4543 N FARMDALE AVE 91602
Certificate Information: 4543 N FARMDALE AVE 91602
- Application / Permit
- 19014-10000-02407
- Plan Check / Job No.
- B19LA09320
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-STORY ADDITION AND REMODEL THROUGHOUT EXISTING SFD AND ATTACH 2 CAR GARAGE TO FRONT OF PROPERTY
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2019 | MONICA RAMIREZ |
| Corrections Issued | 6/4/2019 | MONICA RAMIREZ |
| Quality Review Completed | 6/5/2019 | HERNAN ARREOLA |
| Green Plans Picked Up | 6/7/2019 | APPLICANT |
| Building Plans Picked Up | 6/10/2019 | APPLICANT |
| Applicant returned to address corrections | 7/23/2019 | MONICA RAMIREZ |
| Applicant returned to address corrections | 7/31/2019 | MONICA RAMIREZ |
| Plan Check Approved | 8/30/2019 | MONICA RAMIREZ |
| Issued | 3/3/2020 | LADBS |
| CofO in Progress | 9/2/2022 | DAVID MATSON |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Hold | Cleared | 6/3/2019 | LOURDES RAMIRO |
| Permit | Cleared | 6/27/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/29/2019 | ERIK BEASLEY |
| Trees in Parkway | Cleared | 7/29/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 8/7/2019 | SARAH ABOULHOSN |
| Roof/Waste drainage to street | Cleared | 8/14/2019 | ERIK BEASLEY |
| Low Impact Development | Cleared | 8/28/2019 | RYAN HUDSON |
Contact Information
| Contractor | West American Design And Development Inc; Lic. No.: 641213-B | 6060 W MANCHESTER AVE STE 107 LOS ANGELES, CA 90045 |
| Engineer | Hamilton,, John O; Lic. No.: C53284 | P O BOX 866 HAWTHORNE, CA 90251 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/31/2020 | Corrections Issued | THOMAS FINNILA |
| Footing/Foundation/Slab | 7/31/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Piling/Pier/Caisson | 7/31/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 10/7/2020 | Partial Inspection | DANIEL ORRANTE |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2020 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 10/27/2020 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2020 | Conditional Approval | THOMAS FINNILA |
| Footing/Foundation/Slab | 11/4/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 11/4/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2021 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2021 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2021 | Partial Approval | THOMAS FINNILA |
| PLUMBING-Rough | 5/11/2021 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 5/27/2021 | Corrections Issued | THOMAS FINNILA |
| Grading Pre-Inspection | 5/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 5/27/2021 | Conditional Approval | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/27/2021 | Partial Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/4/2021 | Approved | THOMAS FINNILA |
| HVAC-Rough | 6/4/2021 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 6/4/2021 | Partial Approval | THOMAS FINNILA |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 6/15/2021 | Approved | THOMAS FINNILA |
| MERV13>=Rough | 6/15/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 7/15/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 7/15/2021 | Partial Inspection | CALEB MEISTER |
| Pre-Inspection | 7/15/2021 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Final | 6/22/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 7/22/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Gas Test | 7/22/2022 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 7/22/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 8/2/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| PLUMBING-Final | 8/2/2022 | No Access for Inspection | DEANDRE HOFFMAN |
| Service/Power Release | 8/2/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 8/8/2022 | Corrections Issued | THOMAS FINNILA |
| Gas Test | 8/8/2022 | Corrections Issued | THOMAS FINNILA |
| HVAC-Final | 8/8/2022 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Final | 8/8/2022 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Final | 8/16/2022 | Approved | THOMAS FINNILA |
| Final | 8/16/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Footing/Foundation/Slab | 8/16/2022 | Approved | THOMAS FINNILA |
| Gas Test | 8/16/2022 | Approved | THOMAS FINNILA |
| Green Building Final | 8/16/2022 | Approved | THOMAS FINNILA |
| HVAC-Final | 8/16/2022 | Corrections Issued | THOMAS FINNILA |
| MERV13>=Final | 8/16/2022 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 8/16/2022 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 8/16/2022 | SGSOV Approved | THOMAS FINNILA |
| Service/Power Release | 8/16/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 8/16/2022 | Approved | THOMAS FINNILA |
| HVAC-Final | 8/26/2022 | Approved | THOMAS FINNILA |
| Service/Power Release | 8/26/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 9/2/2022 | OK to Issue CofO | DAVID MATSON |
| Service/Power Release | 9/2/2022 | Approved | DAVID MATSON |