117 E 57TH ST 90011

Certificate Information: 117 E 57TH ST 90011

Application / Permit
19014-10000-02016
Plan Check / Job No.
B19LA07857
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 10' X 18'-2" TO AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER AB494 AND SB229
Permit Issued
Issued on 2/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2019 APPLICANT
Assigned to Plan Check Engineer 5/23/2019 SELLA BENYAMIN
Corrections Issued 5/29/2019 SELLA BENYAMIN
Quality Review Completed 5/30/2019 FELIX FIGUEROA
Building Plans Picked Up 6/7/2019 APPLICANT
Green Plans Picked Up 9/13/2019 APPLICANT
Plan Check Approved 2/6/2020 SELLA BENYAMIN
Issued 2/6/2020 LADBS
CofO in Progress 3/4/2021 RONALD MYRICK
Permit Finaled 3/4/2021 RONALD MYRICK
CofO Issued 3/4/2021 RONALD MYRICK
Permit Finaled 3/4/2021 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 6/7/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 6/21/2019 JEANETTE VONG
Low Impact Development Cleared 6/21/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 6/21/2019 JEANETTE VONG
Sewer availability Cleared 6/21/2019 JEANETTE VONG
Hydrant and Access approval Cleared 6/25/2019 GEORGE SUCHAND
Construction near power lines Cleared 11/24/2019 RIDWAN HARDY
Green Code Cleared 12/9/2019 VIVIAN LAO

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Francisco Javier; Lic. No.: C76510 2705 S FREMONT AVE APT D      ALHAMBRA, CA 91803

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/27/2020 Partial Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 3/3/2020 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 3/3/2020 Not Ready for Inspection JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 3/6/2020 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/2/2020 Partial Approval RUBEN SALAS
Green Building Rough 4/2/2020 Corrections Issued RUBEN SALAS
Rough-Elec/Plmb/HVAC 4/2/2020 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 4/20/2020 Approved ENRIQUE MIRELES
Green Building Rough 4/20/2020 Approved ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 4/20/2020 Approved ENRIQUE MIRELES
Insulation 4/23/2020 Conditional Approval SABAS ALONSO
Interior/Exterior Lathing 4/23/2020 Conditional Approval SABAS ALONSO
Drywall Nailing 4/30/2020 Approved SABAS ALONSO
ELECTRICAL-Final 5/15/2020 Approved ROBERT MCDOWELL
Final 5/15/2020 Conditional Approval ROBERT MCDOWELL
Footing/Foundation/Slab 5/15/2020 Approved ROBERT MCDOWELL
Green Building Final 5/15/2020 Approved ROBERT MCDOWELL
HVAC-Final 5/15/2020 Approved ROBERT MCDOWELL
PLUMBING-Final 5/15/2020 Approved ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 5/15/2020 SGSOV Approved ROBERT MCDOWELL
Smoke Detectors 5/15/2020 Approved ROBERT MCDOWELL