3416 N VERDUGO ROAD 90065
Certificate Information: 3416 N VERDUGO ROAD 90065
- Application / Permit
- 19014-10000-02283
- Plan Check / Job No.
- B19LA08840
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- ADDITION TO EXISTING BLDG AND CHANGE OF USE FROM STORE AND OFFICE TO NEW RESTAURANT. MAKE (3) EXISITING DETACHED BUILDINGS TO COMBINE AS (1) BUILDING WITH THE ADDITION. NO CHANGES TO THE EXTERIOR OF BUILDING AND NO CHANGES TO EXISTING PARKING.
- Permit Issued
- Issued on 12/31/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2019 | APPLICANT |
| Green Plans Picked Up | 5/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | YOUNG KIM |
| Disabled Access Plans Picked Up | 5/20/2019 | APPLICANT |
| Corrections Issued | 5/21/2019 | YOUNG KIM |
| Quality Review Completed | 5/31/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 6/3/2019 | APPLICANT |
| Applicant returned to address corrections | 8/6/2019 | YOUNG KIM |
| Applicant returned to address corrections | 11/6/2019 | YOUNG KIM |
| Applicant returned to address corrections | 11/22/2019 | YOUNG KIM |
| Applicant returned to address corrections | 12/27/2019 | YOUNG KIM |
| Plan Check Approved | 12/31/2019 | YOUNG KIM |
| Issued | 12/31/2019 | LADBS |
| TCO Issued (Expire Date: 12-01-2021) | 6/4/2021 | ERNESTO CORRAL |
| CofO in Progress | 11/16/2021 | DANIEL COLLINS |
| Permit Finaled | 11/17/2021 | ERNESTO CORRAL |
| CofO Issued | 11/17/2021 | ERNESTO CORRAL |
| Permit Finaled | 11/17/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/6/2019 | ELENA LOPEZ |
| "Q" conditions | Cleared | 6/19/2019 | SOPHIE GABEL-SCHEINBAU |
| ZA Case | Cleared | 6/19/2019 | SOPHIE GABEL-SCHEINBAU |
| Green Code | Cleared | 7/23/2019 | SARAH ABOULHOSN |
| DAS Clearance | Cleared | 7/25/2019 | WAI LAU |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2019 | JAMES MORALEZ |
| Sewer availability | Cleared | 7/26/2019 | JAMES MORALEZ |
| Specific Plan | Cleared | 8/2/2019 | OLGA RUANO |
| Food establishment approval | Cleared | 8/6/2019 | LACDHS APPROVED |
| Grading Pre-Inspection | Cleared | 8/7/2019 | PATRICK MISCHLICH |
| Food Service Establishment | Cleared | 10/3/2019 | JASH PATEL |
| Supp. Use District POD/CDO/TDO | Cleared | 12/19/2019 | NICOLE SANCHEZ |
| ZA Case | Cleared | 12/20/2019 | LATANYA ROUX |
Contact Information
| Contractor | Clc Builders Inc; Lic. No.: 580175-B | 22916 ELKWOOD STREET WEST HILLS, CA 91304 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/24/2020 | Conditional Approval | RONALD PACHECO |
| Piling/Pier/Caisson | 1/24/2020 | Partial Inspection | ERNESTO CORRAL |
| Pre-Inspection | 1/24/2020 | Approved | ERNESTO CORRAL |
| Excavation/Setback/Form/Re-Bar | 2/7/2020 | Partial Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 2/25/2020 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Rough | 6/8/2020 | Not Ready for Inspection | KATY RAMIREZ |
| Wood Frame | 6/8/2020 | No Access for Inspection | KATY RAMIREZ |
| Pre-Inspection | 6/9/2020 | Approved | KATY RAMIREZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2020 | Partial Approval | RONALD PACHECO |
| Excavation/Setback/Form/Re-Bar | 6/25/2020 | Partial Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 6/26/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 6/29/2020 | Conditional Approval | RONALD PACHECO |
| Green Building Rough | 7/14/2020 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 7/14/2020 | Not Ready for Inspection | RONALD PACHECO |
| Excavation/Setback/Form/Re-Bar | 7/24/2020 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 7/31/2020 | Partial Approval | RONALD PACHECO |
| Excavation/Setback/Form/Re-Bar | 8/6/2020 | Partial Approval | RONALD PACHECO |
| Green Building Rough | 8/14/2020 | Approved | RONALD PACHECO |
| Wood Frame | 8/14/2020 | Partial Approval | RONALD PACHECO |
| Masonry Wall/Backfill | 8/25/2020 | Partial Approval | RONALD PACHECO |
| Insulation | 9/2/2020 | Approved | RONALD PACHECO |
| Drywall Nailing | 9/8/2020 | Approved | RONALD PACHECO |
| T-Bar Ceiling | 10/29/2020 | Not Ready for Inspection | RONALD PACHECO |
| Interior/Exterior Lathing | 11/16/2020 | Partial Approval | RONALD PACHECO |
| Final | 2/8/2021 | Corrections Issued | RONALD PACHECO |
| Footing/Foundation/Slab | 2/8/2021 | Approved | RONALD PACHECO |
| Green Building Final | 2/8/2021 | Not Ready for Inspection | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Not Ready | RONALD PACHECO |
| Smoke Detectors | 2/8/2021 | Not Ready for Inspection | RONALD PACHECO |
| Wood Frame | 2/8/2021 | Not Ready for Inspection | RONALD PACHECO |
| Final | 5/7/2021 | Not Ready for Inspection | LANNY MERRICK |
| Green Building Final | 5/7/2021 | Approved | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 5/7/2021 | SGSOV Approved | LANNY MERRICK |
| Smoke Detectors | 5/7/2021 | Approved | LANNY MERRICK |
| Wood Frame | 5/7/2021 | Approved | LANNY MERRICK |
| Final | 11/1/2021 | Partial Inspection | DANIEL COLLINS |
| Special/Order Compliance | 11/3/2021 | Conditional Approval | MARK FERRARI |
| Final | 11/16/2021 | OK to Issue CofO | DANIEL COLLINS |