5771 W VALLEY OAK DR 90068
Certificate Information: 5771 W VALLEY OAK DR 90068
- Application / Permit
- 19014-10000-02177
- Plan Check / Job No.
- B19LA08518
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel to (E) SFD, including new elevator within (E) building.
- Permit Issued
- Issued on 11/30/2020
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 11/30/2020
Permit Application Status History
| Submitted | 5/2/2019 | APPLICANT |
| Green Plans Picked Up | 5/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2019 | HELEN NGUYEN |
| Corrections Issued | 5/23/2019 | HELEN NGUYEN |
| Quality Review Completed | 6/11/2019 | TU HUA |
| Building Plans Picked Up | 6/11/2019 | APPLICANT |
| Applicant returned to address corrections | 9/4/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 9/18/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/1/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 11/22/2019 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/22/2020 | HELEN NGUYEN |
| Plan Check Approved | 3/11/2020 | HELEN NGUYEN |
| Issued | 11/30/2020 | APPLICANT |
Permit Application Clearance Information
| CPC | Cleared | 6/14/2019 | TREVOR MARTIN |
| Miscellaneous | Cleared | 6/14/2019 | TREVOR MARTIN |
| Private street | Cleared | 9/18/2019 | MARC WOERSCHING |
| "D" conditions | Cleared | 11/5/2019 | AMANDA BRIONES |
| Green Code | Cleared | 11/5/2019 | COLIN LOREDO |
| ZI | Cleared | 11/5/2019 | AMANDA BRIONES |
| Grading Pre-Inspection | Cleared | 1/22/2020 | HELEN NGUYEN |
Contact Information
| Architect | Peck,, Christopher M; Lic. No.: C27316 | C.M. PECK CONSULTING 25 S. EL MOLINO AVE PASADENA, CA 911012023 |
| Contractor | Van Lokeren Construction Inc; Lic. No.: 816234-B | 22836 MACFARLANE DRIVE WOODLAND HILLS, CA 91364 |
| Engineer | Peck,, Christopher Mount; Lic. No.: C58162 | 25 SOUTH EL MOLINO AVE PASADENA, CA 911012023 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/7/2021 | Partial Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 8/2/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/2/2021 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/30/2021 | Partial Approval | BRIAN SULLIVAN |
| Masonry Wall/Backfill | 8/30/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 8/30/2021 | Partial Approval | BRIAN SULLIVAN |
| Insulation | 9/1/2021 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/1/2021 | Partial Approval | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 9/1/2021 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 9/1/2021 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/7/2021 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 9/8/2021 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 9/8/2021 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/28/2021 | Corrections Issued | BRIAN SULLIVAN |
| Reinforced Concrete Frame | 9/30/2021 | Partial Approval | SCOTT FINNILA |
| Structural Steel Frame | 3/8/2022 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/10/2022 | Approved | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 3/10/2022 | Approved | BRIAN SULLIVAN |
| Shower Pan | 3/10/2022 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 3/24/2022 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/3/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 2/3/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 2/3/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Smoke Detectors | 2/3/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |