2052 N WOLLAM ST 90065

Certificate Information: 2052 N WOLLAM ST 90065

Application / Permit
19014-10000-02005
Plan Check / Job No.
B19LA07825
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION AND GARAGE TO AN EXISTING SINGLE FAMILY RESIDENCE WITH ATTACHED TWO CAR GARAGE
Permit Issued
Issued on 7/20/2020
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 FARSHAD ALIMOHAMADI
Corrections Issued 5/14/2019 FARSHAD ALIMOHAMADI
Quality Review Completed 5/17/2019 ARMEN JIVALAGIAN
Green Plans Picked Up 6/7/2019 APPLICANT
Building Plans Picked Up 6/10/2019 APPLICANT
Applicant returned to address corrections 11/15/2019 FARSHAD ALIMOHAMADI
Plan Check Approved 1/13/2020 FARSHAD ALIMOHAMADI
Issued 7/20/2020 APPLICANT
CofO in Progress 7/13/2022 HAMIK HARTOUNIAN
Permit Finaled 7/23/2022 DEROLD HAUFF
CofO Issued 7/23/2022 DEROLD HAUFF
Permit Finaled 7/23/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/25/2019 ELAINE LEI
Green Code Cleared 7/25/2019 SARAH ABOULHOSN
Hydrant and Access approval Cleared 7/25/2019 JEREMY CARTER
Permit Cleared 7/25/2019 ELAINE LEI
Sewer availability Cleared 7/25/2019 ELAINE LEI
Trees in Parkway Cleared 12/11/2019 JOHN KIM
Low Impact Development Cleared 12/12/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/12/2019 CELINA MORENO
Miscellaneous Cleared 12/13/2019 KIT AWAKUNI
Specific Plan Cleared 12/13/2019 KIT AWAKUNI
GPI Written Notices Cleared 1/13/2020 FARSHAD ALIMOHAMADI

Contact Information

Architect Espinosa,, Mauricio; Lic. No.: C34617 949 CHUNG KING ROAD      LOS ANGELES, CA 90012
Contractor E S V Prime Construction Specialists; Lic. No.: 861628-B 3330 BARHAM BLVD #103      LOS ANGELES, CA 90068
Engineer Vidal,, Juan Alonso; Lic. No.: GE861 7438 SHIRLEY AVE      RESEDA, CA 91335
Geologist Kruger,, Mark Otto; Lic. No.: EG2345 10120 NATIONAL BLVD      LOS ANGELES, CA 90034

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/22/2020 Corrections Issued HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 10/27/2020 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 10/28/2020 Conditional Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 10/29/2020 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 11/13/2020 Partial Approval HAMIK HARTOUNIAN
Deputy Reinf. Concrete 11/16/2020 Conditional Approval HAMIK HARTOUNIAN
Underground Mechanical 12/18/2020 Partial Approval HAMIK HARTOUNIAN
Wood Frame 12/18/2020 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 1/4/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 1/4/2021 Partial Approval HAMIK HARTOUNIAN
Deputy Wood Construction 1/6/2021 No Access for Inspection ELMER BLAND
Wood Frame 1/6/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Corrections Issued SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/30/2021 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/6/2021 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 4/6/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 4/6/2021 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 4/9/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/12/2021 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/12/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 4/12/2021 Approved HAMIK HARTOUNIAN
HVAC-Rough 4/12/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 4/12/2021 Approved HAMIK HARTOUNIAN
Insulation 4/22/2021 Partial Inspection THOMAS LOGRASSO
Shower Pan 4/22/2021 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 4/27/2021 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 4/27/2021 Partial Approval HAMIK HARTOUNIAN
Insulation 5/11/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/11/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 6/3/2021 Approved CHRISTOPHER DELLEFIELD
Final 5/23/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/23/2022 Approved OSVALDO PARAMO
Gas Test 5/23/2022 Approved OSVALDO PARAMO
Green Building Final 5/23/2022 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 5/23/2022 Approved OSVALDO PARAMO
ELECTRICAL-Final 6/29/2022 Approved HAMIK HARTOUNIAN
Final 6/29/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 6/29/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Final 6/29/2022 Approved HAMIK HARTOUNIAN
Final 7/6/2022 Corrections Issued HAMIK HARTOUNIAN
Final 7/12/2022 OK to Issue CofO HAMIK HARTOUNIAN