16717 W SUNSET BLVD 1 90272
Certificate Information: 16717 W SUNSET BLVD 1 90272
- Application / Permit
- 19014-10000-01721
- Plan Check / Job No.
- B19LA06840
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY 378 SQFT. ADDITION TO AN EXISTING SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 1/18/2022
- Issuing Office
- Current Status
- CofO Issued on 2/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2019 | RACHEL BEYENE |
| Green Plans Picked Up | 5/10/2019 | APPLICANT |
| Corrections Issued | 5/15/2019 | RACHEL BEYENE |
| Quality Review Completed | 5/17/2019 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 3/11/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 3/12/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 8/7/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 11/13/2020 | RACHEL BEYENE |
| Plan Check Approved | 12/17/2021 | RAHEL BEYENE |
| Issued | 1/18/2022 | APPLICANT |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| CofO in Progress | 12/20/2022 | BRENDAN LOONEY |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
| CofO Issued | 2/11/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/11/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 7/29/2019 | ANNA VAN |
| ZA Case | Cleared | 7/29/2019 | ANNA VAN |
| Coastal Zone | Cleared | 9/26/2019 | SARAHI ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 11/22/2019 | JOHN CONNEALLY |
| Sewer availability | Cleared | 11/22/2019 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 11/25/2019 | PATRICK MISCHLICH |
| Low Impact Development | Cleared | 1/2/2020 | JORGE MEJIA LEMUS |
| GPI Written Notices | Cleared | 8/7/2020 | RAHEL BEYENE |
| Roof/Waste drainage to street | Cleared | 10/15/2021 | DINAH GARIN |
| Green Code | Cleared | 12/17/2021 | RAHEL BEYENE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hazrati,, Kayvan Naghib; Lic. No.: C60556 | 465 PUERTO DEL MAR PACIFIC PALISADES, CA 90272 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/11/2022 | Not Ready for Inspection | ANDREW NAVE |
| Drywall Nailing | 2/11/2022 | Not Ready for Inspection | ANDREW NAVE |
| Final | 2/11/2022 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 2/11/2022 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Final | 2/11/2022 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Rough | 2/11/2022 | Not Ready for Inspection | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 2/11/2022 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 2/11/2022 | Not Ready for Inspection | ANDREW NAVE |
| BUILDING-Rough-Frame | 3/1/2022 | Partial Inspection | ANDREW NAVE |
| Drywall Nailing | 3/1/2022 | Partial Inspection | ANDREW NAVE |
| ELECTRICAL-Final | 3/1/2022 | Partial Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 3/1/2022 | Partial Inspection | ANDREW NAVE |
| Green Building Final | 3/1/2022 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Rough | 3/1/2022 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Final | 3/1/2022 | Partial Inspection | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 3/1/2022 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 3/1/2022 | Corrections Issued | ANDREW NAVE |
| Wood Frame | 3/1/2022 | Partial Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 4/1/2022 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/11/2022 | Corrections Issued | ANDREW NAVE |
| Deputy Drilled-In Anchors | 4/13/2022 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 4/14/2022 | Partial Approval | ANDREW NAVE |
| Deputy Drilled-In Anchors | 4/19/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/19/2022 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 4/22/2022 | Approved | ANDREW NAVE |
| Deputy Drilled-In Anchors | 4/29/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2022 | Partial Approval | ANDREW NAVE |
| Insulation | 4/29/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 5/2/2022 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Approved | ANDREW NAVE |
| HVAC-Rough | 5/2/2022 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 5/4/2022 | Approved | ANDREW NAVE |
| Smoke Detectors | 5/4/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 11/16/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 11/16/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Final | 11/16/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 11/16/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 11/16/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 11/16/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 12/7/2022 | No Access for Inspection | BRENDAN LOONEY |
| Drywall Nailing | 12/7/2022 | No Access for Inspection | BRENDAN LOONEY |
| Final | 12/7/2022 | No Access for Inspection | BRENDAN LOONEY |
| Green Building Final | 12/7/2022 | No Access for Inspection | BRENDAN LOONEY |
| Green Building Rough | 12/7/2022 | No Access for Inspection | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 12/7/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 12/15/2022 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 12/15/2022 | Approved | BRENDAN LOONEY |
| Final | 12/15/2022 | OK to Issue CofO | BRENDAN LOONEY |
| Green Building Final | 12/15/2022 | Approved | BRENDAN LOONEY |
| Green Building Rough | 12/15/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | BRENDAN LOONEY |