 BOLSA AVE #107 HUNTINGTON BEACH, CA 92649 |
| Engineer | Dang,, Vinh Duc Le; Lic. No.: C65096 | 1209 W ALTON AVE SANTA ANA, CA 92707 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 3/10/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 3/12/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Footing/Foundation/Slab | 3/16/2021 | Approved | LEOPOLDO MENDOZA |
| Excavation/Setback/Form/Re-Bar | 3/19/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 3/25/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Light Gage Steel Frame | 3/31/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 4/6/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Insulation | 4/6/2021 | Approved | LEOPOLDO MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2021 | Partial Approval | LEOPOLDO MENDOZA |
| Interior/Exterior Lathing | 4/20/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 5/6/2021 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 5/6/2021 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Rough | 5/6/2021 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 5/6/2021 | Approved | SORIN CIRSTOIU |
| Wood Frame | 5/6/2021 | Partial Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 5/12/2021 | Partial Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 5/19/2021 | Partial Approval | SORIN CIRSTOIU |
| Final | 5/20/2021 | Conditional Approval | SORIN CIRSTOIU |
| Green Building Final | 5/20/2021 | Approved | SORIN CIRSTOIU |
| Green Building Rough | 5/20/2021 | Approved | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 5/20/2021 | SGSOV Gas Company | SORIN CIRSTOIU |
| Wood Frame | 5/20/2021 | Approved | SORIN CIRSTOIU |