4819 E BALTIMORE ST 90042

Certificate Information: 4819 E BALTIMORE ST 90042

Application / Permit
19014-10000-01999
Plan Check / Job No.
B19LA07814
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED CONVERSION OF RECROOM TO BEDROOM, 1-STORY FRONT AND REAR ADDITION AND REMODEL TO SFD, NEW REAR WOOD DECK
Permit Issued
Issued on 12/9/2020
Issuing Office
Current Status
CofO Issued on 12/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/18/2019 APPLICANT
Assigned to Plan Check Engineer 4/18/2019 SINA KHOSRAVI
Corrections Issued 4/18/2019 SINA KHOSRAVI
Plan Check Approved 4/26/2019 SHANGQIN XIE
No Progress 9/4/2020 RICARDO RAMIREZ
Plan Check Approved 11/9/2020 FERNANDO FLORES
Issued 12/9/2020 APPLICANT
Building Plans Picked Up 12/16/2020 APPLICANT
CofO in Progress 5/1/2021 CRAIG VAUGHAN
Permit Finaled 12/4/2021 DEROLD HAUFF
CofO Issued 12/4/2021 DEROLD HAUFF
Permit Finaled 12/4/2021 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 4/18/2019 ELAINE LEI
BHO/Hillside ordinance Cleared 4/18/2019 ELAINE LEI
BHO/Hillside ordinance Cleared 4/18/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 4/18/2019 ELAINE LEI
GPI Written Notices Cleared 4/18/2019 SINA KHOSRAVI
Grading Pre-Inspection Cleared 4/18/2019 SINA KHOSRAVI
Roof/Waste drainage to street Cleared 4/18/2019 ELAINE LEI
Low Impact Development Cleared 9/29/2020 MARTIN FRAGOSO

Contact Information

Contractor Vision & Build Enterprises; Lic. No.: 920657-B 556 S FAIR OAKS AVENUE STE 101      PASADENA, CA 91105
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/7/2021 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 1/7/2021 Partial Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 1/27/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 2/5/2021 Partial Approval COREY HUPP
Green Building Rough 2/5/2021 Not Ready for Inspection COREY HUPP
BUILDING-Rough-Frame 2/22/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 2/22/2021 Corrections Issued CRAIG VAUGHAN
Green Building Rough 2/22/2021 Approved CRAIG VAUGHAN
PLUMBING-Rough 2/22/2021 Approved CRAIG VAUGHAN
Wood Frame 2/22/2021 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/2/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 3/2/2021 Approved CRAIG VAUGHAN
HVAC-Rough 3/2/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/2/2021 Approved CRAIG VAUGHAN
Insulation 3/8/2021 Approved CRAIG VAUGHAN
Light Gage Steel Frame 3/8/2021 Corrections Issued CRAIG VAUGHAN
Light Gage Steel Frame 3/19/2021 Approved CRAIG VAUGHAN
Drywall Nailing 3/23/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 4/19/2021 Approved CRAIG VAUGHAN
Final 4/19/2021 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 4/19/2021 Approved CRAIG VAUGHAN
Green Building Final 4/19/2021 Approved CRAIG VAUGHAN
HVAC-Final 4/19/2021 Approved CRAIG VAUGHAN
Light Gage Steel Frame 4/19/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 4/19/2021 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 4/19/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 4/19/2021 Approved CRAIG VAUGHAN
Final 4/30/2021 OK to Issue CofO CRAIG VAUGHAN