2418 N DALLAS ST 90031
Certificate Information: 2418 N DALLAS ST 90031
- Application / Permit
- 19014-10000-02038
- Plan Check / Job No.
- B19LA07934
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 19'-7" X 42'-4" IRREGULAR SHAPED 2 -STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 7/29/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/14/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | SELLA BENYAMIN |
| Corrections Issued | 5/14/2019 | SELLA BENYAMIN |
| Quality Review Completed | 5/16/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 5/17/2019 | APPLICANT |
| Building Plans Picked Up | 5/22/2019 | APPLICANT |
| Plan Check Approved | 7/25/2019 | SELLA BENYAMIN |
| Issued | 7/29/2019 | LADBS |
| CofO in Progress | 7/14/2020 | RUBEN SALAS |
| Permit Finaled | 7/14/2020 | DEROLD HAUFF |
| CofO Issued | 7/14/2020 | DEROLD HAUFF |
| Permit Finaled | 7/14/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/13/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 6/13/2019 | JEANETTE VONG |
| Green Code | Cleared | 7/5/2019 | COLIN LOREDO |
| ZI | Cleared | 7/5/2019 | SOPHIE GABEL-SCHEINBAU |
| Low Impact Development | Cleared | 7/11/2019 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 7/12/2019 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Pinzon,, Eduardo A; Lic. No.: C74869 | 821 W SPRUCE ST WEST COVINA, CA 91790 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 9/11/2019 | Conditional Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2019 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 10/1/2019 | Partial Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 11/20/2019 | Not Ready for Inspection | AJA COLLAY |
| Green Building Rough | 11/20/2019 | Not Ready for Inspection | AJA COLLAY |
| MERV13>=Rough | 11/20/2019 | Not Ready for Inspection | AJA COLLAY |
| PLUMBING-Rough | 11/20/2019 | Not Ready for Inspection | AJA COLLAY |
| Wood Frame | 11/20/2019 | Not Ready for Inspection | AJA COLLAY |
| BUILDING-Rough-Frame | 12/26/2019 | Conditional Approval | SCOTT FINNILA |
| Green Building Rough | 12/26/2019 | Not Ready for Inspection | SCOTT FINNILA |
| HVAC-Rough | 12/26/2019 | Partial Approval | SCOTT FINNILA |
| MERV13>=Rough | 12/26/2019 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 12/26/2019 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 1/2/2020 | Partial Inspection | AJA COLLAY |
| ELECTRICAL-Rough | 1/8/2020 | Approved | AJA COLLAY |
| BUILDING-Rough-Frame | 1/22/2020 | Conditional Approval | AJA COLLAY |
| Green Building Rough | 1/22/2020 | Not Ready for Inspection | AJA COLLAY |
| Interior/Exterior Lathing | 1/27/2020 | Not Ready for Inspection | AJA COLLAY |
| Interior/Exterior Lathing | 1/31/2020 | No Access for Inspection | HORACE FULTZ |
| BUILDING-Rough-Frame | 2/4/2020 | Approved | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2020 | Approved | AJA COLLAY |
| HVAC-Rough | 2/4/2020 | Approved | AJA COLLAY |
| Interior/Exterior Lathing | 2/4/2020 | Approved | AJA COLLAY |
| Interior/Exterior Lathing | 2/5/2020 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 2/6/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Insulation | 2/6/2020 | Partial Inspection | ROBERT VORHIS |
| BUILDING-Rough-Frame | 2/11/2020 | Approved | CHARLES BOGHOSKHAN |
| Drywall Nailing | 2/11/2020 | Approved | CHARLES BOGHOSKHAN |
| Green Building Rough | 2/11/2020 | Approved | CHARLES BOGHOSKHAN |
| Insulation | 2/11/2020 | Approved | CHARLES BOGHOSKHAN |
| Wood Frame | 2/11/2020 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 3/2/2020 | Approved | CHARLES BOGHOSKHAN |
| Final | 6/5/2020 | Corrections Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 6/5/2020 | Approved | RUBEN SALAS |
| Green Building Final | 6/5/2020 | Approved | RUBEN SALAS |
| MERV13>=Final | 6/5/2020 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 6/5/2020 | SGSOV Approved | RUBEN SALAS |
| Smoke Detectors | 6/5/2020 | Approved | RUBEN SALAS |
| Final | 6/12/2020 | Conditional Approval | RUBEN SALAS |