1518 N CAHUENGA BLVD 90028
Certificate Information: 1518 N CAHUENGA BLVD 90028
- Application / Permit
- 19014-10000-01735
- Plan Check / Job No.
- B19LA06876
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Change of use from Laudry to Restauramt, Interior remodel of existing building, new dimising walls for restaurant layout. Provide new accessible restrooms. Roof remodel for roof deck restaurant.
- Permit Issued
- Issued on 11/12/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | SALVADOR QUINTANILLA |
| Corrections Issued | 4/30/2019 | SALVADOR QUINTANILLA |
| Quality Review Completed | 5/3/2019 | GARO TELMI |
| Building Plans Picked Up | 5/8/2019 | APPLICANT |
| Green Plans Picked Up | 5/8/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 5/13/2019 | APPLICANT |
| Applicant returned to address corrections | 7/16/2019 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 9/26/2019 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 10/7/2019 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 10/15/2019 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/1/2019 | SALVADOR QUINTANILLA |
| Plan Check Approved | 11/5/2019 | SALVADOR QUINTANILLA |
| Issued | 11/12/2019 | LADBS |
| CofO in Progress | 2/20/2024 | RAFAEL CORTES |
| CofO in Progress | 2/21/2024 | RAFAEL ESPINOZA |
| CofO Issued | 2/22/2024 | ADAM BURGESS |
| Permit Finaled | 2/22/2024 | ADAM BURGESS |
Permit Application Clearance Information
| Green Code | Cleared | 7/19/2019 | COLIN LOREDO |
| Low Impact Development | Cleared | 7/23/2019 | MITESH PATEL |
| Project located in CRA area | Cleared | 8/22/2019 | JIM URQUHART |
| Roof/Waste drainage to street | Cleared | 8/22/2019 | JEANIE LAM |
| "D" conditions | Cleared | 8/23/2019 | STEVEN WECHSLER |
| ZI | Cleared | 8/23/2019 | STEVEN WECHSLER |
| Fire Marshall Fire Life Safety | Cleared | 9/13/2019 | PEJMAN NOORI |
| Food Service Establishment | Cleared | 9/26/2019 | KENNETH BROWNE |
| Food establishment approval | Cleared | 9/26/2019 | LACDHS APPROVED |
| Bicycle Parking | Cleared | 10/7/2019 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2019 | ROBYN STEELE |
| Sewer availability | Cleared | 10/23/2019 | ROBYN STEELE |
| Miscellaneous | Cleared | 10/28/2019 | JOE LUCKEY |
| ZA Case | Cleared | 10/28/2019 | JOE LUCKEY |
| Bicycle Parking | Cleared | 11/4/2019 | EDUARDO HERMOSO |
| DAS Clearance | Cleared | 11/4/2019 | SHINE LIN |
Contact Information
| Contractor | Calasia Construction Inc; Lic. No.: 938255-B | 3050 FLETCHER DRIVE LOS ANGELES, CA 90065 |
| Engineer | Nishi,, Thomas Yoshimasa; Lic. No.: S4030 | 1615 BUCKINGHAM RD LOS ANGELES, CA 90019 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/13/2019 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 11/21/2019 | Approved | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 2/19/2020 | Partial Approval | EDWIN GREGORYONA |
| Excavation/Setback/Form/Re-Bar | 2/20/2020 | Partial Approval | EDWIN GREGORYONA |
| Insulation | 3/10/2020 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 3/17/2020 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 4/1/2020 | Partial Approval | EDWIN GREGORYONA |
| Structural Steel Frame | 4/1/2020 | Partial Inspection | EDWIN GREGORYONA |
| Wood Frame | 4/1/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 4/14/2020 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Not Ready for Inspection | EDWIN GREGORYONA |
| Light Gage Steel Frame | 4/27/2020 | Partial Approval | EDWIN GREGORYONA |
| Structural Steel Frame | 4/27/2020 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 4/27/2020 | Partial Approval | EDWIN GREGORYONA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2020 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 5/5/2020 | Partial Inspection | EDWIN GREGORYONA |
| Piling/Pier/Caisson | 5/5/2020 | Not Ready for Inspection | EDWIN GREGORYONA |
| Light Gage Steel Frame | 6/5/2020 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 6/5/2020 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 6/19/2020 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 6/24/2020 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 8/21/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Steel/Welding | 11/6/2020 | Partial Approval | EDWIN GREGORYONA |
| Wood Frame | 12/3/2020 | Partial Approval | LANNY MERRICK |
| Interior/Exterior Lathing | 1/28/2021 | Partial Inspection | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 2/4/2021 | Partial Approval | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 2/23/2021 | Partial Approval | TIMOTHY BUXTON |
| Interior/Exterior Lathing | 8/13/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Interior/Exterior Lathing | 8/17/2021 | Approved | RUSSELL BONVOULOIR |
| Green Building Final | 10/26/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Final | 11/10/2021 | Partial Inspection | SORIN CIRSTOIU |
| Green Building Final | 11/10/2021 | Approved | SORIN CIRSTOIU |
| Special/Order Compliance | 11/16/2021 | Partial Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 12/1/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Final | 12/3/2021 | Partial Inspection | SORIN CIRSTOIU |
| Footing/Foundation/Slab | 12/3/2021 | Approved | SORIN CIRSTOIU |
| Green Building Rough | 12/3/2021 | Approved | SORIN CIRSTOIU |
| Reinforced Masonry Frame | 12/3/2021 | Approved | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Approved | SORIN CIRSTOIU |
| Smoke Detectors | 12/3/2021 | Approved | SORIN CIRSTOIU |
| Final | 12/8/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Special/Order Compliance | 1/26/2024 | Corrections Issued | RAFAEL CORTES |
| Special/Order Compliance | 2/1/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 2/15/2024 | Conditional Approval | RAFAEL CORTES |
| Final | 2/20/2024 | OK to Issue CofO | RAFAEL CORTES |