240 N BRANCH ST 90042

Certificate Information: 240 N BRANCH ST 90042

Application / Permit
19014-10000-01883
Plan Check / Job No.
B19LA07350
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
20' X 26' 7" 2-STORY ADDITION TO REAR AND INTERIOR REMODEL TO REMOVE LOAD-BEARING WALLS TO CREATE AN OPEN FLOOR PLAN TO (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 7/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2019 APPLICANT
Assigned to Plan Check Engineer 5/23/2019 GURUNATH NESARAJAH
Corrections Issued 5/31/2019 GURUNATH NESARAJAH
Quality Review Completed 5/31/2019 OMID HEDAYAT
Building Plans Picked Up 6/7/2019 APPLICANT
Green Plans Picked Up 8/26/2019 APPLICANT
Plan Check Approved 1/21/2020 GURUNATH NESARAJAH
Issued 7/14/2020 APPLICANT
CofO in Progress 4/19/2021 CRAIG VAUGHAN
Permit Finaled 5/1/2021 DEROLD HAUFF
Permit Finaled 5/1/2021 DEROLD HAUFF
CofO Issued 5/1/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/19/2019 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 7/19/2019 TODD MALAND
Highway dedication Cleared 7/19/2019 ADRIAN SANCHEZ
Sewer availability Cleared 7/19/2019 ADRIAN SANCHEZ
Green Code Cleared 11/20/2019 SARAH ABOULHOSN
Low Impact Development Cleared 11/20/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 12/30/2019 ERIK BEASLEY
GPI Written Notices Cleared 1/21/2020 GURUNATH NESARAJAH

Contact Information

Contractor Macco Construction Inc; Lic. No.: 793557-B 4833 SAN MARCOS PLACE      LOS ANGELES, CA 90042
Engineer Vega,, Cayetano Gonzalez; Lic. No.: C43117 9234 STAMPS AVE      DOWNEY, CA 90240

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/3/2020 Partial Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 8/10/2020 Approved CRAIG VAUGHAN
PLUMBING-Rough 8/19/2020 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 9/17/2020 Partial Approval RUBEN SALAS
ELECTRICAL-Rough 10/2/2020 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 10/2/2020 Partial Approval CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 10/2/2020 Corrections Issued CRAIG VAUGHAN
Wood Frame 10/2/2020 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 10/16/2020 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 10/16/2020 Approved CRAIG VAUGHAN
Green Building Rough 10/16/2020 Approved CRAIG VAUGHAN
HVAC-Rough 10/16/2020 Approved CRAIG VAUGHAN
Shower Pan 10/16/2020 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 11/2/2020 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 11/2/2020 Approved CRAIG VAUGHAN
Drywall Nailing 11/20/2020 Corrections Issued CRAIG VAUGHAN
Service/Power Release 12/9/2020 Corrections Issued CRAIG VAUGHAN
Service/Power Release 12/16/2020 Approved OSVALDO PARAMO
Drywall Nailing 2/16/2021 Approved CRAIG VAUGHAN
Final 2/16/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 2/16/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/16/2021 SGSOV Approved CRAIG VAUGHAN
Smoke Detectors 2/16/2021 Corrections Issued CRAIG VAUGHAN
Final 2/17/2021 Not Ready for Inspection CRAIG VAUGHAN
Green Building Final 2/17/2021 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 2/17/2021 Not Ready for Inspection CRAIG VAUGHAN
Final 4/7/2021 Corrections Issued CRAIG VAUGHAN
Green Building Final 4/7/2021 Corrections Issued CRAIG VAUGHAN
Smoke Detectors 4/7/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 4/16/2021 Approved CRAIG VAUGHAN
Final 4/16/2021 OK to Issue CofO CRAIG VAUGHAN
Green Building Final 4/16/2021 Approved CRAIG VAUGHAN
HVAC-Final 4/16/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 4/16/2021 Approved CRAIG VAUGHAN
Smoke Detectors 4/16/2021 Approved CRAIG VAUGHAN