4105 S DEGNAN BLVD 90008
Certificate Information: 4105 S DEGNAN BLVD 90008
- Application / Permit
- 19014-10000-02508
- Plan Check / Job No.
- B19LA09712
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1-STORY ADDITION OF FAMILY ROOM TO SFD
- Permit Issued
- Issued on 5/13/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2019 | SINA KHOSRAVI |
| Corrections Issued | 5/13/2019 | SINA KHOSRAVI |
| Plan Check Approved | 5/13/2019 | AUNG SOE |
| Issued | 5/13/2019 | LADBS |
| CofO in Progress | 8/10/2021 | DAVID FEILER |
| CofO Issued | 8/14/2021 | DEROLD HAUFF |
| Permit Finaled | 8/14/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 5/13/2019 | ELAINE LEI |
Contact Information
| Contractor | Gwg Construction Inc; Lic. No.: 643695-B | 1740 W 127TH STREET LOS ANGELES, CA 90047 |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/28/2019 | Not Ready for Inspection | COREY HUPP |
| Pre-Inspection | 5/29/2019 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 7/8/2019 | Conditional Approval | COREY HUPP |
| Deputy Drilled-In Anchors | 8/21/2019 | Conditional Approval | COREY HUPP |
| BUILDING-Rough-Frame | 8/29/2019 | Not Ready for Inspection | COREY HUPP |
| ELECTRICAL-Rough | 8/29/2019 | Approved | COREY HUPP |
| BUILDING-Rough-Frame | 9/4/2019 | Approved | COREY HUPP |
| Footing/Foundation/Slab | 9/4/2019 | Approved | COREY HUPP |
| Green Building Rough | 9/4/2019 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 9/10/2019 | Approved | COREY HUPP |
| Insulation | 9/13/2019 | Approved | COREY HUPP |
| Drywall Nailing | 9/16/2019 | Approved | COREY HUPP |
| Final | 6/22/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Final | 6/22/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/22/2021 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 7/23/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Final | 7/23/2021 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Final | 7/23/2021 | Not Ready for Inspection | DAVID FEILER |
| Wood Frame | 7/23/2021 | Not Ready for Inspection | DAVID FEILER |
| Final | 8/5/2021 | OK to Issue CofO | DAVID FEILER |
| Green Building Final | 8/5/2021 | Approved | DAVID FEILER |