445 S FIGUEROA ST 90071
Certificate Information: 445 S FIGUEROA ST 90071
- Application / Permit
- 19014-10000-01791
- Plan Check / Job No.
- B19LA07016
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- SECOND LEVEL ADDITION TO INCLUDE NEW 30' X 90' OPEN LATICE PATIO COVER AND TENANT IMPROVEMENT.
- Permit Issued
- Issued on 8/17/2020
- Issuing Office
- Current Status
- CofO Issued on 10/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 4/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | MICHAEL PEREZ |
| Corrections Issued | 4/29/2019 | MICHAEL PEREZ |
| Quality Review Completed | 5/3/2019 | QUAN NGHIEM |
| Building Plans Picked Up | 5/6/2019 | APPLICANT |
| Green Plans Picked Up | 7/31/2020 | APPLICANT |
| Applicant returned to address corrections | 8/12/2020 | MICHAEL PEREZ |
| Plan Check Approved | 8/13/2020 | MICHAEL PEREZ |
| Issued | 8/17/2020 | APPLICANT |
| CofO in Progress | 9/30/2021 | DANIEL COLLINS |
| Permit Finaled | 10/4/2021 | ERNESTO CORRAL |
| CofO Issued | 10/4/2021 | ERNESTO CORRAL |
| Permit Finaled | 10/4/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| "D" conditions | Cleared | 5/15/2019 | JOE LUCKEY |
| CPC | Cleared | 5/15/2019 | JOE LUCKEY |
| CPC | Cleared | 5/15/2019 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 5/15/2019 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 5/15/2019 | ELAINE LEI |
| Sewer availability | Cleared | 5/15/2019 | ELAINE LEI |
| ZA Case | Cleared | 5/15/2019 | JOE LUCKEY |
| Green Code | Cleared | 6/7/2019 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 6/12/2019 | SHINE LIN |
| Project located in CRA area | Cleared | 6/18/2019 | JIM URQUHART |
| Specific Plan | Cleared | 7/29/2019 | CHI DANG |
| Historic monument | Cleared | 12/3/2019 | LAMBERT GIESSINGER |
Contact Information
| Architect | Swartz,, David Louis; Lic. No.: C19729 | 1437 4TH STREET SUITE 400 SANTA MONICA, CA 90401 |
| Contractor | Swinerton Builders; Lic. No.: 92-B | 260 TOWNSEND ST 5TH FL-LEGAL SAN FRANCISCO, CA 94107 |
| Engineer | Youssef,, Nabih Fouad Guirg; Lic. No.: S2026 | 550 S HOPE ST STE 1700 LOS ANGELES, CA 90071 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 10/28/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 10/29/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 10/30/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/2/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/4/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 11/6/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 11/9/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 11/10/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 11/12/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 11/13/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 11/25/2020 | Conditional Approval | DANIEL COLLINS |
| Deputy Steel/Welding | 12/1/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 12/2/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 12/3/2020 | Conditional Approval | KATY RAMIREZ |
| Deputy Steel/Welding | 12/4/2020 | Conditional Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 12/23/2020 | Partial Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 1/5/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 1/5/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 1/6/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 1/6/2021 | Conditional Approval | DANIEL COLLINS |
| Light Gage Steel Frame | 1/6/2021 | Approved | DANIEL COLLINS |
| Structural Steel Frame | 1/6/2021 | Approved | DANIEL COLLINS |
| Insulation | 1/19/2021 | Approved | DANIEL COLLINS |
| Drywall Nailing | 1/25/2021 | Partial Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 1/28/2021 | Partial Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 2/4/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 2/5/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Fireproofing | 2/10/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Fireproofing | 2/11/2021 | Conditional Approval | DANIEL COLLINS |
| Deputy Fireproofing | 2/12/2021 | Conditional Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 2/17/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 2/18/2021 | Partial Approval | KATY RAMIREZ |
| Green Building Rough | 2/23/2021 | Approved | DANIEL COLLINS |
| Reinforced Concrete Frame | 2/23/2021 | Partial Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 3/22/2021 | Partial Approval | DANIEL COLLINS |
| Deputy Drilled-In Anchors | 4/1/2021 | Conditional Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 4/1/2021 | Conditional Approval | KATY RAMIREZ |
| Deputy Reinf. Concrete | 4/5/2021 | Conditional Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 4/8/2021 | Partial Approval | DANIEL COLLINS |
| Deputy Reinf. Concrete | 4/9/2021 | Conditional Approval | KATY RAMIREZ |
| Excavation/Setback/Form/Re-Bar | 4/15/2021 | Partial Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 4/22/2021 | Partial Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 4/27/2021 | Partial Approval | DANIEL COLLINS |
| Excavation/Setback/Form/Re-Bar | 5/5/2021 | Partial Approval | DANIEL COLLINS |
| Pre-Inspection | 5/24/2021 | Partial Inspection | DANIEL COLLINS |
| Final | 6/28/2021 | OK for TCO | DANIEL COLLINS |
| Footing/Foundation/Slab | 6/28/2021 | Approved | DANIEL COLLINS |
| Green Building Final | 6/28/2021 | Not Ready for Inspection | DANIEL COLLINS |
| Reinforced Concrete Frame | 6/28/2021 | Approved | DANIEL COLLINS |
| SGSOV-Seismic Gas S/O Valve | 6/28/2021 | SGSOV Approved | DANIEL COLLINS |
| Smoke Detectors | 6/28/2021 | Approved | DANIEL COLLINS |
| Deputy Reinf. Concrete | 8/24/2021 | Conditional Approval | TIMOTHY BUXTON |
| Final | 9/14/2021 | Conditional Approval | DANIEL COLLINS |
| Green Building Final | 9/14/2021 | Approved | DANIEL COLLINS |