8319 S WINSFORD AVE 90045

Certificate Information: 8319 S WINSFORD AVE 90045

Application / Permit
19014-10000-02208
Plan Check / Job No.
B19LA08616
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SECOND STORY ACCESSORY DWELING UNIT ABOVE (E) GARAGE PER AB 494 and SB 229
Permit Issued
Issued on 8/5/2020
Issuing Office
Current Status
CofO Issued on 4/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2019 APPLICANT
Assigned to Plan Check Engineer 5/16/2019 MONICA RAMIREZ
Corrections Issued 5/20/2019 MONICA RAMIREZ
Quality Review Completed 5/31/2019 HERNAN ARREOLA
Applicant returned to address corrections 5/6/2020 MONICA RAMIREZ
Green Plans Picked Up 6/3/2020 APPLICANT
Applicant returned to address corrections 7/1/2020 MONICA RAMIREZ
Building Plans Picked Up 7/6/2020 APPLICANT
Plan Check Approved 8/5/2020 MONICA RAMIREZ
Issued 8/5/2020 APPLICANT
CofO in Progress 3/31/2021 BRENDAN LOONEY
CofO Issued 4/29/2021 VINCENT COTTON
Permit Finaled 4/29/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 6/13/2019 ELENA LOPEZ
Specific Plan Cleared 6/13/2019 LATANYA ROUX
Eng Process Fee Ord 176,300 Cleared 7/12/2019 KAREN LE
Sewer availability Cleared 7/12/2019 KAREN LE
Grading Pre-Inspection Cleared 9/27/2019 PATRICK MISCHLICH
Green Code Cleared 10/18/2019 MONICA RAMIREZ
Hydrant and Access approval Cleared 10/18/2019 JEREMY CARTER
Construction near power lines Cleared 3/6/2020 RIDWAN HARDY
Construction within easement Cleared 3/6/2020 RIDWAN HARDY
Low Impact Development Cleared 7/14/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/24/2020 NIKTA MOUSAVI

Contact Information

Contractor Owner-Builder       ,
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/9/2020 Corrections Issued JUAN VALENZUELA
METHANE-Barrier 9/9/2020 Approved JUAN VALENZUELA
METHANE-Subgrade 9/9/2020 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/11/2020 Partial Approval JUAN VALENZUELA
Deputy Steel/Welding 9/24/2020 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 9/24/2020 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 10/2/2020 Approved JOHNNY MIRANDA
Deputy Steel/Welding 10/9/2020 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/14/2020 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/16/2020 Partial Approval JUAN VALENZUELA
ELECTRICAL-Rough 11/24/2020 Approved DAVID HEINE
PLUMBING-Rough 11/24/2020 Approved DAVID HEINE
BUILDING-Rough-Frame 12/29/2020 Approved DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 12/29/2020 Approved DAVID HEINE
Green Building Rough 12/29/2020 Approved DAVID HEINE
Insulation 12/29/2020 Approved DAVID HEINE
Interior/Exterior Lathing 12/29/2020 Partial Approval DAVID HEINE
METHANE-Rough 12/29/2020 Approved DAVID HEINE
Drywall Nailing 1/8/2021 Approved DAVID HEINE
Interior/Exterior Lathing 1/8/2021 Partial Approval DAVID HEINE
Interior/Exterior Lathing 1/13/2021 Approved DAVID HEINE
ELECTRICAL-Final 2/22/2021 Corrections Issued JUAN VALENZUELA
Final 2/22/2021 Corrections Issued JUAN VALENZUELA
Green Building Final 2/22/2021 Corrections Issued JUAN VALENZUELA
HVAC-Final 2/22/2021 Corrections Issued JUAN VALENZUELA
PLUMBING-Final 2/22/2021 Corrections Issued JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 2/22/2021 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 2/22/2021 Not Ready for Inspection JUAN VALENZUELA
Smoke Detectors 2/22/2021 Approved JUAN VALENZUELA
ELECTRICAL-Final 2/26/2021 Approved DAVID HEINE
HVAC-Final 2/26/2021 Approved DAVID HEINE
PLUMBING-Final 2/26/2021 Approved DAVID HEINE
Final 3/4/2021 Corrections Issued JUAN VALENZUELA
Green Building Final 3/4/2021 Not Ready for Inspection JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Not Ready JUAN VALENZUELA
Service/Power Release 3/4/2021 Not Ready for Inspection JUAN VALENZUELA
Final 3/23/2021 Corrections Issued BRENDAN LOONEY
Green Building Final 3/23/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Not Ready BRENDAN LOONEY
Service/Power Release 3/23/2021 Not Ready for Inspection BRENDAN LOONEY
Final 3/30/2021 OK to Issue CofO BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/30/2021 SGSOV Approved BRENDAN LOONEY
Service/Power Release 3/30/2021 Approved BRENDAN LOONEY