5517 W BARTON AVE 90038
Certificate Information: 5517 W BARTON AVE 90038
- Application / Permit
- 19014-10000-02149
- Plan Check / Job No.
- B19LA08429
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING ATTIC TO SECOND STORY AT EXISTING 1-STORY SINGLE FAMILY DWELLING; NEW ADDITION 8'0" x 24'10" AT 1ST FLOOR & NEW BALCONY AT 2ND FLOOR.
- Permit Issued
- Issued on 3/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2019 | PRANITA SHAH |
| Corrections Issued | 5/29/2019 | PRANITA SHAH |
| Green Plans Picked Up | 5/29/2019 | APPLICANT |
| Quality Review Completed | 6/14/2019 | HERNAN ARREOLA |
| Plan Check Approved | 7/10/2019 | PRANITA SHAH |
| Issued | 3/5/2020 | LADBS |
| CofO in Progress | 11/13/2024 | JEFFREY MEAD |
| No Progress | 11/19/2024 | DEROLD HAUFF |
| CofO in Progress | 11/19/2024 | DEROLD HAUFF |
| Permit Finaled | 2/20/2025 | DEROLD HAUFF |
| CofO Issued | 2/20/2025 | DEROLD HAUFF |
| Permit Finaled | 2/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/18/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2019 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 6/18/2019 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 6/18/2019 | CELINA MORENO |
| Sewer availability | Cleared | 6/18/2019 | CELINA MORENO |
| Green Code | Cleared | 7/8/2019 | PRANITA SHAH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/26/2021 | Partial Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 12/19/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 10/25/2023 | Partial Approval | JEFFREY MEAD |
| Wood Frame | 10/25/2023 | Corrections Issued | JEFFREY MEAD |
| Drywall Nailing | 11/8/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Partial Approval | JEFFREY MEAD |
| Excavation/Setback/Form/Re-Bar | 1/4/2024 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 1/4/2024 | Partial Approval | JEFFREY MEAD |
| Wood Frame | 4/17/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/8/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Rough | 7/8/2024 | Approved | JEFFREY MEAD |
| Green Building Rough | 7/8/2024 | Approved | JEFFREY MEAD |
| HVAC-Rough | 7/8/2024 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 7/8/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 10/24/2024 | Corrections Issued | JEFFREY MEAD |
| Final | 10/24/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Footing/Foundation/Slab | 10/24/2024 | Approved | JEFFREY MEAD |
| Green Building Final | 10/24/2024 | Approved | JEFFREY MEAD |
| SGSOV-Seismic Gas S/O Valve | 10/24/2024 | SGSOV Approved | JEFFREY MEAD |
| Smoke Detectors | 10/24/2024 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | JEFFREY MEAD |
| Final | 11/12/2024 | OK to Issue CofO | JEFFREY MEAD |
| Special/Order Compliance | 12/17/2024 | Corrections Issued | JOAQUIN GREENOUGH |