3320 N RED ROSE DR 91436
Certificate Information: 3320 N RED ROSE DR 91436
- Application / Permit
- 19014-10000-02246
- Plan Check / Job No.
- B19LA08744
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 1202 SF ADDITION TO AN (E) 3472 SF 1-STORY SFD AND REMODALE OF THE S.F.D
- Permit Issued
- Issued on 8/23/2021
- Issuing Office
- Current Status
- CofO Issued on 1/7/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2019 | RAHEL BEYENE |
| Corrections Issued | 6/14/2019 | RAHEL BEYENE |
| Quality Review Completed | 7/2/2019 | QUAN NGHIEM |
| Green Plans Picked Up | 7/19/2019 | APPLICANT |
| Applicant returned to address corrections | 12/10/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 1/22/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 3/23/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 4/1/2021 | RAHEL BEYENE |
| Plan Check Approved | 5/20/2021 | RAHEL BEYENE |
| Building Plans Picked Up | 6/3/2021 | APPLICANT |
| Issued | 8/23/2021 | APPLICANT |
| CofO in Progress | 5/6/2025 | JOHN COLEMAN |
| No Progress | 5/12/2025 | SEAN WIRCH |
| CofO in Progress | 5/12/2025 | SEAN WIRCH |
| Permit Finaled | 1/7/2026 | MICHAEL PELHAM |
| CofO Issued | 1/7/2026 | MICHAEL PELHAM |
| Permit Finaled | 1/7/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 5/1/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 5/1/2020 | GUILLERMO PETRA |
| BHO/Hillside ordinance | Cleared | 5/1/2020 | GUILLERMO PETRA |
| ZA Case | Cleared | 5/14/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 5/14/2020 | DENZEL HENDERSON |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 5/20/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 11/3/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 1/15/2021 | MITESH PATEL |
| Green Code | Cleared | 1/22/2021 | RAHEL BEYENE |
| Roof/Waste drainage to street | Cleared | 1/22/2021 | GUILLERMO PETRA |
| Miscellaneous | Cleared | 3/26/2021 | JASON CHAN |
| Specific Plan | Cleared | 3/26/2021 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 4/13/2021 | VASIL MIHALEV |
| GPI Written Notices | Cleared | 5/13/2021 | RAHEL BEYENE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1243 21ST AVE NE APT B HICKORY, NC 28601 |
| Engineer | Garcia,, Ricardo Ray; Lic. No.: C66957 | 27702 QUINCY ST CASTAIC, CA 91384 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 1423 S BEVERLY GLEN BLVD APT B LOS ANGELES, CA 90024 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2023 | Approved | VINCENT HANLEY |
| Deputy Grading | 8/22/2023 | Approved | SEAN HAUPT |
| Deputy Grading | 8/23/2023 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/31/2023 | Partial Approval | VINCENT HANLEY |
| Reinforced Concrete Frame | 8/31/2023 | Partial Approval | VINCENT HANLEY |
| Deputy Reinf. Concrete | 9/1/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 10/2/2023 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 10/2/2023 | Partial Approval | VINCENT HANLEY |
| Sewer | 10/2/2023 | Approved | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 10/11/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/11/2023 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 10/13/2023 | Approved | VINCENT HANLEY |
| Deputy Reinf. Concrete | 10/16/2023 | Conditional Approval | MORRIS JACKSON |
| BUILDING-Rough-Frame | 11/16/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/16/2023 | Partial Approval | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Approved | VINCENT HANLEY |
| Deputy Wood Construction | 1/12/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 2/15/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 2/15/2024 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 2/15/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 3/4/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 3/4/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 3/4/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 3/4/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 3/4/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/10/2024 | Approved | VINCENT HANLEY |
| Insulation | 4/18/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 4/29/2024 | Approved | VINCENT HANLEY |
| Service/Power Release | 4/29/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/28/2024 | Partial Approval | SEAN WIRCH |
| Shower Pan | 5/28/2024 | Partial Approval | SEAN WIRCH |
| Shower Pan | 6/26/2024 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 6/28/2024 | Approved | THOMAS FINNILA |
| Final | 10/3/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 10/3/2024 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Not Ready | THOMAS FINNILA |
| Smoke Detectors | 10/3/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Final | 11/15/2024 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 11/15/2024 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 11/15/2024 | Corrections Issued | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Not Ready | THOMAS FINNILA |
| ELECTRICAL-Final | 12/4/2024 | Approved | THOMAS FINNILA |
| HVAC-Final | 12/4/2024 | Approved | THOMAS FINNILA |
| PLUMBING-Final | 12/4/2024 | Approved | THOMAS FINNILA |
| Final | 4/17/2025 | Corrections Issued | THOMAS FINNILA |
| Final | 4/21/2025 | Corrections Issued | THOMAS FINNILA |
| Green Building Final | 4/21/2025 | Approved | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Approved | THOMAS FINNILA |
| Smoke Detectors | 4/21/2025 | Approved | THOMAS FINNILA |
| Final | 5/6/2025 | OK to Issue CofO | JOHN COLEMAN |