19216 W SINGING HILLS DR 91326

Certificate Information: 19216 W SINGING HILLS DR 91326

Application / Permit
19014-10000-01694
Plan Check / Job No.
B19LA06732
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Golf Club
Work Description
INTERIOR TI OF EXISTING COUNTRY CLUB, NEW ACCESSIBLE EXTERIOR VERTICAL LIFT, MILLWORK, FINISHES,NON-BEARING PARTITIONS, RESTROOMS REMODEL (E) SHADE STRUCTURE.
Permit Issued
Issued on 12/14/2020
Issuing Office
Current Status
Issued on 12/14/2020

Permit Application Status History

Submitted 4/16/2019 APPLICANT
Assigned to Plan Check Engineer 5/2/2019 HERNAN ARREOLA
Green Plans Picked Up 5/3/2019 APPLICANT
Disabled Access Plans Picked Up 5/7/2019 APPLICANT
Corrections Issued 5/15/2019 HERNAN ARREOLA
Quality Review Completed 5/28/2019 BILL STUTSMAN
Building Plans Picked Up 5/29/2019 APPLICANT
Applicant returned to address corrections 11/4/2019 HERNAN ARREOLA
Applicant returned to address corrections 11/18/2019 HERNAN ARREOLA
Plan Check Approved 3/11/2020 HERNAN ARREOLA
Issued 12/14/2020 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 8/6/2019 SARAHI ORTEGA
ZA Case Cleared 8/6/2019 SARAHI ORTEGA
ZA Case Cleared 8/6/2019 SARAHI ORTEGA
ZA Case Cleared 8/6/2019 SARAHI ORTEGA
Green Code Cleared 11/19/2019 COLIN LOREDO
DAS Clearance Cleared 2/3/2020 HERNAN ARREOLA
Grading Pre-Inspection Cleared 2/6/2020 KIRK LINKLATER

Contact Information

Architect Ternasky,, Frank S; Lic. No.: C25718 2702 COWLEY WAY      SAN DIEGO, CA 92110
Engineer Schell,, William Francis; Lic. No.: S4529 3969 FIRST AVE 2ND FLOOR   GSSI ENGINEERS    SAN DIEGO, CA 92103

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2021 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 2/8/2021 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 2/9/2021 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 2/10/2021 Conditional Approval JEFFREY FULTON
Wood Frame 3/25/2021 Partial Inspection JEFFREY FULTON
Wood Frame 4/27/2021 Partial Inspection JEFFREY FULTON
Pre-Inspection 4/30/2021 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 5/6/2021 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 5/13/2021 Conditional Approval JEFFREY FULTON
Masonry Wall/Backfill 5/13/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 5/24/2021 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 6/3/2021 Conditional Approval JEFFREY FULTON
Drywall Nailing 6/18/2021 Partial Inspection JEFFREY FULTON
Deputy Steel/Welding 6/21/2021 Conditional Approval JEFFREY FULTON
Deputy Steel/Welding 6/25/2021 Conditional Approval JEFFREY FULTON
Structural Steel Frame 7/2/2021 Corrections Issued JEFFREY FULTON
Deputy Steel/Welding 7/7/2021 Conditional Approval JEFFREY FULTON
Structural Steel Frame 7/7/2021 Partial Inspection JEFFREY FULTON
Special/Order Compliance 7/16/2021 Partial Inspection JEFFREY FULTON
Insulation 9/20/2021 Corrections Issued JEFFREY FULTON
Wood Frame 9/22/2021 Corrections Issued JEFFREY FULTON
Wood Frame 10/1/2021 No Access for Inspection ROBERT DAVIS
Wood Frame 10/4/2021 Partial Approval ROBERT DAVIS
Insulation 10/6/2021 Partial Approval ROBERT DAVIS
Drywall Nailing 10/8/2021 Partial Approval DANNY RODRIGUEZ
Drywall Nailing 10/15/2021 Partial Inspection JEFFREY FULTON
Drywall Nailing 10/19/2021 Partial Inspection JEFFREY FULTON
Wood Frame 11/9/2021 Not Ready for Inspection JEFFREY FULTON
Wood Frame 11/15/2021 Approved JONATHAN QUACH
Drywall Nailing 11/19/2021 Partial Inspection JEFFREY FULTON
Final 2/1/2022 Corrections Issued JEFFREY FULTON
Green Building Final 2/1/2022 Partial Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 2/1/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 2/1/2022 Not Ready for Inspection JEFFREY FULTON
Final 2/4/2022 Not Ready for Inspection JEFFREY FULTON
Green Building Final 2/4/2022 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 2/4/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 2/4/2022 Not Ready for Inspection JEFFREY FULTON
Insulation 2/7/2022 No Access for Inspection JEFFREY FULTON
Final 2/8/2022 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 2/8/2022 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 2/8/2022 Approved JEFFREY FULTON
Final 2/14/2022 Corrections Issued JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 2/14/2022 SGSOV Not Ready JEFFREY FULTON