24 E DUDLEY AVE 90291
Certificate Information: 24 E DUDLEY AVE 90291
- Application / Permit
- 19014-10000-01637
- Plan Check / Job No.
- B19LA06526
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED REMODEL AND 2-STORY ADDITION TO SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 10/5/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | SINA KHOSRAVI |
| Green Plans Picked Up | 4/19/2019 | APPLICANT |
| Corrections Issued | 4/25/2019 | SINA KHOSRAVI |
| Quality Review Completed | 5/2/2019 | FELIX FIGUEROA |
| Applicant returned to address corrections | 6/25/2019 | SINA KHOSRAVI |
| Building Plans Picked Up | 8/6/2019 | APPLICANT |
| Plan Check Approved | 8/3/2020 | SINA KHOSRAVI |
| Issued | 10/5/2020 | APPLICANT |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
| CofO Issued | 9/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 5/30/2019 | STEVEN HOFSTAD |
| Green Code | Cleared | 6/25/2019 | KHEDER ALRAZAA |
| Hydrant and Access approval | Cleared | 7/9/2019 | GILBERT URREA |
| Coastal Zone | Cleared | 6/18/2020 | JASON CHAN |
| Specific Plan | Cleared | 6/18/2020 | JASON CHAN |
| ZI | Cleared | 6/18/2020 | JASON CHAN |
Contact Information
| Architect | Ginter,, Gregory Hopkins; Lic. No.: C30686 | 1525 PEARL STREET SANTA MONICA, CA 90405 |
| Contractor | Owner-Builder | , |
| Engineer | Trevellin,, Maurizio; Lic. No.: C71368 | 707 ASHLAND AVE 2 SANTA MONICA, CA 90405 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/22/2023 | Partial Approval | EVAN COOPER |
| METHANE-Barrier | 6/22/2023 | Approved | EVAN COOPER |
| METHANE-Subgrade | 6/22/2023 | Approved | EVAN COOPER |
| Deputy Reinf. Concrete | 7/13/2023 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 7/31/2023 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 8/22/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/30/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 10/30/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Deputy Reinf. Concrete | 11/1/2023 | Conditional Approval | HERBERT GIRON |
| PLUMBING-Rough | 11/30/2023 | Partial Approval | HERBERT GIRON |
| Sewer | 7/12/2024 | Approved | HERBERT GIRON |
| Underground Mechanical | 7/12/2024 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 7/16/2024 | Corrections Issued | STEPHANIE SWANSON |
| Underground Mechanical | 7/17/2024 | Not Ready for Inspection | HERBERT GIRON |
| Gas Test | 6/10/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/1/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/1/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 7/1/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/10/2025 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 9/10/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 9/10/2025 | Approved | JESUS RODRIGUEZ |
| Final | 9/10/2025 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Final | 9/10/2025 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 9/10/2025 | Approved | JESUS RODRIGUEZ |
| METHANE-Final | 9/10/2025 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 9/10/2025 | Approved | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 9/10/2025 | Approved | JESUS RODRIGUEZ |