2243 W 29TH PL 90018

Certificate Information: 2243 W 29TH PL 90018

Application / Permit
19014-10000-01914
Plan Check / Job No.
B19LA07443
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to (E) detached garage and conversion of entire building into an Accessory Dwelling Unit per AB 494 and SB 229.
Permit Issued
Issued on 1/7/2020
Issuing Office
Metro
Current Status
Issued on 1/7/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/12/2019 APPLICANT
Assigned to Plan Check Engineer 4/12/2019 MICHAEL LOPEZ
Corrections Issued 4/12/2019 MICHAEL LOPEZ
Applicant returned to address corrections 12/18/2019 HELEN NGUYEN
Plan Check Approved 12/20/2019 KEVIN MORALES
Issued 1/7/2020 LADBS

Permit Application Clearance Information

Address approval Cleared 6/5/2019 ELAINE LEI
Construction near power lines Cleared 6/5/2019 OSCAR CASTRO
Roof/Waste drainage to street Cleared 6/5/2019 ELAINE LEI
Community Plan Implem. Overlay Cleared 11/14/2019 ANNA VAN
Eng Process Fee Ord 176,300 Cleared 11/14/2019 PAMELA TENEZA
Sewer availability Cleared 11/14/2019 PAMELA TENEZA
HPOZ Cleared 12/13/2019 LYDIA CHAPMAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/4/2020 Approved ROBERT MCDOWELL
Sewer 6/11/2020 Not Ready for Inspection ROBERT MCDOWELL
Underground Mechanical 6/11/2020 Partial Inspection ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 6/16/2020 Approved ROBERT MCDOWELL
Sewer 6/16/2020 Approved ROBERT MCDOWELL
Service/Power Release 7/10/2020 Not Ready for Inspection COREY HUPP
ELECTRICAL-Rough 7/29/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 7/29/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 7/29/2020 Corrections Issued ROBERT MCDOWELL
BUILDING-Rough-Frame 8/10/2020 Not Ready for Inspection ROBERT MCDOWELL
Green Building Rough 8/10/2020 Not Ready for Inspection ROBERT MCDOWELL
Insulation 8/10/2020 Not Ready for Inspection ROBERT MCDOWELL
METHANE-Rough 8/10/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 8/10/2020 Not Ready for Inspection ROBERT MCDOWELL
BUILDING-Rough-Frame 8/17/2020 Not Ready for Inspection ENRIQUE MIRELES
Green Building Rough 8/17/2020 Not Ready for Inspection ENRIQUE MIRELES
Insulation 8/17/2020 Corrections Issued ENRIQUE MIRELES
PLUMBING-Rough 8/17/2020 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 8/20/2020 Approved ROBERT MCDOWELL
Green Building Rough 8/20/2020 Approved ROBERT MCDOWELL
HVAC-Rough 8/20/2020 Approved ROBERT MCDOWELL
Insulation 8/20/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 8/20/2020 Approved ROBERT MCDOWELL
Drywall Nailing 8/27/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 8/27/2020 Partial Approval SABAS ALONSO
ELECTRICAL-Final 1/29/2021 Corrections Issued ROBERT MCDOWELL
Final 1/29/2021 Not Ready for Inspection ROBERT MCDOWELL
Footing/Foundation/Slab 1/29/2021 Approved ROBERT MCDOWELL
Green Building Final 1/29/2021 Approved ROBERT MCDOWELL
HVAC-Final 1/29/2021 Not Ready for Inspection ROBERT MCDOWELL
METHANE-Barrier 1/29/2021 Approved ROBERT MCDOWELL
METHANE-Subgrade 1/29/2021 Approved ROBERT MCDOWELL
PLUMBING-Final 1/29/2021 Corrections Issued ROBERT MCDOWELL
SGSOV-Seismic Gas S/O Valve 1/29/2021 SGSOV Not Ready ROBERT MCDOWELL
Smoke Detectors 1/29/2021 Approved ROBERT MCDOWELL