4656 N TALOFA AVE 91602

Certificate Information: 4656 N TALOFA AVE 91602

Application / Permit
19014-10000-02501
Plan Check / Job No.
B19LA09697
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 37'0" X 37'3" (IRREGULAR) 1,083 SQ/FT 2ND FLOOR ADDITION TO AN EXISITNG TWO STORY DWELLING. REMOVE PARTITION WALL BETWEEN KITCHEN AND LIVING AREA, INTERIOR REMODEL OF FIRST FLOOR.
Permit Issued
Issued on 10/25/2019
Issuing Office
Metro
Current Status
CofO Issued on 8/24/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2019 APPLICANT
Assigned to Plan Check Engineer 5/30/2019 STANLEY RAAP
Corrections Issued 6/5/2019 STANLEY RAAP
Building Plans Picked Up 6/13/2019 APPLICANT
Green Plans Picked Up 7/1/2019 APPLICANT
Quality Review Completed 7/3/2019 TIEN JEN WANG
Plan Check Approved 10/4/2019 STANLEY RAAP
No Progress 10/4/2019 STANLEY RAAP
Plan Check Approved 10/4/2019 STANLEY RAAP
Issued 10/25/2019 LADBS
CofO in Progress 3/31/2022 ARAM AVEDISIAN
CofO Issued 8/24/2022 DANIEL ORRANTE
Permit Finaled 8/24/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/18/2019 ELAINE LEI
Miscellaneous Cleared 6/18/2019 JOE LUCKEY
Sewer availability Cleared 6/18/2019 ELAINE LEI
Tract Map conditions Cleared 6/18/2019 JOE LUCKEY
Low Impact Development Cleared 8/2/2019 JORGE MEJIA LEMUS
Green Code Cleared 8/6/2019 KHEDER ALRAZAA
Roof/Waste drainage to street Cleared 8/20/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/18/2020 Not Ready for Inspection RAYMOND KEHOE
Green Building Rough 5/18/2020 Not Ready for Inspection RAYMOND KEHOE
MERV13>=Rough 5/18/2020 Not Ready for Inspection RAYMOND KEHOE
BUILDING-Rough-Frame 6/18/2020 Approved RAYMOND KEHOE
ELECTRICAL-Rough 6/18/2020 Approved RAYMOND KEHOE
Green Building Rough 6/18/2020 Approved RAYMOND KEHOE
HVAC-Rough 6/18/2020 Approved RAYMOND KEHOE
MERV13>=Rough 6/18/2020 Approved RAYMOND KEHOE
PLUMBING-Rough 6/18/2020 Approved RAYMOND KEHOE
Wood Frame 6/18/2020 Approved RAYMOND KEHOE
Insulation 6/29/2020 Approved PIERRE VEGA
Interior/Exterior Lathing 6/29/2020 Approved PIERRE VEGA
Drywall Nailing 7/10/2020 Approved ROBERT MINASSIANS
Interior/Exterior Lathing 7/10/2020 Approved ROBERT MINASSIANS
Footing/Foundation/Slab 10/23/2020 Approved THOMAS FINNILA
Green Building Final 10/23/2020 Corrections Issued THOMAS FINNILA
MERV13>=Final 10/23/2020 No Access for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 10/23/2020 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 10/23/2020 Corrections Issued THOMAS FINNILA
Green Building Final 10/30/2020 Approved DANIEL DREW
ELECTRICAL-Final 11/18/2020 Approved DANIEL DREW
HVAC-Final 11/18/2020 Approved DANIEL DREW
PLUMBING-Final 11/18/2020 Approved DANIEL DREW
Final 3/7/2022 Corrections Issued MATT KELLERMAN
MERV13>=Final 3/7/2022 Approved MATT KELLERMAN
SGSOV-Seismic Gas S/O Valve 3/7/2022 SGSOV Approved MATT KELLERMAN
Smoke Detectors 3/7/2022 Approved MATT KELLERMAN
Final 3/16/2022 Corrections Issued DAVID MATSON
Final 3/31/2022 OK to Issue CofO ARAM AVEDISIAN